Quality Check For MEP Works - Report-1
Quality Check For MEP Works - Report-1
Project Name/No: ARABIAN RANCHES PHASE III (3A & 3C) – Report No - 01 Date:23 -09-2023
Prepared by: MUHAMMAD SHAHZAD
IN-PROPER CUTTING
FOR INSTALLATION OF
1
GI BACK BOX AND
CONDUITS IN 3C & 3B
S.No Description Photographs Photographs after Work Remarks
CONDUITS INSTALLED
2 IN FRONT OF AC GRILL
IN 3B
NOT FOLLOWING A
PROPER WAY FOR
9
CONDUITING IN PHASE
3C
UN-WANTED HOLE IN GI
10
BACK BOX
NO PROPER WAY OF
11 UPVC CONDUIT
CONNECTION
GI BACK BOX OUT OF
12
THE PLASTER
DB OUT OF THE
PLASTER AND IN-
17 PROPER WAY OF
CONDUITING, CAUSE
WAIST OF WIRE