Emergency Repair Plan 2023.06.17
Emergency Repair Plan 2023.06.17
On June 17, 2023 at 16:30 the OCS patrol teams and Rail car drivers
on site who have been on emergency patrol found a broken and fallen
required as follows:
Organization
duty officers, the catenary emergency vehicle teams, Team leader, Safety
and technical education, OCS inspectors and the track operation team in
Personnel organization
number of
S.N project unit Remark
people
staffs
Repair equipment’s
Model
S.N Name unit quantity Remark
Specifications
7 helmet top 15
8 Electroscope pay 2
13 Shovel pcs 10
Specifi
No. Name of material Unit Quantity Remark
cation
4 Top cantilever p 1
5 inclined cantilever p 1
9 Registration pipe p 1
16 concrete plate p 5
17 hook-type screw p 4
20 pin insulator p 4
21 jumper wire m 10
22 rod insulator p 2
After the emergency repair team arrives at the fault point, follow the
Technical procedures
1. After reaching the site, test electricity and install grounding wires on
two sides,
2. Using the rail crane, pick the broken mast from the ground in order to
4. Remove the broken mast, put it away and clean the area,
5. Excavate 3-meter-deep pit to install new mast and install the new
7. Check the angle, backfill and compact the soil to the foundation of
the mast,
8. Measure the distance from the edge of the mast to the mid-point of
the track,
11.Install stay wire on the mast to ground having its standard of length.
14. Adjust the tension of catenary system using the pulley attached to
wires,
16. Measure the height of the contact wire using laser measurement
device,
17. Adjust the height of contact wire using ladder/rail crane if there is
any deviation,
remove the ground wire, evacuate workers and equipment from the
19.After the leader has confirmed the power on, check the electricity
and confirm.