Professional Documents
Culture Documents
4
TAKASAGO THERMAL ENGINEERING CO., LTD RISK ASSESSMENT FORM
RISK ASSESSMENT
Company: Takasago Thermal Engineering RA Leader: Mr Yan Naing Htoo Approved By: Document No.
Process: Work at height activities RA Members 1: Mr Hein Ko Ko Signature:
Activity Location: RA Members 2: Mr Aung Paing Khant
Original Assessment Date: 09-Feb-2021 RA Members 3: Mr Thaw Zin Name: Mr.Tsuyoshi Miura Revision No.
Last Review Date: 09-Feb-2021 RA Members 4: Mr Myo Khant Kyaw Designation: Project Manager
0
Next Review Date: 09-Feb-2021 RA Members 5: Mr Wai Yan Tun Date: 09-Feb-2021
Major (4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Negligible (1) 1 2 3 4 5
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
Control
Possible Accident / Ill Initial Risk Residual Risk Action by:
Additional Risk Control Implement
No Activity Hazard Health & Persons-at- Existing Risk Control Index Index Designation
Measures ed
Risk (Follow up-date)
S L R S L R Yes / No
-Working at -Falling from -Fatality and serious -Must be worn full body harness 4 3 12 -Precheck before using 3 1 3 -Site Engineer Yes
height height injury during working at height body harness and lanyard -Supervisor
-Lanyard anchor point should be -Opening hatch must be -Labor
above the shoulder covered or barricade
-Anchor point should be strong
enough to hang 5000 pounds and -Life line have to provide
lanyard capacity should be 3000 if necessary
02 pounds
-Using -Body Injuries -The circumference of -Barricade the area and putting 4 3 12 -Checklist 3 1 3 -Site Engineer Yes
Boom lift/ -Falling hazard the lift often significant working at height signage -Signage -Supervisor
Scissor lift and tools can easily fall -Must be worn proper PPE (Body -Operator
-Properties harness etc.) -Short briefing prior to -Signal man
machine damaged from the platform and work.
Works serious injury to anyone -The circumference of the boom lift -Worker
-Environmental who may be standing is clear of any personnel while the -PTW system
hazard. below. boom lift is in use. -Signal man
03
-Must be worn proper PPE.
-Do not lift over the weight limit.
-Machine operator must be trained
person who knowledge operation.
-Avoid windy condition when the
boom lift is extremely high.
Major (4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Negligible (1) 1 2 3 4 5
Table 1 - Severity categories and description
Likelihoo
d Rare Remote Occasional Frequent
Almost Certain (5)
Severity (1) (2) (3) (4)
Catastrophic (5) 5 10 15 20 25
Major (4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Negligible (1) 1 2 3 4 5
Acceptability of
Risk Level Recommended actions
risk
Low Risk No additional risk control measures may be needed. However, frequent review may be needed to
Acceptable
(1-3) ensure that the risk level assigned is accurate and does not increase over time.
A careful evaluation of the hazards should be carried out to ensure that the risk level is reduced to as
low as is practicable within a defined time period.
Medium Risk Moderately
(4-12) acceptable Interim risk control measures, such as administrative controls, may be implemented.
High Risk level must be reduced to at least Medium Risk before work commences.
There should not be any interim risk control measures and risk control measures should not be overly
High Risk
Not acceptable dependent on personal protective equipment or appliances. If need be, the hazard should be
(15-25)
eliminated before work commences.