Activity Location Date* Time
Inspection for MEP Works in the slab
Ground Floor H/L 14/11/2022
for Attic Slab Area
attached Sketch/shop drawing attached method of statement material approval submittal
Contractor's undertaking
I UNDERTAKE FULL RESPONSIBILITY OF HAVING EXECUTED THE SUBJECT
WORK EXACTLY IN ACCORDANCE WITH THE LATEST APPROVED DRAWINGS,
SPECIFICATIONS AND METHOD STATEMENT
Checked Received
Consultant's Contractor's
sign & date sign & date
* Inspections requests must reach the consultant at least 24 hours in advance
1 2 3 4
1840
725 835 280
11 12 13 14 15 16 17 18
+0.85
INT. LVL.
AD-02
TEL.
A +1.00
F.F.LVL.
CU-TEL
SPEED HUMP
10
+0.70 +0.70
MS
DRIVEWAY LVL. DRIVEWAY LVL.
795
50% OF THE PAVING SPACE'S SHOULD 50% OF THE PAVING SPACE'S SHOULD
SPEED HUMP
HAVE SOLAR REFLECTANCE INDEX (SRI) HAVE SOLAR REFLECTANCE INDEX (SRI)
VALUE OF 29 OR ABOVE VALUE OF 29 OR ABOVE
09
MS
B
08
23 22 21
24
SPEED HUMP SPEED HUMP
440
+0.70
DRIVEWAY LVL.
20 19
07
CU-ELE
CU-GAR CU-W.MAN
C CU-GF 01
ALD-01
GARB. R. +0.85
+0.95
INT. LVL.
F.F.LVL.
280
06
AD-01
2865
MS
MS
D
+0.60 W.M W05
+0.65
INT. LVL.
DRIVEWAY LVL.
OPEN SPACE
05 GREEN
BICYCLE PARKING
LIFT LOBBY
+0.65
GR.F.LVL. AD-04
PUMP R. +0.65
INT. LVL.
SC +0.75
04 F.F.LVL.
10
11 09
810
12 08
SLOP 2 %
13 07
14 06
+0.60
15 05 AD-03
INT. LVL.
50% OF THE PAVING SPACE'S SHOULD 16 04 ELEC. WATER TANK
HAVE SOLAR REFLECTANCE INDEX (SRI) 17 03 +0.75
VALUE OF 29 OR ABOVE 18 02
S.S.L & F.F.L
19 01
30 STEPS X 15.83cm
20
3.5 %
03 +0.50
SCGR.F.LVL.
E
SLOP
SD-01
MS
+0.50
GR.F.LVL.
02 LOBBY
+0.65 TRANSFORMER GREEN
GR.F.LVL.
AREA :32.33 SQ/M LW01
F.F.C
RCC
GF-02
+0.45
S.S.L & F.F.L
540
GAS PIPES
01 ENTRANCE
+0.65
GR.F.LVL.
PROPOSED GATE LVL. +0.30
PROPOSED GATE LVL. +0.30
DMD GATE LVL. +31.62
Gate barrier
ATTIC SLAB
ALD-02
F
PROPOSED GATE LVL. +0.35
DMD GATE LVL. +31.67
01
02
03
NO.
Notes:-
SC
MS
MS
MS
DATE:
CAD BY :
DUBAI
CLIENT
SYMBOL
EMIRATES
Signature:
DATE
PROJECT
C215101
LEGEND:
REVISION:
00 10.11.2022
PROJECT NO.
CHECKED BY :
B
A
D
C
CONSULTANT
DRAWING TITLE
MEP CONTRACTOR
MAIN CONTRACTOR
Rejected
Abdul Gafoor
DUBAI
Eng. SWEED
10 Nov 2022
LOCATION
REVISED
DESCRIPTION
DWG. REF.NO.
CONSULTANT'S TABLE
SIGN:
SIGN:
COMPANY
SCALE:
Approved As Submitted
Date:
AL MARZOOQI
SHOP DRAWING
AAQ/SD/GF/SM-01
PROPOSED G+4+R
AUTO-BUILD CONT.
PLOT NO.
NTS@A2
6430288
GROUND FLOOR PLAN H/L
Dwg. Ref G:\Abdul Gafoor System Files\2022\1) Job In Hand\5) G+4+R (Cubic)\
00
STATUS
REV.
AZIZ ALI MOHAMMAD HASAN
All Dimensions are in mm, Otherwise Indicated