E NGINEERING & General electrical enGineerinG & installation services

commercial, industrial, Hotel/resorts,

P OWER S OLUTIONS
(FiJi) Pte. ltd. inFrastructure & develoPments

reG: rcBs2018l12100 contractors license # 424

Tuesday October 27, 2020

The Unit Leader


Planning & Development Our Ref: CEL/Natabua Subdivision/2020
Energy Fiji LTD
Navutu Depot, Lautoka, Fiji

Attention: Mr. Basant Kumar

Subject: Additional Documentation & 11kV Services Quote Request for The Natabua Residential

Subdivision Developed by Challenge Engineering Ltd.

The following are additional documentations in reference to the Challenge Subdivision Project which we will submit in hard
copy as well as soft copies.

Table of Content:
1. This Document with Table of Content + Request for 11kV Services Quotation.
2. Approved Subdivision Scheme Plan in A3
3. 11KV Single Line Diagram with Scope of Works Description.
4. Subdivision Locality & 11kV Extension Route Image.
5. High Voltage Cable Route for TX 1 & 2
6. High Voltage Drop Calculation
7. Cable Schedule & Voltage Drop Worksheet TX1 in A3
8. Cable Schedule & Voltage Drop Worksheet TX2 in A3
9. TX1 Circuit Maximum Demand
10. TX2 Circuit Maximum Demand
11. Road Crossing Category “A” U/G Trenching Details
12. Typical Reticulation Category “B” U/G Trenching Details
13. Subdivision Street Light Distribution
14. Olex 11kV 3C/Al/CWS/MDPE Cable Data
15. Raychem Termination Kit Data
16. Tyree 500KVA TX Nameplate
17. Tyree 300KVA TX Nameplate
18. Tyree 300/500TX Layout & Assembly

EPS Overall Scope of Works (Pad Mount Transformer & Complete LV Reticulation)
Our proposal & designs for the proposed project is based on the following scopes;
 Our offer is contingent of the Design and Submission being approved by EFL.
 Supply and installation of 1x 500KVA Pad Mount Transformers. Location at corner of Road 1 and Road 6.
 Supply and installation of 1x 300KVA Pad Mount Transformers. Location at corner of Road 2 and Road 7.
 Supply & Installation of Underground High Voltage Cable for TX 1 from designated 11kV EFL Network.
 Supply & Installation of Underground High Voltage Cable for TX 2 from designated 11kV EFL Network.
 Supply and Installation of High Voltage termination kits & Termination works for both TX1 & TX2.

Your enGineerinG Partners


293 Sukanaivalu Road, Lautoka. TIN: 50-57227-0-6
P.O. Box D110, Lautoka Email: epowersolutionsltka@gmail.com
Phone: (+679) 973-0449 / 836-5288 / 836-3334
E NGINEERING & General electrical enGineerinG & installation services
commercial, industrial, Hotel/resorts,

P OWER S OLUTIONS
(FiJi) Pte. ltd. inFrastructure & develoPments

reG: rcBs2018l12100 contractors license # 424

 Supply & Installation of Low Voltage Fuses as required for LV Reticulation for both TX1 & TX2.
 Supply & Installation of 44x Pillar Boxes. Including 1x PB for Park Distribution.
 Supply and installation all electrical components for pillar boxes. Including Service Fuse Holder & Fuses for
Lot distribution, Insulating Panel, Neutral Links, & all associated materials required to complete installation.
 Supply & Installation of Underground XLPE Cable from TX to designated Pillar Boxes to complete entire LV
Reticulation.
 Supply & Installation of all Lugs, Bolts & Nuts, Insulation & Phase Indication to complete entire LV
Reticulation.
 Supply & Installation of Ducting/Conduits for High & Low Voltage Road Crossing for Cable Circuits.
 Supply and installation of Underground Rubber Cement Slab & Marker Tape for Entire HV/LV Reticulation
Distribution.
 Supply and installation of earthing system for all required equipment.
 Testing and commissioning of our portion of works.
 All work will be in conformity to AS/NZS 3000/2067 Rules, Local or Governing Authority, Building & Fire
Authority Regulations, Design & your personal requirements.

Request for EFL Quotation for 11kV Portion of Works:

EPS would like to request EFL for Quotation for 11kV Installation for the following scopes:

1. Supply & Installation of 11kV Fuse Unit for TX1 (500KVA). At Queens Road & Tramline Road Junction
2. Associated Works for Fuse Unit TX1 Circuit Installation Works.
3. Termination (only) to Fuse Unit for TX1 Circuit.
4. Supply & Installation of 11kV Fuse Unit for TX2 (300KVA). At Field 40 & Duvavata Temple Road Junction.
5. Associated Works for Fuse Unit for TX2 Circuit Installation Works.
6. Termination (only) to Fuse Unit for TX2 Circuit.

Conclusion:
We thank you and hope our submission is to your satisfaction, however should you require any detailed information, please do
not hesitate to contact our office on the contacts below.

We look forward to hearing from you soon.

HIRENDRA V SHARMA
(Manager) Projects
(679) 707-2505 / 973-0449
epowersolutionsltka@gmail.com

Your enGineerinG Partners


293 Sukanaivalu Road, Lautoka. TIN: 50-57227-0-6
P.O. Box D110, Lautoka Email: epowersolutionsltka@gmail.com