You are on page 1of 1

4348/325/JZ/01/ May 05, 2023

Dr. Jawaad Ahmad


Project Director
COMSATS University
Wah Campus, Wah Cantt.
- Construction of Academic Block-I at Existing CUI Campus, Wah Cantt
- 1st Progress Review Meeting Notice
Refer:
(i) Kick-Off Meeting minutes dated: April 19, 2023;
(ii) Letter.No: 4348/325/JZ/01/4274 dated: April 28, 2023
It is to inform that 1st Progress Review Meeting will be held on Monday, May 05, 2023 (10:00
A.M.) at COMSATS University, Wah Campus, Wah Cantt. All the concerned officials of the
Employer & the Contractor are requested to attend the said meeting.
The agenda of the meeting is as follows:

(i) Submission of Construction Programme, Cash Flow Estimate


& Procurement Schedule - Action by Contractor awaited;
(ii) Method Statement for Dismantling & Excavation Works - Action by Contractor awaited;
(iii) Appointment of Project Manager / Authorized Representative - PEC Registration
Certificate, Action by Contractor awaited;
(iv) List of Contractor’s Site Staff - Action by Contractor awaited;
(v) Submission of 06 Copies of Contract Documents (Volume I, II & IV) – Still awaited;
(vi) Submission of Insurance Policies – Action by Contractor awaited;
(vii) NESPAK Site Staff office & Transport Facility – Action by Contractor awaited;
(viii) Establishment of Field Laboratory & Qualified Lab Technician – Action by Contractor
awaited;
(ix) Sign Boards – Action by Contractor awaited;
(x) Working Days/Hours – Action by Contractor awaited

Items (other than afore-mentioned) will be discussed during the meeting.

Thanking you.
Very truly yours
For National Engineering Services Pakistan (Pvt.) Limited

Jahan Zaib
(Engineer’s Representative)
Copy to:
- Project Manager, Job.No. 4348, NESPAK, Islamabad Office.
- M/s Eiffel Civil & EM (Pvt.) Limited, Plot 12-C/2, 3rd Floor, Mandeer Sqaure, G-8
Markaz, Islamabad.
- Office File.No.4348.

You might also like