Chequeo de Los Fet en Inverter
Chequeo de Los Fet en Inverter
System: Mx Twin
Lecture/Demo: N/A
Special Tools/Procedures:
Procedure:
Note:
Inverter FET check should be performed every 6 months!!!!
FET Check
2. There are 40 FETs in each Inverter.
Verify with a multimeter that the voltage between Drain and Source is between 0.3 V – 0.5 V.
(The multimeter should be in diode check position.)
3. If the voltage between Drain & Source exceeds the above voltage, replace the FET or the Inverter.
SOURCE
GATE