You are on page 1of 12

SIEMENS Fit Up and Weld Visual Report Format Number: SIEMENS-

Issuing Department PG SU AP IN QM PQM Reviewing Department PG SU AP IN QM PQM Document Type: FOR

Prepared: Dilip Chaudhary Approved By: Mridul sen Gupta Language: En

Project:1X20 MW STG PROJECT Plant:KAMANDA STEEL PLANT Unit:1X20 MW STG System:

Name of Client: M/s RUNGTA MINES LIMITED- KAMANDA Report No:RML/SL/TEE/DR-0709 Date:

ISO/ Line Number:62OP42504-U1-673010209-45 Piping Class:CARBON STEEL(CS) Service:WATER Pre‐Heat Temperature: 10 0C (Min)

Equipment Number: NEW FEED DEARATOR OVER FLOW AND DRAIN TO EXIT DEA OVERFLOW LINE Equipment Drawing Number: Inter Pass Temperature: 150 0C (Max)

Temporary PMI
Heat Number Type Of Thickness Dimensional & WPS Root W/V attachment Final Weld Report
Sr No. Matcode/Spool No. (Note-1) Joint No. Joint Size (NB) (mm) Allignment Fit-Up Check Fit-up Date Number Welder Number (Note:7) NDT Visual Final WV Date ( Note-2 & Note
Check
(Note-5) -3)

DR-0709-01 NA J-1 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA


1
DR-0709-01 NA J-2 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
2
DR-0709-01 NA J-3 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
3
DR-0709-02 NA J-4 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
4
DR-0709-02 NA J-5 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
5
DR-0709-03 NA J-6 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
6
DR-0709-03 NA J-7 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
7
DR-0709-04 NA J-8 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
8
DR-0709-04 NA J-9 BW 114.3 6.02 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
9
DR-0705-01 NA J-10 BW 219.1 8.18 OK OK 7/10/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
10
DR-0705-01 NA J-11 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
11
DR-0705-02 NA J-12 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
12
DR-0705-02 NA J-13 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
13
DR-0705-03 NA J-14 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
14
DR-0705-03 NA J-15 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
15
DR-0705-04 NA J-16 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
16
DR-0705-04 NA J-17 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
17
DR-0705-04 NA J-18 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
18
DR-0705-04 NA J-19 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
19
DR-0705-04 NA J-20 BW 219.1 8.18 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
20
DR-0705-05 NA J-21 BW 273.1 9.27 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
21
DR-0705-05 NA J-22 BW 273.1 9.27 OK OK 7/12/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
22
DR-0705-05 NA J-23 BW 273.1 9.27 OK OK 7/13/2021 WPS/COND/FAB03 W-02 OK NA OK 7/22/2021 NA
23
DR-0705-05 NA J-24 BW 114.3 6.02 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
24
DR-0706-02 NA J-25 BW 114.3 6.02 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
25

Unrestricted
DR-0706-02 NA J-26 BW 114.3 6.02 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
26
DR-0706-01 NA J-27 BW 114.3 6.02 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
27
DR-0706-01 NA J-28 BW 114.3 6.02 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
28
DR-0705-06 NA J-29 BW 273.1 9.27 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
29
DR-0705-07 NA J-30 BW 273.1 9.27 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
30
DR-0705-07 NA J-31 BW 273.1 9.27 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
31
DR-0705-08 NA J-32 BW 273.1 9.27 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
32
DR-0705-08 NA J-33 BW 273.1 9.27 OK OK 7/13/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
33
DR-0705-09 NA J-34 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
34
DR-0705-10 NA J-35 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
35
DR-0705-10 NA J-36 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
36
DR-0705-10 NA J-37 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
37
DR-0705-11 NA J-38 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
38
DR-0705-12 NA J-39 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
39
DR-0705-12 NA J-40 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
40
DR-0705-12 NA J-41 BW 273.1 9.27 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
41
DR-0705-13 NA J-42 BW 219.1 8.18 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
42
DR-0705-13 NA J-43 BW 219.1 8.18 OK OK 7/15/2021 WPS/COND/FAB03 W-01 OK NA OK 7/22/2021 NA
43

Note :- 1. For LTCS/ NACE/ IBR Material Heat Number shall be recorded . 2. For LAS/ SS/ Non- Ferrous material,upon satisfactory PMI,QMD engineer shall sign . 3. In Case of LTCS and NACE welding consumables batch number shall be recorded. 4. During LTCS welding heat input shall be monitored & recorded in Remarks. 5. Up o
temporary attachment area,QMD engineer shall sign. 6. Internal Cleaning to be checked as per format No: EPCMD-2-QMOO-FMT-PP-011. 7. Before starting 2nd run welding, root weld visual must be cleared for socket weld, any joint for compressor suction line, major pumps, internally lined pipes, lube oil and control oil lines, sulfuric ac

Siemens Execution Siemens QA/QC Customer Execution Customer QMD


Signature

Name

Date

Unrestricted
EMENS-FOR003

Page: 1 of 1

Internal
Cleaning as per Remarks
Format (Y/N)

YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES

Unrestricted
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES

ks. 5. Up on acceptance of DPT/MPT on


, sulfuric acid and oxygen line

QMD

Unrestricted
SIEMENS Fit Up and Weld Visual Report Format Number: SIEMENS-FOR003

Issuing Department PG SU AP IN QM PQM Reviewing Department PG SU AP IN QM PQM Document Type: FOR

Prepared: Dilip Chaudhary Approved By: Mridul sen Gupta Language: En

Project:1X20 MW STG PROJECT Plant:KAMANDA STEEL PLANT Unit:1X20 MW STG System:

Name of Client: M/s RUNGTA MINES LIMITED- KAMANDA Report No:RML/SL/TEE/VT-0707 Date:

ISO/ Line Number:62OP42504-U1-673010209-46 Piping Class:CARBON STEEL(CS) Service:WATER Pre‐Heat Temperature: 10 0C (Min)

Equipment Number: HP HEATER SRV VENT TO ATMOSPHERE Equipment Drawing Number: Inter Pass Temperature: 150 0C (Max)

Temporary PMI
Heat Number Type Of Thickness Dimensional & WPS Root W/V attachment Final Weld Report Internal
Sr No. Matcode/Spool No. (Note-1) Joint No. Joint Size (NB) (mm) Allignment Fit-Up Check Fit-up Date Number Welder Number (Note:7) NDT Visual Final WV Date ( Note-2 & Note Cleaning as per
Check Format (Y/N)
(Note-5) -3)

VT-0707-01 NA J-1 SW 114.3 6.02


1
VT-0707-01 NA J-2 BW 114.3 6.02
2
VT-0707-01 NA J-3 BW 114.3 6.02
3
VT-0707-01 NA J-4 SW 114.3 6.02
4
VT-0707-02 NA J-5 SW 168.3 7.11
5
VT-0707-02 NA J-6 SW 168.3 7.11
6
VT-0707-02 NA J-7 SW 168.3 7.11
7

Note :- 1. For LTCS/ NACE/ IBR Material Heat Number shall be recorded . 2. For LAS/ SS/ Non- Ferrous material,upon satisfactory PMI,QMD engineer shall sign . 3. In Case of LTCS and NACE welding consumables batch number shall be recorded. 4. During LTCS welding heat input shall be monitored & recorded in Remarks. 5. Up o
acceptance of DPT/MPT on temporary attachment area,QMD engineer shall sign. 6. Internal Cleaning to be checked as per format No: EPCMD-2-QMOO-FMT-PP-011. 7. Before starting 2nd run welding, root weld visual must be cleared for socket weld, any joint for compressor suction line, major pumps, internally lined pipes, lube oil an
lines, sulfuric acid and oxygen line

Siemens Execution Siemens QA/QC Customer Execution Customer QMD


Signature

Name

Date

Unrestricted
R003

Page: 1 of 1

Remarks

ks. 5. Up on
lube oil and control oil

Unrestricted
SIEMENS Fit Up and Weld Visual Report Format Number: SIEMENS-FOR0

Issuing Department PG SU AP IN QM PQM Reviewing Department PG SU AP IN QM PQM Document Type: FOR

Prepared: Dilip Chaudhary Approved By: Mridul sen Gupta Language: En

Project:1X20 MW STG PROJECT Plant:KAMANDA STEEL PLANT Unit:1X20 MW STG System:

Name of Client: M/s RUNGTA MINES LIMITED- KAMANDA Report No:RML/SL/TEE/DM-0703 Date:

ISO/ Line Number:62OP42504-U1-673010209-47 Piping Class:STAINLESS STEEL(SS) Service:WATER Pre‐Heat Temperature: 10 0C (Min)

Equipment Number: NEW FEED DEA. EMERGENCY MAKEUP FROM TP Equipment Drawing Number: Inter Pass Temperature: 150 0C (Max)

Temporary PMI
Heat Number Type Of Thickness Dimensional & WPS Root W/V attachment Final Weld Report
Sr No. Matcode/Spool No. (Note-1) Joint No. Joint Size (NB) (mm) Allignment Fit-Up Check Fit-up Date Number Welder Number (Note:7) NDT Visual Final WV Date ( Note-2 & Note
Check
(Note-5) -3)

DM-0703-01 NA J-1 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA


1
DM-0703-01 NA J-2 SW 21.3 CL3000 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
2
DM-0703-01 NA J-3 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
3
DM-0703-02 NA J-4 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
4
DM-0703-02 NA J-5 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
5
DM-0703-03 NA J-6 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
6
DM-0703-03 NA J-7 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
7
DM-0703-04 NA J-8 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
8
DM-0703-04 NA J-9 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
9
DM-0703-05 NA J-10 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
10
DM-0703-05 NA J-11 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
11
DM-0703-06 NA J-12 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
12
DM-0703-06 NA J-13 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
13
DM-0703-07 NA J-14 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
14
DM-0703-07 NA J-15 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
15
DM-0703-07 NA J-16 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
16
DM-0703-07 NA J-17 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
17
DM-0703-08 NA J-18 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
18
DM-0703-08 NA J-19 BW 114.3 6.02 OK OK 7/15/2021 WPS/SL/014 W-02 OK NA OK 7/18/2021 NA
19

Note :- 1. For LTCS/ NACE/ IBR Material Heat Number shall be recorded . 2. For LAS/ SS/ Non- Ferrous material,upon satisfactory PMI,QMD engineer shall sign . 3. In Case of LTCS and NACE welding consumables batch number shall be recorded. 4. During LTCS welding heat input shall be monitored & recorded in Remarks. 5. Up o
DPT/MPT on temporary attachment area,QMD engineer shall sign. 6. Internal Cleaning to be checked as per format No: EPCMD-2-QMOO-FMT-PP-011. 7. Before starting 2nd run welding, root weld visual must be cleared for socket weld, any joint for compressor suction line, major pumps, internally lined pipes, lube oil and control oil lin
oxygen line

Siemens Execution Siemens QA/QC Customer Execution Customer QMD


Signature

Name

Date

Unrestricted
EMENS-FOR003

Page: 1 of 1

Internal
Cleaning as per Remarks
Format (Y/N)

YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES

in Remarks. 5. Up on acceptance of
oil and control oil lines, sulfuric acid and

QMD

Unrestricted
SIEMENS Fit Up and Weld Visual Report Format Number: SIEMENS-

Issuing Department PG SU AP IN QM PQM Reviewing Department PG SU AP IN QM PQM Document Type: FOR

Prepared: Dilip Chaudhary Approved By: Mridul sen Gupta Language: En

Project:1X20 MW STG PROJECT Plant:KAMANDA STEEL PLANT Unit:1X20 MW STG System:

Name of Client: M/s RUNGTA MINES LIMITED- KAMANDA Report No:RML/SL/TEE/CD-0270 Date:

ISO/ Line Number: LP HEATER CONDENSATE OUTLET FROM TP TO NEW FEED DEARATOR Piping Class:CARBON STEEL(CS) Service:WATER Pre‐Heat Temperature: 10 0C (Min)

Equipment Drawing Number: Inter Pass Temperature: 150 0C (Max)

Dimensional & Temporary PMI


Sr No. Matcode/Spool No. Heat Number Joint No. Type Of Size (NB) Thickness Allignment Fit-Up Check Fit-up Date WPS Welder Number Root W/V attachment Final Weld Final WV Date Report
(Note-1) Joint (mm) Number (Note:7) NDT Visual ( Note-2 & Note
Check (Note-5) -3)

CD-0270-01 NA J-1 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA


1
CD-0270-01 NA J-2 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
2
CD-0270-01 NA J-3 SW 21.3 3.73 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
3
CD-0270-01 NA J-3a SW 21.3 3.73 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
4
CD-0270-01 NA J-3b SW 21.3 3.73 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
5
CD-0270-01 NA J-3c SW 21.3 3.73 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
6
CD-0270-01 NA J-3d SW 21.3 3.73 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
7
CD-0270-01 NA J-4 SW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
8
CD-0270-01 NA J-5 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
9
CD-0270-02 NA J-6 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
10
CD-0270-02 NA J-7 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
11
CD-0270-03 NA J-8 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
12
CD-0270-03 NA J-9 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-02 OK NA OK 7/26/2021 NA
13
CD-0270-04 NA J-10 BW 168.3 7.11 OK OK 7/20/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
14
CD-0270-04 NA J-11 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
15
CD-0270-05 NA J-12 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
16
CD-0270-05 NA J-13 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
17
CD-0270-06 NA J-14 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
18
CD-0270-06 NA J-15 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
19
CD-0270-06 NA J-16 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
20
CD-0270-06 NA J-17 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
21
CD-0270-07 NA J-18 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
22
CD-0270-07 NA J-19 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
23
CD-0270-07 NA J-20 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
24
CD-0270-07 NA J-21 BW 168.3 7.11 OK OK 7/22/2021 WPS/COND/FAB03 W-01 OK NA OK 7/26/2021 NA
25

Unrestricted
Note :- 1. For LTCS/ NACE/ IBR Material Heat Number shall be recorded . 2. For LAS/ SS/ Non- Ferrous material,upon satisfactory PMI,QMD engineer shall sign . 3. In Case of LTCS and NACE welding consumables batch number shall be recorded. 4. During LTCS welding heat input shall be monitored & recorded in Remarks. 5. Up o
on temporary attachment area,QMD engineer shall sign. 6. Internal Cleaning to be checked as per format No: EPCMD-2-QMOO-FMT-PP-011. 7. Before starting 2nd run welding, root weld visual must be cleared for socket weld, any joint for compressor suction line, major pumps, internally lined pipes, lube oil and control oil lines, sulfuric

Siemens Execution Siemens QA/QC Customer Execution Customer QMD


Signature

Name

Date

Unrestricted
EMENS-FOR003

Page: 1 of 1

Internal
Cleaning as per Remarks
Format (Y/N)

YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES

Unrestricted
arks. 5. Up on acceptance of DPT/MPT
ines, sulfuric acid and oxygen line

QMD

Unrestricted

You might also like