Prepared by:
CELIA T. FALSIS
Owner
F & T Construction and Supply
UTILIZATION SCHEDULE
PERIOD
NTH 2nd MONTH
Name of Project: CONSTRUCTION OF PROVINCIAL ROAD
Location: BRGY. MOJON, BELISON, ANTIQUE
Bidder: F & T CONSTRUCTION AND SUPPLY
Date: APRIL 2, 2018
MANPOWER UTILIZATION SC
CATEGORY No.
1st MONTH
Project Engineer 1
Safety Officer 1
Foreman 1
Mason/Steelman 4
Operator 2
Laborer/Helper 10
Drivers 3
TOTAL MANPOWER 22
Prepared by:
CELIA T. FALSIS
Owner
F & T Construction and Supply
OWER UTILIZATION SCHEDULE
PERIOD
1st MONTH 2nd MONTH
CONSTRUCTION SCHEDU
Name of Project: CONSTRUCTION OF PROVINCIAL ROAD
Location: BRGY. MOJON, BELISON, ANTIQUE
PERT CPM:
Bidder: F & T CONSTRUCTION AND SUPPLY
Date: APRIL 2, 2018
TOTAL 100.00%
Monthly (%)
PERCENT ACCOMPLISHMENT
Cummulative (%)
Monthly (Php)
CASH FLOW
Cummulative (Php)
Prepared by:
CELIA T. FALSIS
Owner
PERT CPM:
SPL 2
60CD
SPL 3 311
SPL 1 10CD 44CD SPL 3
1CD 5CD
1.59%
46,425.8020 3.17% S-CURVE
0%
0%
975,721.82
SPL 3
5CD
100%
50%
1.59%
0%
0%
CASH FLOW BY QUARTER AND PAYM
Name of Project: CONSTRUCTION OF PROVINCIAL ROAD
Location: BRGY. MOJON, BELISON, ANTIQUE
Bidder: F & T CONSTRUCTION AND SUPPLY
Date: APRIL 2, 2018
PERIOD Q1
QUARTERLY (%) 29.54%
PERCENT ACCOMPLISHMENT
CUMMULATIVE (%) 29.54%
QUARTERLY (Php) 288,228.2256
CASH FLOW
CUMMULATIVE (Php) 288,228.2256
Total project bid cost 975,721.82
Prepared by:
CELIA T. FALSIS
Owner
F & T Construction and Supply
UARTER AND PAYMENT SCHEDULE
Q2 Q3 Q4
15.96% 31.47% 23.05%
45.50% 76.97% 100.00%
155,725.2025 307,059.6573 227,236.1938
443,953.4281 758,604.1262 975,721.82
DETAILED ESTIMATE
Name of Project: CONSTRUCTION OF PROVINCIAL ROAD
Location: BRGY. MOJON, BELISON, ANTIQUE
Bidder: F & T CONSTRUCTION AND SUPPLY
Date: APRIL 2, 2018
ITEM
DESCRIPTION % WT QTY UNIT UNIT COST AMOUNT
NO.
SPL 1 Project Billboard ( two unit 8' x 8' ) 1.11% 2.00 unit 5,429.18 10,858.36
a. Materials
Tarpulin billboard with lumber frame and support 2.00 units 4,000.00 8,000.00
8,000.00
b. Labor
VAT/Tax: 710.36
TOTAL ITEM COST 10,858.36
ITEM UNIT COST 5,429.18
SPL 2 Construction Safety and Health 8.42% 2.00 month 41,097.63 82,195.26
a. Materials
Signages and warning devices 8.00 sets 700.00 5,600.00
Construction helmet 15.00 pcs 600.00 9,000.00
Reflectorized vest 15.00 pcs 300.00 4,500.00
Safety boots 15.00 pcs 1,200.00 18,000.00
b. Labor
ITEM
DESCRIPTION % WT QTY UNIT UNIT COST AMOUNT
NO.
VAT/Tax: 5,377.26
TOTAL ITEM COST 82,195.26
ITEM UNIT COST 41,097.63
a. Materials
N O N E
b. Labor
1 Engineer 3.00 day 650.00 1,950.00
1 Foreman 3.00 day 420.00 1,260.00
2 Operator 3.00 day 400.00 2,400.00
1 Driver 3.00 day 380.00 1,140.00
VAT/Tax: 3,037.20
TOTAL ITEM COST 46,425.80
ITEM UNIT COST 82.84
a. Materials
Portland Cement, Type 1, 40kg 1,290.00 bags 285.00 367,650.00
DETAILED ESTIMATE
Name of Project: CONSTRUCTION OF PROVINCIAL ROAD
Location: BRGY. MOJON, BELISON, ANTIQUE
Bidder: F & T CONSTRUCTION AND SUPPLY
Date: APRIL 2, 2018
ITEM
DESCRIPTION % WT QTY UNIT UNIT COST AMOUNT
NO.
b. Labor
1 Engineer 13.00 days 650.00 8,450.00
1 Foreman 13.00 days 420.00 5,460.00
2 Technician 13.00 days 500.00 13,000.00
3 Mason/Steelman/Carpenter 13.00 days 400.00 15,600.00
c. Equipment
1 One Bagger Concrete Mixer 13.00 days 2,000.00 26,000.00
VAT/Tax: 58,536.97
TOTAL ITEM COST 836,242.40
ITEM UNIT COST 1,193.78
ITEM
DESCRIPTION % WT QTY UNIT UNIT COST AMOUNT
NO.
TOTAL AMOUNT IN WORDS: Nine Hundred Seventy Five Thousand Seven Hundred Twenty One
Pesos and 82/100 Centavos Only
Prepared by:
CELIA T. FALSIS
Owner
F & T Construction and Supply
INVITATION TO BID
ADVERTISEMENT NO.
IB NO. K-2018-028(SC)
SPL 1 2.00 unit Project Billboard ( two unit 8' x 8' ) 5,500.00 11,000.00 5,429.18 10,858.36
SPL 2 2.00 month Occupational Safety and Health Program 20,729.912500 41,459.83 41,097.63 82,195.26
TOTAL AMOUNT IN WORDS: NINE HUNDRED SEVENTY FIVE THOUSAND SEVEN HUNDRED TWENTY ONE PESOS AND 82/100 CENTAVOS ONLY
Purpose: Concreting of Provincial Road
Place of Delivery: Brgy. Mojon, Belison, Antique
I hereby certify that the articles/services listed above are available in our store/stockroom and ready for delivery
upon receipt of the Contract/Purchase Order.
SPL 3 Road Resurface Levelling and Compaction of Existing Item 201 46,425.8020
311 Portland Cement Concrete Pavement, Class "A" (0.20m thk.) 836,242.3997
TOTAL BID
COST: 975,721.82
TOTAL
AMOUNT IN
Nine Hundred Seventy Five Thousand Seven Hundred Twenty One Pesos and
WORDS: 82/100 Centavos Only
Prepared by:
CELIA T. FALSIS
Owner
F & T Construction and Supply