Professional Documents
Culture Documents
THE EAST TOWER 17TH FLOOR, JAKARTA, JL. DR. IDE ANAK. AGUNG GDE AGUNG KAR,. E1.2 NO.1, CV. ANUGRAH KARYA BERSAMA
PERIOD : NOVEMBER 29 - NOVEMBER 30 JAKARTA SELATAN 12950
JL. KARASAK BARU NO.32 RT.006 RW.002
BANDUNG
YEAR : 2021
PROJECT : CONSTRUCTION OF A NEW WAREHOUSE FOR THE SINAR MUKTI FARMER GROUP
4TH WEEK LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED WEEKLY PROGRESS
1 - WORK ITEMS WEIGHT (%)
SKILL D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL
2 - 1 Sand Fill 50 mm P 0,25%
3 - 2 Plastering + Glaring P 1,73%
1 Head Builder 2 1 - - - - - 3 man 4 - 3 Septic Tank Work P 0,15%
2 Bricklayer 2 2 - - - - - 4 man 5 4 P
3 Blacksmith 2 - - - - - - 2 man 6 5 P
4 Carpenter - - - - - - - - man 7 6 P
5 Painter - - - - - - - - man 8 7 P
6 Worker 1 1 - - - - - 2 man 9 8 P
7 Foreman/Superintendent 1 1 - - - - - 2 man 10 9 P
8 etc. - - - - - - - - man 11 - 10 P
12
13
14
THIS WEEK PROGRESS 2,14%
15
H 0 0 0 0 0 0 0
OVERCAST 0,00 H
M 0 0 0 0 0 0 0
1ST DAY LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED TODAY'S WORK
SKILL TOTAL
1 Completion of the installation Steel Roof Truss Canal C
1 Head Builder 2 man 2 Plastering Wall
2 Bricklayer 2 man 3 Continue work of Septictank
3 Blacksmith 2 man 4
4 Carpenter - man 5
5 Painter - man 6
6 Worker 1 man 7
7 Foreman/Superintendent 1 man 8
8 etc. - man 9
H 0
P RAIN 00 : 00 00 : 00
M 0
H 0
BRIGHT 00 : 00 00 : 00
M 0
H 0
OVERCAST 00 : 00 00 : 00
M 0
2ND DAY LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED TODAY'S WORK
SKILL TOTAL
1 Red Bricks Plastering Wall
1 Head Builder 1 man 2 Continue work of Septictank
2 Bricklayer 2 man 3
3 Blacksmith - man 4
4 Carpenter - man 5
5 Painter - man 6
6 Worker 1 man 7
7 Foreman/Superintendent 1 man 8
8 etc. - man 9
10
H 1
P RAIN 11 : 00 12 : 01
M -1
H 0
BRIGHT 00 : 00 00 : 00
M 0
H 0
OVERCAST 00 : 00 00 : 00
M 0
1 Lightweight Steel Roof Truss Canal C 98,64 m2 5,75% 1,15% 1,15% 1,15% 1,15% 1,15%
2 Zincalume spandex Roof, 0.5 mm 118,37 m2 7,38% 0,74% 0,74%53,69%
0,74% 0,74% 0,74% 1,85% 1,85%
3 Gutter 9,00 m1 0,28% 0,03% 0,03% 0,03% 0,03% 0,03% 0,07% 0,07%
4 Flashing zincalume 118,37 m2 4,21% 0,42%50,25%
0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42%
WEEKLY WEIGHT PROGRESS (ACTUAL) 100,00% 0,00% 12,81% 2,62% 2,45% 2,42% 2,42% 2,42% 2,90% 2,86% 2,86% 2,86% 3,66% 3,66% 0,00% 1,53% 1,32% 3,44% 3,44% 3,94% 2,84% 3,51% 0,99% 1,14% 3,41% 3,30% 1,37% 4,18% 6,20% 2,95% 2,95% 0,72% 0,72% 0,72% 0,72% 4,55% 1,04% 1,04% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
CUMULATIVE WEEKLY WEIGHT PROGRESS (ACTUAL) 0,00% 12,81% 15,43% 17,89% 20,31% 22,74% 25,16% 28,06% 30,92% 33,79% 36,65% 40,31% 43,97% 43,97% 45,50% 46,82% 50,25% 53,69% 57,63% 60,47% 63,98% 64,97% 66,12% 69,53% 72,82% 74,19% 78,37% 84,58% 87,52% 90,47% 91,19% 91,91% 92,64% 93,36% 97,91% 98,96% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
WEEKLY WEIGHT PROGRESS (PLAN) 100,00% 0,00% 12,76% 2,53% 2,57% 2,44% 2,42% 2,46% 0,81% 0,81% 0,81% 0,81% 0,81% 0,81% 0,81% 1,76% 1,76% 1,76% 1,76% 1,76% 1,76% 1,76% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 1,84% 1,84% 1,84% 1,84% 1,84% 1,84% 1,84% 1,61% 1,61% 1,61% 1,61% 1,61% 1,61% 1,61% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 0,52% 0,52% 0,52% 0,20% 0,20% 0,20% 0,20%
CUMULATIVE WEEKLY WEIGHT PROGRESS (PLAN) 0,00% 12,76% 15,30% 17,87% 20,31% 22,74% 25,19% 26,00% 26,81% 27,62% 28,44% 29,25% 30,06% 30,87% 32,62% 34,38% 36,14% 37,89% 39,65% 41,40% 43,16% 45,33% 47,49% 49,66% 51,83% 53,99% 56,16% 58,33% 60,16% 62,00% 63,83% 65,67% 67,50% 69,34% 71,17% 72,78% 74,39% 76,00% 77,61% 79,22% 80,83% 82,44% 84,61% 86,78% 88,95% 91,11% 93,28% 95,45% 97,62% 98,14% 98,67% 99,19% 99,39% 100% 100% 100%