WEEKLY REPORT

PERIOD : NOVEMBER 29 - NOVEMBER 30 (WEEK - 4)


YEAR : 2021

JICA PROJECT TEAM, SANYU CONSULTANS INC.


THE EAST TOWER 17TH FLOOR, JAKARTA, JL. DR. IDE ANAK. AGUNG GDE AGUNG KAR,. E1.2 NO.1,
JAKARTA SELATAN 12950

CONSTRUCTION OF A NEW WAREHOUSE FOR THE SINAR MUKTI FARMER GROUP


TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY

CONTRACTOR : CV. ANUGRAH KARYA BERSAMA


JL. KARASAK BARU NO.32 RT.006 RW.002 BANDUNG
WEEKLY REPORT JICA PROJECT TEAM, SANYU CONSULTANS INC. CONTRACTOR :

THE EAST TOWER 17TH FLOOR, JAKARTA, JL. DR. IDE ANAK. AGUNG GDE AGUNG KAR,. E1.2 NO.1, CV. ANUGRAH KARYA BERSAMA
PERIOD : NOVEMBER 29 - NOVEMBER 30 JAKARTA SELATAN 12950
JL. KARASAK BARU NO.32 RT.006 RW.002
BANDUNG
YEAR : 2021
PROJECT : CONSTRUCTION OF A NEW WAREHOUSE FOR THE SINAR MUKTI FARMER GROUP

4TH WEEK LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY

MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED WEEKLY PROGRESS
1 - WORK ITEMS WEIGHT (%)
SKILL D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL
2 - 1 Sand Fill 50 mm P 0,25%
3 - 2 Plastering + Glaring P 1,73%
1 Head Builder 2 1 - - - - - 3 man 4 - 3 Septic Tank Work P 0,15%
2 Bricklayer 2 2 - - - - - 4 man 5 4 P
3 Blacksmith 2 - - - - - - 2 man 6 5 P
4 Carpenter - - - - - - - - man 7 6 P
5 Painter - - - - - - - - man 8 7 P
6 Worker 1 1 - - - - - 2 man 9 8 P
7 Foreman/Superintendent 1 1 - - - - - 2 man 10 9 P
8 etc. - - - - - - - - man 11 - 10 P
12
13
14
THIS WEEK PROGRESS 2,14%
15

WORK BEGINS : 07:00 WORK ENDS : 17:00 REMARKS SUPERVISOR'S NOTES :

WHEATHER D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL


LAST WEEK PROGRESS TOTAL PROGRESS
WEIGHT (%)
H 0 1 0 0 0 0 0 1. 1ST WEEK PROGRESS P 25,16% WORK DONE WEIGHT (%)
P RAIN
M 0 -1 0 0 0 0 0
0,98 H
2. 2ND WEEK PROGRESS P 18,81% 1 LAST WEEK PROGRESS P 63,98%
3. 3RD WEEK PROGRESS P 20,01% 2 THIS WEEK PROGRESS (W-3) P 2,14%
H 0 0 0 0 0 0 0
BRIGHT 0,00 H
M 0 0 0 0 0 0 0 TOTAL LAST WEEK PROGRESS 63,98% TOTAL PROGRESS 66,12%

H 0 0 0 0 0 0 0
OVERCAST 0,00 H
M 0 0 0 0 0 0 0

APPROVED BY CHECKED BY: MADE BY: VALIDATED BY:

SONY SYAFARI EEP HERRY K AGUS WARYONO


Project Manager Site Manager Field Supervisor JICA PROJECT TEAM
DAILY REPORT JICA PROJECT TEAM, SANYU CONSULTANS INC. CONTRACTOR :
THE EAST TOWER 17TH FLOOR, JAKARTA, JL. DR. IDE ANAK. AGUNG GDE AGUNG KAR,. E1.2 NO.1, CV. ANUGRAH KARYA BERSAMA
DAY : MONDAY JAKARTA SELATAN 12950
JL. KARASAK BARU NO.32 RT.006 RW.002
DATE : NOVEMBER 29, 2021 BANDUNG
PROJECT : CONSTRUCTION OF A NEW WAREHOUSE FOR THE SINAR MUKTI FARMER GROUP

1ST DAY LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY

MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED TODAY'S WORK
SKILL TOTAL
1 Completion of the installation Steel Roof Truss Canal C
1 Head Builder 2 man 2 Plastering Wall
2 Bricklayer 2 man 3 Continue work of Septictank
3 Blacksmith 2 man 4
4 Carpenter - man 5
5 Painter - man 6
6 Worker 1 man 7
7 Foreman/Superintendent 1 man 8
8 etc. - man 9

WORK BEGINS : 07:00 WORK ENDS : 17:00 SUPERVISOR'S NOTES :


WHEATHER BEGINS ENDS REMARKS:

H 0
P RAIN 00 : 00 00 : 00
M 0

H 0
BRIGHT 00 : 00 00 : 00
M 0

H 0
OVERCAST 00 : 00 00 : 00
M 0

APPROVED BY CHECKED BY: MADE BY:

SONY SYAFARI EEP HERRY K AGUS WARYONO


Project Manager Site Manager Field Supervisor
PHOTOGRAPHS
DAILY REPORT JICA PROJECT TEAM, SANYU CONSULTANS INC. CONTRACTOR :
THE EAST TOWER 17TH FLOOR, JAKARTA, JL. DR. IDE ANAK. AGUNG GDE AGUNG KAR,. E1.2 NO.1, CV. ANUGRAH KARYA BERSAMA
DAY : TUESDAY JAKARTA SELATAN 12950
JL. KARASAK BARU NO.32 RT.006 RW.002
DATE : NOVEMBER 30, 2021 BANDUNG
PROJECT : CONSTRUCTION OF A NEW WAREHOUSE FOR THE SINAR MUKTI FARMER GROUP

2ND DAY LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY

MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED TODAY'S WORK
SKILL TOTAL
1 Red Bricks Plastering Wall
1 Head Builder 1 man 2 Continue work of Septictank
2 Bricklayer 2 man 3
3 Blacksmith - man 4
4 Carpenter - man 5
5 Painter - man 6
6 Worker 1 man 7
7 Foreman/Superintendent 1 man 8
8 etc. - man 9
10

WORK BEGINS : 07:00 WORK ENDS : 17:00 SUPERVISOR'S NOTES :


WHEATHER BEGINS ENDS REMARKS:

H 1
P RAIN 11 : 00 12 : 01
M -1

H 0
BRIGHT 00 : 00 00 : 00
M 0

H 0
OVERCAST 00 : 00 00 : 00
M 0

APPROVED BY CHECKED BY: MADE BY:

SONY SYAFARI EEP HERRY K AGUS WARYONO


Project Manager Site Manager Field Supervisor
PHOTOGRAPHS
TIME SCHEDULLE (PLAN vs ACTUAL AT NOVEMBER 30, 2021)
(CONCRETE FRAME CONSTRUCTION)
PROJECT : WAREHOUSE DEVELOPMENT
WORK : SINAR MUKTI WAREHOUSE BUILDING
LOCATION: TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG Bandung, November 8, 2021

MONTH - 1 MONTH - 2 MONTH - 2


WEIGHT
NO WORK ITEMS VOL-UNIT W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8
(%)
H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-1 H-2 H-3 H-4 H-5 H-6 H-7
I. PREPARATORY WORK
1 Mobilization & Demobilization 1,00 ls 4,02% 4,02%
2 Setting Out - ls 0,00%
3 Temporary Shelter 20,00 m2 4,87% 4,87%
4 Temporary Warehouse 20,00 m2 3,78% 3,78%

II, STRUCTURE WORK


A. FOUNDATION WORK
1 Soil Excavation 14,40 m3 0,28% 0,14% 0,14%
2 Sand Fill 50 mm 1,44 m2 0,01% 0,01%
3 Working Floor 50 mm 1,44 m2 0,03% 0,03%
4 Concrete Foundation Treads & Stump Columns 8,72 m3 12,12% 2,42% 2,42% 2,42% 2,42% 2,42%
5 Landfill 2,80 m3 0,03% 0,03%
6 Land Disposal 2,80 m3 0,06% 0,03% 0,03%
B. FLOOR WORK
1 Smoothing and Compaction 72,00 m2 0,21% 0,21%
2 Basecourse Fill 200 mm - m2 0,00%
3 Sand Fill 50 mm 72,00 m2 0,48% 0,10% 0,13% 0,13% 0,13%
4 Plastic Sheet 72,00 m2 0,18% 0,18%
5 Concrete Floor K-200 H=120 Whiremes M8 8,64 m3 10,53% 2,63% 2,63% 2,63% 2,63%
66,12%
C. STRUCTURE WORK 64,97%
3
63,98%
1 Sloof of Reinforced Concrete 20X20 3,00 m 5,68% 0,95% 0,95% 0,95% 0,95% 0,95% 0,95%
2 Concrete Column 25X25 2,50 unit 5,52% 0,92% 0,92% 0,92% 0,92% 0,92% 0,92%
60,47%
3 Ringbalk 15x20 2,72 unit 5,49% 1,10% 1,10% 1,10% 1,10% 1,10%
D. ROOF WORK 57,63%

1 Lightweight Steel Roof Truss Canal C 98,64 m2 5,75% 1,15% 1,15% 1,15% 1,15% 1,15%
2 Zincalume spandex Roof, 0.5 mm 118,37 m2 7,38% 0,74% 0,74%53,69%
0,74% 0,74% 0,74% 1,85% 1,85%
3 Gutter 9,00 m1 0,28% 0,03% 0,03% 0,03% 0,03% 0,03% 0,07% 0,07%
4 Flashing zincalume 118,37 m2 4,21% 0,42%50,25%
0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42%

III. ARCHITECTURAL WORK


46,82%
A. FLOOR FINISHING WORK 45,50%
1 Floorhardener natural 5kg/m2 F0 72,00 m2 1,63% 43,97% 43,97% 0,41% 0,41% 0,41% 0,41%
B. WALL WORK
1 Hebel Brick Wall 114,50 m2 5,99% 1,00% 1,00% 1,00% 1,00% 1,00%40,31%
1,00%
2 Plastering + Glaring 229,00 m2 7,58% 0,51% 0,51% 0,51% 0,87% 0,87% 0,87% 0,87% 0,87% 0,87% 0,87%
36,65%
3 Installation of Harmonica Ram 10,40 m2 1,59% 0,79% 0,79%
4 Skonengan 21,00 m2 0,05% 33,79% 0,01% 0,01% 0,01% 0,01%
C. PAINTING WORK
30,92%
1 Exterior Wall Painting 114,50 m2 1,60% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18%
2 Interior Wall Painting 114,50 m2 1,23% 28,06% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14%
D. SANITARY WORK
1 SITTING CLOSET, CW 660 NJ / SW 660 J 1,00 unit 0,97% 25,16% 0,97%
2 Clean & Dirty Water Pipes 1,00 Ls 0,80% 22,74% 0,80%
3 Bathroom Faucet 2,00 unit 0,08% 0,08%
20,31%
4 Mirror 1,00 unit 0,13% 0,13%
17,89%
5 Fiber Tub 1,00 unit 0,34% 0,34%
6 Septic Tank Work 1,00 set 0,90% 15,43% 0,23% 0,23% 0,15% 0,15% 0,15%
E. DOOR AND WINDOW FRAMEWORK 12,81%
1 Rolling Door 10,40 m2 2,84% 0,57% 2,27%
2 Fiber Door for Bathroom 1,00 unit 0,95% 0,95%
F. CEILING WORK
1 Gypsum Bathroom Ceiling 5,00 m2 0,23% 0,23%
G. LIGHTING INSTALLATION WORK
1 Installation of Light Point 4,00 point 0,46% 0,15% 0,15% 0,15%
2 Installation of outlet points 10,00 point 1,73% 0,00% 0,58% 0,58% 0,58%

WEEKLY WEIGHT PROGRESS (ACTUAL) 100,00% 0,00% 12,81% 2,62% 2,45% 2,42% 2,42% 2,42% 2,90% 2,86% 2,86% 2,86% 3,66% 3,66% 0,00% 1,53% 1,32% 3,44% 3,44% 3,94% 2,84% 3,51% 0,99% 1,14% 3,41% 3,30% 1,37% 4,18% 6,20% 2,95% 2,95% 0,72% 0,72% 0,72% 0,72% 4,55% 1,04% 1,04% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%

CUMULATIVE WEEKLY WEIGHT PROGRESS (ACTUAL) 0,00% 12,81% 15,43% 17,89% 20,31% 22,74% 25,16% 28,06% 30,92% 33,79% 36,65% 40,31% 43,97% 43,97% 45,50% 46,82% 50,25% 53,69% 57,63% 60,47% 63,98% 64,97% 66,12% 69,53% 72,82% 74,19% 78,37% 84,58% 87,52% 90,47% 91,19% 91,91% 92,64% 93,36% 97,91% 98,96% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

WEEKLY WEIGHT PROGRESS (PLAN) 100,00% 0,00% 12,76% 2,53% 2,57% 2,44% 2,42% 2,46% 0,81% 0,81% 0,81% 0,81% 0,81% 0,81% 0,81% 1,76% 1,76% 1,76% 1,76% 1,76% 1,76% 1,76% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 1,84% 1,84% 1,84% 1,84% 1,84% 1,84% 1,84% 1,61% 1,61% 1,61% 1,61% 1,61% 1,61% 1,61% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 0,52% 0,52% 0,52% 0,20% 0,20% 0,20% 0,20%

CUMULATIVE WEEKLY WEIGHT PROGRESS (PLAN) 0,00% 12,76% 15,30% 17,87% 20,31% 22,74% 25,19% 26,00% 26,81% 27,62% 28,44% 29,25% 30,06% 30,87% 32,62% 34,38% 36,14% 37,89% 39,65% 41,40% 43,16% 45,33% 47,49% 49,66% 51,83% 53,99% 56,16% 58,33% 60,16% 62,00% 63,83% 65,67% 67,50% 69,34% 71,17% 72,78% 74,39% 76,00% 77,61% 79,22% 80,83% 82,44% 84,61% 86,78% 88,95% 91,11% 93,28% 95,45% 97,62% 98,14% 98,67% 99,19% 99,39% 100% 100% 100%