Joint Measurement Sheet: 1 25/03/2023 KY/SLOPE&DRAIN-OCM/CON/01/2022 Taisun Bina
Joint Measurement Sheet: 1 25/03/2023 KY/SLOPE&DRAIN-OCM/CON/01/2022 Taisun Bina
CONTRACT TITLE : CONSTRUCTION AND COMPLETION OF DRAINAGE IMPROVEMENT WORKS AT KOLEJ YAYASAN UEM (KYUEM),
LEMBAH BERINGIN, SELANGOR DARUL EHSAN.
WORKS DESCRIPTION : BILL NO. 2 - DRAINAGE IMPROVEMENT WORKS (ALL QUANTITIES ARE PROVISIONAL)
ITEM
DESCRIPTION UNIT QUANTITY
NO.
Excavation
2.2 Q111.1 - Surface Drain (Half Round Drain Width 300mm wide) m 0
Calculation: Recurring to pay based on work progress
Allocation Total to date
Initial 0m 7,250.00 -
Recurring 0m - -
Completion 0m - -
% of work progress to date = 0.00%
Previous claim = -
Amount for this claim = -
Amount to date = -
2.3 Q111.2 - Surface Drain (Half Round Drain Width 350mm wide) m 14m
Calculation: Recurring to pay based on work progress
Allocation Total to date
Initial 14m 700.00 700.00
Recurring 0m - -
Completion 0m - -
% of work progress to date = 5.556%
Previous claim = -
Amount for this claim = 700.00
Amount to date = 700.00
I/We acknowledge and confirm the above mentioned works done and materials on site are in accordance with the terms and conditions, drawings,
specifications and in accordance with the Contract Document.
D2-10
JOINT MEASUREMENT SHEET
CONTRACT TITLE : CONSTRUCTION AND COMPLETION OF DRAINAGE IMPROVEMENT WORKS AT KOLEJ YAYASAN UEM (KYUEM),
LEMBAH BERINGIN, SELANGOR DARUL EHSAN.
WORKS DESCRIPTION : BILL NO. 2 - DRAINAGE IMPROVEMENT WORKS (ALL QUANTITIES ARE PROVISIONAL)
ITEM
DESCRIPTION UNIT QUANTITY
NO.
2.22 Q230.2 - Drain (Precast half round drain width 350mm wide) m 14m
Calculation: Recurring to pay based on work progress
Allocation Total to date
Initial 14m 7,000.00 7,000.00
Recurring 0m - -
Completion 0m - -
% of work progress to date = 5.556%
Previous claim = -
Amount for this claim = 7,000.00
Amount to date = 7,000.00
2.23 Q230.3 - Drain (Precast half round drain width 450mm wide) m 0
Calculation: Recurring to pay based on work progress
Allocation Total to date
Initial 0m 58,000.00 -
Recurring 0m - -
Completion 0m - -
% of work progress to date = 0.00%
Previous claim = -
Quantity for this claim = -
Quantity to date = -
2.24 Q230.4 - Drain (Precast half round drain width 550mm wide) m 0
Calculation: Recurring to pay based on work progress
Allocation Total to date
Initial 0m 19,610.00 -
Recurring 0m - -
Completion 0m - -
% of work progress to date = 0.00%
Previous claim = -
Amount for this claim = -
Amount to date = -
I/We acknowledge and confirm the above mentioned works done and materials on site are in accordance with the terms and conditions, drawings,
specifications and in accordance with the Contract Document.