REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)

PHYSICAL AND FINANCIAL ACCOMPLISHMENT REPORT


As of May 31, 2023

Name of Project: CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM LEVEL II (PWSS)


Date Started: May 1, 2023
Target Completion Date: July 31, 2023
Location: Brgy. Patola, Talugtug, Nueva Ecija
Implementating Agency: MEO

Obligations Disbursement Physical Status (%) Employment


As Reporting Period For the Month As Reporting Period For the Month Target to Date Target for the Month Actual to Date Actual for the Month Male Female
1,298,445.69 1,298,445.69 - - 38% 38% 38% 38% 15 15

Submitted by: ENGR. WILSON M. NIMENZO Noted by: HON. PACIFICO B. MONTA
Designation: OIC - MPDC Municipal Mayor