You are on page 1of 19

Daily Meeting Construction

JAWA 9&10 CFSPP (2 x 1,000MW)

13th July 2022


JETTY AREA
WORK STATUS - MAIN WORKS

Work
S/N Location Unit Total Today Accum. M/P Plan for Tomorrow Target Remark
Activity

Pilling nos 23 - 23 Pilling work -


Trestle &
Conveyer
Onshore
Cutting Pile nos 23 - 23 Cutting work -

Pilling nos 26 - 23 Pilling work -

1 Trestle & 67 PDP


Conveyer
Offshore
Cutting pile nos 26 - 23 Cutting work -

Pilling nos 453 - 109 Pilling work -


Jetty &
Mooring
Dolphin Cutting Pile nos 453 - 99 Cutting work 6

Note: Cut off progress - 07:00 AM


PLAN & ACTUAL OF DELIVERY PILE VS PILE DRIVEN

LAST WEEK NEXT WEEK

Stock per 12 July 2022


1. Stock on progress ( finish, coating, install shoe, blasting) = 50 nos
2. Next payment 18 July 2022 equal to 31 nos
3. Next payment 21 July 2022 equal to 36 nos of SPP
SCHEDULE CUTTING PILE
UPDATE JETTY CONDITION
13 July 2022

Offshore trestle Progress SPP till


- Piling = 23 nos (target 26 nos) 13 July 2022
- Cutting = 23 nos Onshore Trestle = 23
Offshore Trestle = 23
Offshore Jetty = 110

Total = 156 nos


Onshore trestle (finished)
- Piling = 23 nos (100%) Offshore jetty = 110 nos
- Cutting = 23 nos (100%) - Pilling = 109 nos (total 453 nos)
- Cutting = 99 nos (progres 119 nos/total 453 nos )
SCHEDULE PRECAST JETTY

LAST WEEK NEXT WEEK


PROGRESS OF MOULDING FABRICATION ( PT Indosupply Mulia Bersama)

PO Moulding from HKAston to PT Indosupply

1. Cross Beam (2000 x 10000) : 1 set wall & 2 table set


2. Cross Beam (1000 x 17000) : 1 set wall & 2 table set
3. Cross beam (900 x 15000) : 1 set wall & 2 table set

Progress per 12 July 2022


1. Moulding Fabrication, Progress (30%):
a. Cross Beam (2000 x 10000) : table 2 set
b. Cross Beam (1000 x 17000) : wall 1 set & table 1 set
c. Long Beam (900 x 15000) : table 2 set
PROGRESS at PT SMI (PRECAST HKA)

Crane 55 Ton 1 unit on site and accessories Casting bed for beam and slab

Casting bed Build a workshop


ECCENTRICITY OF PILLING
DESIGN ACTUAL DEVIATION
PILE TYPE/DIA/THK
(GLOBAL COORDINATE SYSTEM) (GLOBAL COORDINATE SYSTEM) N E DISTANCE
NO (mm) N E N E (MM) (MM) (MM)
J250 SPPØ1016 t=19 mm 9,348,576,406 612,557,010 9,348,576,398 612,557,028 -8 18 20
J249 SPPØ1016 t=19 mm 9,348,578,113 612,555,185 9,348,578,215 612,555,123 102 -62 119
J248 SPPØ1016 t=19 mm 9,348,582,075 612,550,949 9,348,582,231 612,550,973 156 24 158
J247 SPPØ1016 t=19 mm 9,348,586,105 612,546,640 9,348,586,081 612,546,645 -24 5 25
J246 SPPØ1016 t=19 mm 9,348,590,067 612,542,404 9,348,589,902 612,542,312 -165 -92 189
J245 SPPØ1016 t=19 mm 9,348,591,775 612,540,578 9,348,591,719 612,540,546 -56 -32 64
J239 SPPØ1016 t=19 mm 9,348,588,123 612,537,162 9,348,588,246 612,537,312 123 150 194
J240 SPPØ1016 t=19 mm 9,348,586,415 612,538,988 9,348,586,377 612,538,944 -38 -44 58
J241 SPPØ1016 t=19 mm 9,348,582,454 612,543,224 9,348,582,506 612,543,291 52 67 85
J242 SPPØ1016 t=19 mm 9,348,578,423 612,547,533 9,348,578,495 612,547,625 72 92 117
J243 SPPØ1016 t=19 mm 9,348,574,462 612,551,769 9,348,574,441 612,551,724 -21 -45 50
J244 SPPØ1016 t=19 mm 9,348,572,754 612,553,595 9,348,572,854 612,553,732 100 137 170
J233 SPPØ1016 t=19 mm 9,348,584,471 612,533,747 9,348,584,535 612,533,818 64 71 96
J234 SPPØ1016 t=19 mm 9,348,582,764 612,535,573 9,348,582,736 612,535,541 -28 -32 43
J235 SPPØ1016 t=19 mm 9,348,578,802 612,539,809 9,348,578,816 612,539,823 14 14 20
J236 SPPØ1016 t=19 mm 9,348,574,772 612,544,118 9,348,574,765 612,544,002 -7 -116 116
J237 SPPØ1016 t=19 mm 9,348,570,810 612,548,354 9,348,570,743 612,548,276 -67 -78 103
J238 SPPØ1016 t=19 mm 9,348,569,102 612,550,180 9,348,569,165 612,550,255 63 75 98
J232 SPPØ1016 t=19 mm 9,348,565,450 612,546,764 9,348,565,480 612,546,775 30 11 32
J231 SPPØ1016 t=19 mm 9,348,567,158 612,544,938 9,348,567,182 612,544,963 24 25 35
J230 SPPØ1016 t=19 mm 9,348,571,120 612,540,702 9,348,571,191 612,540,737 71 35 79
J229 SPPØ1016 t=19 mm 9,348,575,150 612,536,393 9,348,575,280 612,536,526 130 133 186
J228 SPPØ1016 t=19 mm 9,348,579,112 612,532,157 9,348,579,144 612,532,203 32 46 56
J227 SPPØ1016 t=19 mm 9,348,580,820 612,530,331 9,348,580,891 612,530,403 71 72 101
J221 SPPØ1016 t=19 mm 9,348,577,168 612,526,916 9,348,577,256 612,526,980 88 64 109
J222 SPPØ1016 t=19 mm 9,348,575,460 612,528,742 9,348,575,596 612,528,866 136 124 184
J223 SPPØ1016 t=19 mm 9,348,571,498 612,532,978 9,348,571,537 612,533,014 39 36 53
J224 SPPØ1016 t=19 mm 9,348,567,468 612,537,287 9,348,567,433 612,537,255 -35 -32 47
ECCENTRICITY OF PILLING

GRID 40-36
PLAN AND REBAR ARRANGEMENT OF PIERHEAD
PLAN AND REBAR ARRANGEMENT OF ABUTMENT
BEAM REBAR ARRANGEMENT TRESTLE NEARSHORE &
OFFSHORE
SLAB REBAR ARRANGEMENT TRESTLE NEARSHORE &
OFFSHORE
TYPICAL HEADSTOCK REBAR TRESTLE NEARSHORE &
OFFSHORE
DETAIL PILE HEAD TREATMENT SPP 1016/19
DETAIL PILE HEAD TREATMENT SPP 914/19
THANK YOU