Professional Documents
Culture Documents
GEOSS Understanding and Mitigating Geotechnical Risk in Underground Construction
GEOSS Understanding and Mitigating Geotechnical Risk in Underground Construction
geotechnical risk in
underground construction
20th September 2023
Nick Osborne
Major Projects Director
15 February 2023
1 Introduction
6 Case studies
7 Conclusion
Introduction
Mott MacDonald
Background
Experiences, learning and diversity
Mott MacDonald
Urbanisation
Key driver of Infrastructure
100
• Countries need to invest in their
infrastructure 90
70
• Drives business investment
60
• Role of the engineer
50
40
30
20
10
0
1940 1950 1960 1970 1980 1990 2000 2010 2020 2030 2040
Mott MacDonald
“Civil Engineering is the art of
directing the great sources of power
in nature to improve society”
Institution of Civil Engineers
Underground
congestion:
an increasing
problem
Urban tunnelling
is a challenge
More Challenging Projects - North South Corridor Singapore
Permanent
bored pile
DTL Tunnels
GI Treatment
D-wall
Mott MacDonald
What is the Consequence of loss?
Average
• US$ 32.5 million
• 14 months
Mott MacDonald
What are the key The Design
challenges faced Ground Approval
in underground
construction?
Achieving
the Stakeholder
programme engagement
Volume of
Safety
Information
Interfacing Operations
How big of a
challenge is the
ground?
Mott MacDonald
What is the biggest source of risk?
70
60
50
40
30
20
10
0
Geotechnics Contamination Obstructions Services Detailed Design Miscallaneous
Geotechnical sources of Construction problem (source Clayton et al 2001)
Mott MacDonald
Cause of global collapses – Bored/mined tunnel
26%
7%
17%
4 boreholes
Soft = 30m
Mixed = 30m
Rock = 110m
15 boreholes
Soft = 60m
Mixed = 95m
Rock = 15m
Mott MacDonald
Do not underestimate issues driven by ground water flow
Mott MacDonald
Sophisticated leapfrog – Ground model
Mott MacDonald
Effective design
processes
Mott MacDonald
Geological processes
6 5
Monitoring, 4 Construction
tests and site processes
observations Empiricism
Case histories
2
Knowledge 3
Idealisation
Modelling analysis
Validation
Ground Appropriate
Behaviour Model
Measurement
Lab & field testing
Observation
Mott MacDonald
What tools do we have available?
Mott MacDonald
Mott MacDonald
Digital design leads to carbon reduction
2000 tonnes
Reference design of C02 saved Approved design
Mott MacDonald
Carbon calculation
Moata Carbon Portal
Mott MacDonald
Construction
processes - feedback
Mott MacDonald
Verification of the Design
Essential component of the process
Approved Design
Mott MacDonald
Case studies
Mott MacDonald
Case study 1 – Singapore river crossing
Mott MacDonald
The Project
Mott MacDonald
Major concerns
• Program risk
• Construction risk
• Environmental impact
• Public and tourist perception
• Safety
• Impact on adjacent structures – CTE
• Potential obstructions
Mott MacDonald
33
Potential obstructions
Mott MacDonald
34
Key design considerations
Mott MacDonald
Construction sequence
Back fill
Construction of Construction of Launching of
Ground Improvement
Canal (42m) Coffer Dam TBM
Removal of Anchor
Complete
replacement of river
42m
Mott MacDonald
Construction sequence
Back fill
Construction of Construction of Launching of
Ground Improvement
Canal (42m) Coffer Dam TBM
Removal of Anchor
Coffer Dam to
create dry
working using
geo bags
Mott MacDonald
Construction sequence
Back fill
Construction of Construction of Launching of
Ground Improvement
Canal (42m) Coffer Dam TBM
Removal of Anchor
Ground Improvement
for TBM Driving
Mott MacDonald
Construction sequence
Back fill
Construction of Construction of Launching of
Ground Improvement
Canal (42m) Coffer Dam TBM
Removal of Anchor
TBM Driving
Mott MacDonald
River crossing site
Mott MacDonald
Obstructions
Mott MacDonald
River wall obstructions
Mott MacDonald
Noise & dust
Mott MacDonald
Key reasons for success
Mott MacDonald
Jakarta Metro
Pemuda Statue -
Engineering the
Risk Out
Mott MacDonald
Conclusion
Mott MacDonald
Conclusion
Lessons learned from my experience
1 2 3 4 5
Risk Processes Team Learn Experience
• Geotechnical risk • Identify risk • Work as a team – • Learn from yours Large number of tools
is the largest • Mitigate risk pulling in the right and team member available but nothing
challenge to major direction mistakes beats experience
underground • Monitor risk
• Communication
infrastructure • Understanding • lessons learned
and understanding
contractual reviewed as a team
of team skillsets
• Problem solving obligations - so everyone
risks and turning • Health, safety and learns together
them into wellbeing, at the
opportunities forefront of every
team
Mott MacDonald
Q&A
Thank you