RPMES FORM 1

REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)


INITIAL PROJECT REPORT
Physical and Financial Targets for Ongoing Programs and Projects
FY 2023

Implementing Agency: LOCAL GOVERNMENT OF MATUGUINAO

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)

(a) Name of Project


(b) Location
(c) Sector/Subsector
Total Project Target JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL
(d) Funding Source
(e) Mode of Implementation
(f) Project Schedule
1. Construction of Public Toilet for Mahanud FS - - - - - - - - 78,942.88 118,414.31 197,357.19
Elementary School in Brgy. Mahanud, Matuguinao,
Samar % 40.00% 60.00% 100.00%
Location: Brgy. Mahanud, Matuguinao, Samar
Sector/Subsector: Toilet
Funding Source: FY 2023 20% EDF
Mode of Implementation: By Contract
Target Start Date: September 5, 2023
Target Completion: October 19, 2023

OI
EG Male-7 Male-7 Male - 7
FS - Financial Schedule % - Overall Physical Target in Percent OI - Output Indicator EG - Employment Generated

Submitted by: ENGR. FILEMON G. COBILLA Noted by: HON. ARAN DELA CRUZ BOLLER
Designation/Office: MUNICIPAL ENGINEER MUNICIPAL MAYOR