You are on page 1of 8

Job No. 1 Sheet No. 1 Rev.

Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU
PINANG (SCHEDULE 2)
-SEDIMENT YIELD ESTIMATION
- Existing Condition Member/Location :
Drg. Ref. :
Job Title : SEDIMENT YIELD Made by Ainur Date Mar-19 Remark

SEDIMENT YIELD ESTIMATION

The Modified Universal Soil Loss Equation (MUSLE) is used to determine the sediment yield

The design of all sediment control BMP's required the quantity of the sediment to be trapped.
The design rainfall as per requirement of MASMA is set to be 200 mm to the catchment under consideration

1) Determination of Runoff Parameters

a) Design Storm
Design Storm = 200 mm
Catchment Area, A = 0.81 ha
Table 2.1 Time of Concentration,tc = 4 minutes
0.333
tc = 107 n L L = 45.211 m
0.2
S S = 16.074
n = 0.02 ( From Table 2.2 for existing )
to = 4.4 minutes Adopt tc = minutes

Duration of storm,D = 20 minutes


Intensity of design storm, I = 200 mm/h

Eqn. 2.3 b) Calculate Peak Discharge, Qp using Rational Method

Table 2.5 Run Off Coefficient, C = 0.50 (forest)

Qp = C. I . A = 0.22483 m3/s
360

Sec 2.3.2 c) Calculate Runoff Volume, V using Rational Method Hydrograph Method (Type 1)

3
Since D>tc V = 0.5 x (2 x D) x (Qp) = 269.79 m
Where, D is in seconds
Job No. 1 Sheet No. 2 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU
-SEDIMENT YIELD ESTIMATION PINANG (SCHEDULE 2)

Member/Location :
Drg. Ref. :
Job Title : Made by Ainur Date Mar-19 Remark

2) Calculation of Sediment Yield

Eqn. 12.4 Y = 89.6(VQp)0.56 (K.LS.C.P)

where,
Y = Sediment yield per storm event (tonnes)
V = Runofff Volume in m3
Qp = Peak Discharge in m3/s
K = Soil erodibility factor
LS = Slope Length and Slope Steepness Factor USLE Factor
C = Cover Management Factor
P = Support Practice Factor

Soil Erodibility Factor


Eqn. 12.3

NOTE

K = 0.0560

Slope Length and Sloipe Steepness Factor, LS

λ = 45 m , Horizontal Slope Length


s = 16.1 % , Slope Steepness
LS = 1.227

Cover management and Support Practice


C = 0.030
P = 1

As Such, Total Sediment Yield to Load the Sediment Basin per Storm Event
Y = 1.84022 Tonnes
Job No. 1 Sheet No. 3 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU
PINANG (SCHEDULE 2)
-SEDIMENT YIELD ESTIMATION
- With Conservation Practice Member/Location :
Drg. Ref. :
Job Title : SEDIMENT YIELD Made by Ainur Date Mar-19 Remark

SEDIMENT YIELD ESTIMATION

The Modified Universal Soil Loss Equation (MUSLE) is used to determine the sediment yield

The design of all sediment control BMP's required the quantity of the sediment to be trapped.
The design rainfall as per requirement of MASMA is set to be 200 mm to the catchment under consideration Table 1.3, CH 1

1) Determination of Runoff Parameters

a) Design Storm
Design Storm = 200 mm
Catchment Area, A = 0.81 ha
Table 2.1 Time of Concentration,tc = 4 minutes
0.333
tc = 107 n L L = 45.211 m
0.2
S S = 16.074
n = 0.02 ( From Table 2.2 for Conservation phase )
to = 4.4 minutes Adopt tc = minutes

Duration of storm,D = 20 minutes


Intensity of design storm, I = 200 mm/h

Eqn. 2.3 b) Calculate Peak Discharge, Qp using Rational Method

Table 2.5 Run Off Coefficient, C = 0.63 (meadows)

Qp = C. I . A = 0.2833 m3/s
360

Sec 2.3.2 c) Calculate Runoff Volume, V using Rational Method Hydrograph Method (Type 1)

3
Since D>tc V = 0.5 x (2 x D) x (Qp) = 339.94 m
Where, tc is in seconds
Job No. 1 Sheet No. 4 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU
-SEDIMENT YIELD ESTIMATION PINANG (SCHEDULE 2)

Member/Location :
Drg. Ref. :
Job Title : Made by Ainur Date Mar-19 Remark

2) Calculation of Sediment Yield

Eqn. 12.4 Y = 89.6(VQp)0.56 (K.LS.C.P)

where,
Y = Sediment yield per storm event (tonnes)
V = Runofff Volume in m3
Qp = Peak Discharge in m3/s
K = Soil erodibility factor
LS = Slope Length and Slope Steepness Factor USLE Factor
C = Cover Management Factor
P = Support Practice Factor

Soil Erodibility Factor


Eqn. 12.3

NOTE

K = 0.0560

Slope Length and Sloipe Steepness Factor, LS

λ = 45 m , Horizontal Slope Length


s = 16.1 % , Slope Steepness
LS = 1.227

Cover management and Support Practice


C = 0.06
P = 0.640

As Such, Total Sediment Yield to Load the Sediment Basin per Storm Event
Y = 3.051 Tonnes
Job No. 1 Sheet No. 5 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU PINANG
(SCHEDULE 2)
-SEDIMENT YIELD ESTIMATION
- Worst Case Scenario Member/Location :
Drg. Ref. :
Job Title : SEDIMENT YIELD Made by Ainur Date Mar-19 Remark

SEDIMENT YIELD ESTIMATION

The Modified Universal Soil Loss Equation (MUSLE) is used to determine the sediment yield

The design of all sediment control BMP's required the quantity of the sediment to be trapped.
The design rainfall as per requirement of MASMA is set to be 200 mm to the catchment under consideration Table 1.3, CH 1

1) Determination of Runoff Parameters

a) Design Storm
Design Storm = 200 mm
Catchment Area, A = 0.8094 ha
Table 2.1 Time of Concentration,tc = 4 minutes
0.333
tc = 107 n L L = 45.211 m
0.2
S S = 16.07
n = 0.02 ( From Table 2.2 for Worst case )
to = 4.4 minutes Adopt tc = minutes

Duration of storm,D = 20 minutes


Intensity of design storm, I = 200 mm/h

Eqn. 2.3 b) Calculate Peak Discharge, Qp using Rational Method

Table 2.5 Run Off Coefficient, C = 0.8 (bare earth)

Qp = C. I . A = 0.36 m3/s
360

Sec 2.3.2 c) Calculate Runoff Volume, V using Rational Method Hydrograph Method (Type 1)

3
Since D>tc V = 0.5 x (2 x D) x (Qp) = 431.66 m
Where, tc is in seconds
Job No. 1 Sheet No. 6 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU PINANG
-SEDIMENT YIELD ESTIMATION (SCHEDULE 2)

Member/Location :
Drg. Ref. :
Job Title : Made by Ainur Date Mar-19 Remark

2) Calculation of Sediment Yield

Eqn. 12.4 Y = 89.6(VQp)0.56 (K.LS.C.P)

where,
Y = Sediment yield per storm event (tonnes)
V = Runofff Volume in m3
Qp = Peak Discharge in m3/s
K = Soil erodibility factor
LS = Slope Length and Slope Steepness Factor USLE Factor
C = Cover Management Factor
P = Support Practice Factor

Soil Erodibility Factor


Eqn. 12.3

NOTE

K = 0.0560

Slope Length and Sloipe Steepness Factor, LS

λ = 45 m , Horizontal Slope Length


s = 16 % , Slope Steepness
LS = 1.227

Cover management and Support Practice


C = 1
P = 1

As Such, Total Sediment Yield to Load the Sediment Basin per Storm Event
Y = 103.8 Tonnes
Job No. 1 Sheet No. 7 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU PINANG
(SCHEDULE 2)
-SEDIMENT YIELD ESTIMATION
- Post Construction Member/Location :
Drg. Ref. :
Job Title : SEDIMENT YIELD Made by Ainur Date Mar-19 Remark

SEDIMENT YIELD ESTIMATION

The Modified Universal Soil Loss Equation (MUSLE) is used to determine the sediment yield

The design of all sediment control BMP's required the quantity of the sediment to be trapped.
The design rainfall as per requirement of MASMA is set to be 200 mm to the catchment under consideration Table 1.3, CH 1

1) Determination of Runoff Parameters

a) Design Storm
Design Storm = 200 mm
Catchment Area, A = 0.8094 ha
Table 2.1 Time of Concentration,tc = 4 minutes
0.333
tc = 107 n L L = 45.211 m
0.2
S S = 16.07
n = 0.02 ( From Table 2.2 for Post Construction )
to = 4.4 minutes Adopt tc = minutes

Duration of storm,D = 20 minutes


Intensity of design storm, I = 200 mm/h

Eqn. 2.3 b) Calculate Peak Discharge, Qp using Rational Method

Table 2.5 Run Off Coefficient, C = 0.91 (impervious)

Qp = C. I . A = 0.41 m3/s
360

Sec 2.3.2 c) Calculate Runoff Volume, V using Rational Method Hydrograph Method (Type 1)

3
Since D>tc V = 0.5 x (2 x D) x (Qp) = 491.02 m
Where, tc is in seconds
Job No. 1 Sheet No. 8 Rev.
Calculation Sheet
MENGGANTI JAMBATAN SEDIA ADA DI FT 006/041/93 BARAT DAYA, PULAU PINANG
-SEDIMENT YIELD ESTIMATION (SCHEDULE 2)

Member/Location :
Drg. Ref. :
Job Title : Made by Ainur Date Mar-19 Remark

2) Calculation of Sediment Yield

Eqn. 12.4 Y = 89.6(VQp)0.56 (K.LS.C.P)

where,
Y = Sediment yield per storm event (tonnes)
V = Runofff Volume in m3
Qp = Peak Discharge in m3/s
K = Soil erodibility factor
LS = Slope Length and Slope Steepness Factor USLE Factor
C = Cover Management Factor
P = Support Practice Factor

Soil Erodibility Factor


Eqn. 12.3

NOTE

K = 0.0560

Slope Length and Sloipe Steepness Factor, LS

λ = 45 m , Horizontal Slope Length


s = 16.1 % , Slope Steepness
LS = 1.227

Cover management and Support Practice


C = 0.01
P = 0.5

As Such, Total Sediment Yield to Load the Sediment Basin per Storm Event
Y = 0.60 Tonnes

You might also like