You are on page 1of 7

DORCHESTER HOTEL & RESIDENCES -T&C EXECUTIVE SUMMARY

Cumulative Actual Cumulative Actual Progress (Consultant Approval)


Weekly Actual
System Weightage
Physical Progress (Approved Progress)
Overall Progress Residential Tower Podium Area Hotel Tower
(Sutton)

LV 20% 85.62% 83.17% 92.53% 84.38% 78.80% 0.63%

HVAC 25% 83.17% 79.36% 81.49% 78.43% 87.71% 0.13%

Plumbing 15% 60.67% 57.79% 51.25% 56.68% 56.84% 4.26%

Fire Fighting 10% 87.79% 81.92% 95.96% 79.56% 97.09% 0.00%

ELV 30% 67.73% 64.50% 71.96% 58.20% 67.60% 0.03%

Overall T&C Progress 100% 76.11% 72.68% 77.75% 70.40% 76.20% 0.81%
P Planned CIR

DORCHESTER HOTEL & RESIDENCES S Sutton Approved


Weekly progressed Activity
Commissioning Activity Summary Report
A Consultant Approved
TC T&C Approved
KPI SUMMARY Date: 19-09-23
OVERALL RESIDENTIAL PODIUM AREA HOTEL

Cumulative Cumulative Cumulative Cumulative Cumulative


Sep-23 Sep-23
System Equipment Type Activity Witnessed Approved Pending Quantity Approved Approved Approved Week Ending Week Ending
Total Quantity Type
Quantity Quantity For Approval
Total Quantity
Quantity
Total Quantity
Quantity
Total Quantity
Quantity (19/09/2023) (26/09/2023) Comments
(Sutton/T&C) (Consultant) (Consultant) (Consultant) (Consultant) P S A P S A

SAT 9 Panels 9 9 0 ----- ----- 9 9 ----- -----

MDB/EMDB Cold Test 9 Panels 9 9 0 ----- ----- 9 9 ----- -----


EMDB PENDING ASSOCIATED WITH GENERATOR COMMISSIONING
Live & Functional test 9 Panels 9 8 1 ----- ----- 9 8 ----- ----- 1

Cold Test 73 Panels 73 73 0 25 25 23 23 25 25


SMDB/ESMDB
Live & Functional test 73 Panels 73 71 2 25 25 23 23 25 23 1

SAT 30 Panels 29 29 1 5 4 20 20 5 5

MCC/EMCC Cold Test 30 Panels 30 30 0 5 5 20 20 5 5

Live & Functional Test 30 Panels 26 24 6 5 4 20 17 5 3 1

SAT 3 Panels 3 3 0 ----- ----- 3 3 ----- -----

ACB Control Panel Cold Test 3 Panels 3 3 0 ----- ----- 3 3 ----- -----

Live Test 3 Panels 3 0 3 ----- ----- 3 0 ----- ----- 3

Cold Test 5 Unit's 5 5 0 ----- ----- 5 5 ----- -----


Busbar
Live Test 5 Unit's 5 5 0 ----- ----- 5 5 ----- -----

SAT 6 Panels 6 6 0 ----- ----- 6 6 ----- -----

Capacitor Bank Cold Test 6 Panels 6 6 0 ----- ----- 6 6 ----- -----

Live Test 6 Panels 6 6 0 ----- ----- 6 6 ----- -----

LV SAT 4 Panels 4 4 0 1 1 2 2 1 1

ATS Cold Test 4 Panels 4 4 0 1 1 2 2 1 0

Live Test 4 Panels 1 0 4 1 0 2 0 1 0 1

Cold Test 363 Panels 362 350 13 74 71 44 40 245 239


DB
Live Test 363 Panels 80 76 287 74 58 44 15 245 3 10 8

Cold Test 65 Panels 58 49 16 7 7 35 25 23 17 5


Control Panel
Live & Functional Test 65 Panels 52 43 22 7 7 35 20 23 17 5 4

Pit Resistance Test 48 Pits 48 48 0 ----- ----- 48 48 ----- -----


Earthing
Cable Continuity Test 48 Pits 46 46 2 ----- ----- 48 46 ----- -----

Pit Resistance Test 2 Pits 2 2 0 ----- ----- 2 2 ----- -----


Lightning Protection
Cable Continuity Test 2 Pits 2 0 2 ----- ----- 2 0 ----- -----

Cable Cold Test 1 Unit's 1 1 0 ----- ----- 1 1 ----- -----

Generator Load Bank Test 1 Unit's 0 0 1 ----- ----- 1 0 ----- -----

Functional Test 1 Unit's 0 0 1 ----- ----- 1 0 ----- -----

Cold Test 3 Unit's 3 3 0 ----- ----- 3 3 ----- -----

UPS Load Bank Test 3 Unit's 0 0 3 ----- ----- 3 0 ----- -----

Functional Test 3 Unit's 0 0 3 ----- ----- 3 0 ----- -----

Cable Test 49 Panels 43 40 9 13 13 21 14 15 13

Lighting Control Functional Test 49 Panels 12 12 37 13 9 21 0 15 3 3 3

Head End Testing 1 System 0 0 1 ----- ----- 1 0 ----- -----

Cable Test 225 Panels 225 225 0 ----- ----- ----- ----- 225 225

GRMS Functional Test 225 Panels 0 0 225 ----- ----- ----- ----- 225 0

Head End Test 1 System 0 0 1 ----- ----- ----- ----- 1 0

IPTV/SMATV Functional test 225 Rooms 0 0 225 ----- ----- ----- ----- 225 0
P Planned CIR

DORCHESTER HOTEL & RESIDENCES S Sutton Approved


Weekly progressed Activity
Commissioning Activity Summary Report
A Consultant Approved
TC T&C Approved
KPI SUMMARY Date: 19-09-23
OVERALL RESIDENTIAL PODIUM AREA HOTEL

Cumulative Cumulative Cumulative Cumulative Cumulative


Sep-23 Sep-23
System Equipment Type Activity Witnessed Approved Pending Quantity Approved Approved Approved Week Ending Week Ending
Total Quantity Type
Quantity Quantity For Approval
Total Quantity
Quantity
Total Quantity
Quantity
Total Quantity
Quantity (19/09/2023) (26/09/2023) Comments
IP Telephone Functional test 40 Level's 0 0 40 1 0 16 0 23 0

Digital Signage Functional Test 7 Units 7 7 0 ----- ----- 7 7 ----- -----

AV Systems Cold Test (Common Area) 15 Loops 15 15 0 ----- ----- 15 15 ----- -----
AV - Common Area
AV Systems Functional Test 15 Loops 0 0 15 ----- ----- 15 0 ----- -----

CCTV Cable Test 978 Cameras 805 802 176 179 168 491 356 306 277
Connectivity only tested as agreed before in residential tower.Not witnessed by
CCTV CCTV Functional Test (Connectivity only) 978 Cameras 930 930 48 179 176 491 249 304 299 consultant.

CCTV Head End testing (With FOV Test) 978 System 50 0 978 179 0 491 0 306 0 50
Some IDF's are partially only submitted, cables with length issues to be submitted
Fluke Test (IDF) 29 Racks 29 29 0 4 4 11 11 14 13 seperately.

Fluke Test (Guest Rooms) 225 HCC's 222 222 3 ----- ----- ----- ----- 225 222
SCS
Fibre Optic Cable Test 58 Racks 58 58 0 8 8 22 22 28 28

Active Components Functional Test 1 Network 0 0 1 ----- ----- 1 0 ----- -----

Wi-Fi Functional Test 29 Racks 8 0 29 4 0 11 0 14 0

Cable Test 1 Panel 0 0 1 ----- ----- 1 0 ----- -----


LPG Leak Detection
Functional Test 1 Panel 0 0 1 ----- ----- 1 0 ----- -----

Cable Test 111 Loops 74 74 37 11 11 82 45 18 18

BGM Functional Test 111 Loops 0 0 111 11 0 82 0 18 0


ELV
Head End Testing 1 System 0 0 1 ----- ----- 1 0 ----- -----

Cable Test 13 Unit's 12 11 2 ----- ----- 6 6 7 5


Disabled Toilet Alarm
Functional Test 13 Unit's 12 11 2 ----- ----- 6 6 7 5

Cable Test 2 Unit's 0 0 2 ----- ----- 2 0 ----- -----


Gate Barriers
Functional Test 2 Unit's 0 0 2 ----- ----- 2 0 ----- -----

Intercom Cable Test 58 Unit's 54 54 4 51 45 7 0 ----- ----- Cable testing only included in SIS scope.

Cable Test 145 Door's 36 36 109 8 0 121 36 16 0

Access Control Functional Test 145 Door's 36 36 109 8 0 121 36 16 0

Head End testing 1 System 0 0 1 ----- ----- 1 0 ----- -----

Cable test 35 Panels 34 33 2 3 3 25 24 7 6

BMS Functional test 35 Panels 22 16 19 3 2 25 12 7 2 2

BMS Head end test. 1 System 0 0 1 ----- ----- 1 0 ----- -----

Fire Alarm Cable Test 47 Loops 47 47 0 16 16 11 11 20 20

Fire Alarm Device Address Test 47 Loops 41 35 12 16 15 11 4 20 16


Fire Alarm
Fire Alarm Functional Test 5 Panels 0 0 5 ----- ----- 5 0 ----- -----

Cause & Effect Testing 1 System 0 0 1 ----- ----- 1 0 ----- -----

Cable Test 80 Loops 62 60 20 31 30 20 7 29 23


Voice Evacuation
Functional Test 80 Loops 54 53 27 31 27 20 6 29 20

Cable Test 12 Circuits 12 12 0 3 3 5 5 4 4


Fire Telephone
Functional Test 12 Circuits 12 12 0 3 3 5 5 4 4

Cable Test 177 Circuits 177 177 0 33 33 85 85 59 59

CBS Autonomy/ LUX Level Test 10 Circuits 0 0 10 2 0 4 0 4 0


1 PANEL PARTIALLY APPROVED IN HOTEL
Functional Test 10 Panels 8 4 6 2 1 4 0 4 3
P Planned CIR

DORCHESTER HOTEL & RESIDENCES S Sutton Approved


Weekly progressed Activity
Commissioning Activity Summary Report
A Consultant Approved
TC T&C Approved
KPI SUMMARY Date: 19-09-23
OVERALL RESIDENTIAL PODIUM AREA HOTEL

Cumulative Cumulative Cumulative Cumulative Cumulative


Sep-23 Sep-23
System Equipment Type Activity Witnessed Approved Pending Quantity Approved Approved Approved Week Ending Week Ending
Total Quantity Type
Quantity Quantity For Approval
Total Quantity
Quantity
Total Quantity
Quantity
Total Quantity
Quantity (19/09/2023) (26/09/2023) Comments
Pump Alignment Test 6 Pumps 6 6 0 ----- ----- 6 6 ----- -----
Fire Pump
Functional Test 6 Pumps 6 6 0 ----- ----- 6 6 ----- -----

Fire Hose Cabinet Fire Hose Reel & Landing valve Functional 228 Cabinets 228 228 0 61 61 108 108 58 58

Zone Control Valve ZCV Functional Test 73 Unit's 64 54 19 27 22 21 11 25 21 1

Supervisory Valve Supervisory Valve Functional Test 13 Unit's 13 13 0 ----- ----- 7 6 6 6


Fire Fighting
Room Integrity Test 10 Rooms 10 6 4 ----- ----- 10 6 ----- -----

FM200 Pre-Commissioning 10 Panel's 6 6 4 ----- ----- 10 5 ----- -----

Functional Test 10 Panel's 6 6 4 ----- ----- 10 5 ----- -----

Pre-Commissioning 1 Panel 0 0 1 ----- ----- 1 0 ----- -----


Foam Deluge
Functional Test 1 Panel 0 0 1 ----- ----- 1 0 ----- -----

Functional Test 553 Unit's 553 553 0 120 120 151 151 282 282
Motorized Dampers
Fire Interface Test 544 Unit's 0 0 0 120 0 142 0 282 0

Fire Damper Drop Test 1090 Unit's 1085 1085 5 360 357 173 171 557 557

Flushing 1 Network 1 1 0 ----- ----- 1 1 ----- -----


AWAITING REPORT FROM RAVI
Pump Pre Commissioning 6 Pump's 4 4 2 ----- ----- 6 4 ----- -----
Chilled Water System AWAITING REPORT FROM RAVI
Pump Functional Test 6 Pump's 4 4 2 ----- ----- 6 4 ----- -----

Balancing 2 Network 1 0 2 ----- ----- 2 0 ----- -----

Flushing 1 Network 1 1 0 ----- ----- 1 1 ----- -----


LTHW System (Primary)
Balancing 1 Network 0 0 1 ----- ----- 1 0 ----- -----

Heat Exchangers (Hot Water) Functional Test 9 Unit's 0 0 9 2 0 5 0 2 0

Pressurization Unit Functional Test 1 Unit's 1 1 0 ----- ----- 1 1 ----- -----

Dosing Unit Functional Test 1 Unit's 1 1 0 ----- ----- 1 1 ----- -----

Fresh Air Handling Units Initial Start-Up & Pre-Commissioning 17 Unit's 17 17 0 2 2 10 10 5 5


(FAHU) Air Balancing 17 Unit's 17 17 0 2 2 10 10 5 5

Initial Start-Up & Pre-Commissioning 22 Unit's 21 19 3 3 3 14 11 5 5 1


Air Handling Unit AHU/MAHU
Air Balancing 22 Unit's 21 19 3 3 3 14 11 5 5 1

HVAC Initial Start-Up & Pre Commissioning 6 Unit's 4 4 2 ----- ----- 4 2 2 2 PERFORMANCE ONLY IN KMEP SCOPE
Ecology Unit
Air Balancing (Performance only) 6 Unit's 4 4 2 ----- ----- 4 2 2 2 PERFORMANCE ONLY IN KMEP SCOPE

Initial Start-Up & Pre Commissioning 41 Unit's 37 36 5 3 2 28 25 10 9


General Fan
General Fan Air Balancing 41 Unit's 37 36 5 3 2 28 25 10 9

Pre Commissioning (Pressure Test) 6 Unit's 2 2 4 ----- ----- 6 2 ----- -----


DX Unit
Functional Test (Air Balancing) 6 Unit's 6 6 0 ----- ----- 6 6 ----- ----- 1

FCU/BCU Air balancing 823 Unit's 820 813 10 78 78 228 223 516 510 7

Pre Commissioning 11 Unit's 8 8 3 ----- ----- 11 8 ----- -----


Car Park Supply Fan
Commissioning 11 Unit's 8 8 3 ----- ----- 11 8 ----- -----

Pre Commissioning 11 Unit's 11 11 0 ----- ----- 11 11 ----- -----


Car Park Exhaust Fan
Commissioning 11 Unit's 11 11 0 ----- ----- 11 11 ----- -----
P Planned CIR

DORCHESTER HOTEL & RESIDENCES S Sutton Approved


Weekly progressed Activity
Commissioning Activity Summary Report
A Consultant Approved
TC T&C Approved
KPI SUMMARY Date: 19-09-23
OVERALL RESIDENTIAL PODIUM AREA HOTEL

Cumulative Cumulative Cumulative Cumulative Cumulative


Sep-23 Sep-23
System Equipment Type Activity Witnessed Approved Pending Quantity Approved Approved Approved Week Ending Week Ending
Total Quantity Type
Quantity Quantity For Approval
Total Quantity
Quantity
Total Quantity
Quantity
Total Quantity
Quantity (19/09/2023) (26/09/2023) Comments
Pre Commissioning 14 Unit's 11 11 3 3 2 7 5 4 4
Make Up Air Fan
Commissioning 14 Unit's 11 11 3 3 2 7 5 4 4

Pre Commissioning 15 Unit's 13 13 2 3 3 7 5 5 5


Smoke Extract Fan
Commissioning 15 Unit's 13 13 2 3 3 7 5 5 5

Pre Commissioning 6 Unit's 5 5 1 2 1 4 4 1 1 3 FANS CANCELLED AS PER CONFIRMATION MAIL (STAIRSOPEN TO SKY)
Staircase Pressurization Fan
Commissioning 6 Unit's 5 5 1 2 1 4 4 1 1

DWS Pump Pre Commissioning 36 Pumps 26 26 10 9 7 20 17 7 2

DWS Pump Commissioning 36 Pumps 26 26 10 9 7 20 17 7 2


Domestic Water System
DWS balancing 1 Network 0 0 1 ----- ----- 1 0 ----- -----

Chlorination 1 Network 0 0 1 ----- ----- 1 0 ----- -----

Boiler Functional Test 4 Units 0 0 4 ----- ----- 4 0 ----- -----

Calorifiers Functional Test 16 Units 0 0 16 8 0 2 0 6 0

Hot Water System Heat Exchanger Functional Test 40 Units 0 0 40 17 0 9 0 14 0


(DWS Ancillary) Dosing Unit Functional Test 1 Units 0 0 1 ----- ----- 1 0 ----- -----
Plumbing
PRV Functional Test 85 Units 57 45 40 45 24 28 15 12 6 12

Filtration system Functional Test 1 Unit's 1 1 0 ----- ----- 1 1 ----- -----

Domestic Water Tanks Leak Test/ Float Valve Functional Test 8 Tanks 0 0 8 2 0 4 0 2 2

Sewage & sump Pump Pre Comm: 29 Unit's 25 25 4 ----- ----- 29 25 ----- -----

Sewage & sump Pump commissioning 29 Unit's 25 25 4 ----- ----- 29 25 ----- -----
Drainage
Drainage Flow Test 59 Level's 59 59 0 26 26 9 9 24 24

Royal Flush 59 Level's 0 0 59 26 0 9 0 24 0

Grease Seperator Grease Seperator Functional Test 4 Unit's 0 0 4 ----- ----- 4 0 ----- -----

LPG pre commissioning 1 PRMS 0 0 1 ----- ----- 1 0 ----- -----


LPG LPG
Functional Test 1 PRMS 0 0 1 ----- ----- 1 0 ----- -----

Total Quanitities 10669 7346 7175 2950 1984 1503 3990 2318 4687 3135
Commissioning Activity Report Rev: 00

DORCHESTER HOTEL & RESIDENCES Date: 19-09-23

Testing & Commissioning Progress Summary - Break Down


WEIGHTAGE RESIDENTIAL TOWER PODIUM AREA HOTEL TOWER Comments
Approved Approved Approved
Overall Commissioning 1.000 77.75% 70.40% 76.20%
LV SYSTEM COMMISSIONING
Overall 0.200 92.53% 84.38% 78.80%
LV Panels (MDB/SMDB/MCC) 0.076 98.17% 97.38% 95.47%
LV Associated (PFC,ATS) 0.021 80.00% 95.00% 80.00%
Busbar 0.024 100.00%
Control Panels 0.008 100.00% 64.29% 71.74%
Distribution Boards (DB) 0.042 87.16% 62.50% 49.39%
Generator 0.006 30.00%
ACB Trip Panel 0.003 66.00%
Earthing & Lightning Protection 0.012 96.80%
UPS 0.008 50.00%
ELV SYSTEM COMMISSIONING
Overall 0.300 71.96% 58.20% 67.60%
Lighting Control System 0.012 77.69% 33.33% 51.33%
GRMS 0.015 50.00%
IPTV/SMATV 0.009 0.00%
IP Telephone 0.006 0.00% 0.00% 0.00%
Digital Signage 0.006 87.50%
AV (Common Area) 0.003 50.00%
Closed Circuit Television Cameras (CCTV) 0.027 86.15% 71.16% 84.38%
Structural Cabling (IDF's) 0.073 100.00% 91.67% 100.00%
Structural Cabling system (Guest Rooms) 0.010 98.67%
Access Control System Doors (ACS) 0.012 0.00% 23.80% 0.00%
LPG Leak Detection Devices 0.001 20.00%
Background Music System Circuits (BGM) 0.012 50.00% 27.11% 50.00%
Wireless Access System IT Racks (WiFi) 0.003 0.00% 0.00% 0.00%
Disabled Alarm System Pull Cords 0.003 80.00% 71.43%
Gate Barriers 0.003 0.00%
Residential Intercom System Call Points 0.003 0.00% 0.00%
Building Management System (BMS) 0.030 76.67% 65.20% 61.43%
Fire Alarm Loops 0.038 76.88% 48.18% 70.00%
PAVA 0.002 91.61% 23.00% 73.79%
Fire Telephone 0.002 100.00% 100.00% 100.00%
Central Battery System 0.030 40.91% 29.66% 53.39%
HVAC SYSTEM COMMISSIONING
Overall 0.250 81.49% 78.43% 87.71%
Chilled Water Flushing 0.038 100.00%
Heat Exchangers 0.008 0.00% 0.00% 0.00%
CHW Ancillary (PU & DU) 0.003 100.00%
CHW/LTHW PUMPS & BALANCING 0.046 46.67%
AHU 0.030 100.00% 84.29% 100.00%
General Fans 0.020 66.67% 89.29% 83.00%
Fan Coil Unit 0.035 100.00% 98.25% 99.42%
DX Unit 0.003 80.00%
Fire & Life Safety Fans 0.030 67.50% 73.85% 90.00%
Motorized Dampers 0.012 50.00% 50.00% 50.00%
Fire Dampers 0.028 99.17% 98.84% 100.00%
PLUMBING SYSTEM COMMISSIONING
Overall 0.150 51.25% 56.68% 56.84%
Chlorination 0.011 0.00% 0.00% 0.00%
Domestic Water Tanks 0.001 0.00% 0.00% 50.00%
Domestic Water Pumps 0.026 40.91% 45.00% 14.29%
DWS Ancillary (Boiler/calorifier,HEX,DU) 0.057 48.98% 48.48% 72.00%
Sewage & Sump Pumps 0.030 75.76%
Drainage & Rainwater Stacks 0.026 90.00% 90.00% 90.00%
FIRE FIGHTING SYSTEM COMMISSIONING
Overall 0.100 95.96% 79.56% 97.09%
Fire Pump 0.015 100.00%
Fire Hose Cabinet 0.035 100.00% 100.00% 100.00%
Zone Control Valve 0.010 77.78% 47.62% 84.00%
Supervisory Valves 0.010 100.00% 100.00% 100.00%
Room Integrity Test 0.010 100.00%
FM200 Suppression System 0.010 48.00%
Foam Suppression System 0.005 0.00%
LPG System Components 0.005 0.00%
DORCHESTER HOTEL & RESIDENCES - DETAILED T&C SUMMARY
Cum.Actual Progress (Progress at Site)
Actual - Cumulative Actual - Weekly
Actual - Cumulative Actual - Weekly
WBS Breakdown Weightage Total Qty Unit Progress (Sutton Progress(Sutton
(Progress approved) (Progress approved)
Pre- commissioning Commissioning Witness) Witness)

LV 20% 612 85.62% 1.44% 83.17% 0.63%

LV PANELS (MDB,SMDB, MCC) 7.60% 112 No's 100.85% 100.53% 98.60% 0.30% 97.08% 0.61%

LV ASSOCIATED (PFC,ATS) 2.10% 10 No's 100.00% 70.00% 94.00% 2.00% 92.00% 0.00%

BUSBAR 2.40% 5 No's 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

CONTROL PANEL 0.80% 65 No's 90.77% 80.00% 85.38% 4.29% 70.77% 4.29%

DB 4.20% 363 No's 98.34% 23.97% 61.16% 2.06% 58.68% 1.10%

GENERATORS 0.60% 1 Nos 100.00% 0.00% 30.00% 0.00% 30.00% 0.00%

ACB TRIP PANEL 0.30% 3 No's 100.00% 100.00% 100.00% 34.00% 66.00% 0.00%

EARTHING & LIGHTNING PROTECTION 1.20% 50 Pits 100.00% 96.00% 98.40% 0.00% 96.80% 0.00%

UPS 0.80% 3 No's 100.00% 0.00% 50.00% 0.00% 50.00% 0.00%

ELV 30% 2577 67.73% 0.26% 64.50% 0.03%

LIGHTING CONTROL SYSTEM 1.20% 49 Panels 87.76% 20.41% 47.35% 0.82% 44.90% 0.82%

GRMS 1.50% 225 Rooms 100.00% 0.00% 50.00% 0.00% 50.00% 0.00%

IPTV/SMATV 0.90% 225 Rooms 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IP Telephone 0.60% 40 Levels 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Digital Signage 0.60% 8 No's 87.50% 87.50% 87.50% 0.00% 87.50% 0.00%

AV (Common Area) 0.30% 15 Loops 100.00% 0.00% 50.00% 0.00% 50.00% 0.00%

Closed Circuit Television Cameras (CCTV) 2.70% 984 Cameras 81.81% 72.69% 78.16% 0.00% 77.65% 0.00%

Structured & Data Cabling System (SCS) 7.30% 30 Units 96.67% 96.67% 96.67% 0.00% 96.67% 0.00%

Structured & Data Cabling System (Guest Rooms) 1.00% 225 Cabinets 98.67% 98.67% 98.67% 0.00% 98.67% 0.00%

Access Control System Doors (ACS) 1.20% 145 Doors 24.83% 12.41% 19.86% 0.00% 14.90% 0.00%

LPG Leak Detection Devices 0.10% 62 Detectors 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Background Music System Circuits (BGM) 1.20% 112 Loops 66.07% 0.00% 33.04% 0.00% 33.04% 0.00%

Wireless Access System IT Racks (WiFi) 0.30% 30 Racks 33.33% 33.33% 33.33% 0.00% 0.00% 0.00%

Disabled Alarm System Pull Cords 0.30% 14 No's 85.71% 78.57% 82.86% 0.00% 75.71% 0.00%

Gate Barriers 0.30% 2 No's 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Residential Intercom System Call Points 0.30% 58 No's 89.66% 100.00% 93.79% 0.00% 93.79% 0.00%

Building Management System (BMS) 3.00% 35 Panels 97.14% 52.57% 74.86% 2.29% 65.43% 0.00%

Fire Alarm Loops 3.80% 47 Loops 100.00% 53.19% 72.55% 0.00% 68.30% 0.00%

PAVA 0.20% 80 Loops 77.50% 67.50% 69.50% 0.00% 68.00% 0.00%

Fire Telephone 0.20% 12 Loops 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

Central Battery System 3.00% 179 Loops 99.44% 28.49% 49.78% 0.00% 43.07% 0.00%

HVAC 25% 2636 83.17% 0.32% 79.36% 0.13%

Heat Exchangers 0.75% 34 No's 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

CHW Ancillary (PU & DU) 0.25% 2 No's 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

CHW/LTHW Flushing 8.35% 9 Pumps 92.59% 27.78% 162.22% 0.00% 100.00% 0.00%

AHU 3.00% 21 No's 93.33% 93.33% 93.33% 2.22% 90.22% 0.67%

General Fans 2.00% 41 No's 87.80% 87.80% 87.80% 0.00% 87.80% 0.00%

Fan Coil Unit 3.50% 822 No's 99.64% 99.64% 99.64% 0.36% 99.15% 0.36%

DX Unit 0.25% 6 No's 100.00% 100.00% 100.00% 0.00% 80.00% 0.00%

Fire & Life Safety Fans 3.00% 58 No's 86.21% 51.72% 77.59% 0.00% 77.59% 0.00%

Motorized Dampers 1.15% 553 No's 100.00% 50.00% 50.00% 0.00% 50.00% 0.00%

Fire Dampers 2.75% 1090 No's 99.54% 99.54% 99.54% 0.00% 99.54% 0.00%

PLUMBING 15% 245 60.67% 4.72% 57.79% 4.26%

Domestic Water Tanks 0.10% 8 No's 0.00% 12.50% 12.50% 0.00% 12.50% 0.00%

Domestic Water pump & Chlorination 3.65% 38 Pumps 0.00% 24.47% 40.79% 2.63% 38.16% 0.00%

DWS Ancillary (Boiler/calorifier,HEX,DU,PRV) 5.70% 107 No's 54.21% 54.21% 54.21% 11.21% 54.21% 11.21%

Sewage & Sump Pumps 3.00% 33 Pumps 87.88% 87.88% 87.88% 0.00% 75.76% 0.00%

Drainage & Rainwater Stacks 2.55% 59 Levels 100.00% 0.00% 90.00% 0.00% 90.00% 0.00%

FIRE FIGHTING 10% 342 87.79% 0.27% 81.92% 0.00%

Fire Pump 1.50% 6 Pumps 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

Fire Hose Cabinet 3.50% 228 No's 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

Zone Control Valve 1.00% 73 No's 84.93% 84.93% 84.93% 2.74% 78.08% 0.00%

Supervisory Valves 1.00% 13 No's 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

Room Integrity Test 1.00% 10 Rooms 100.00% 100.00% 100.00% 0.00% 100.00% 0.00%

FM200 Suppression System 1.00% 10 Panels 60.00% 67.50% 68.00% 0.00% 56.00% 0.00%

Foam Suppression System 0.50% 1 Panel 0.00% 75.00% 60.00% 0.00% 0.00% 0.00%

LPG System Components 0.50% 1 Station 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Overall T&C Progress 100% 6412 76.11% 1.18% 72.68% 0.81%