ADVANCED RISK ASSESSMENT (ARA)

Country / Location: K.S.A / Date: 9-NOV.-19


Description of Job or MULTIPLE LIFT OF MAST TO SUB BASE AND SET ON MAST STAND Rig#: 210
Work Activity:
ARA#: Rev:
Residual Acceptable?
Specific Job steps / Work Initial Risk Control measures to reduce the
No Hazards or Potential Incidents Risk Tolerable?
Sequence risk
L S IR L S IR Unacceptable?
1 PRE TOUR SAFETY MTG BAD COMMUNICATION, C 3 C3 ASSURE TRANSLATOR IN THE A 2 A2 ACCEPTABLE
LANGUAGE BARRIER MEETING, ASSURE EVERYONE
UNDERSTANDS THERE JOB
RESPONCIBILITIES BEFORE
STARTING TASK. DISCUSS THE
POTENTIAL HAZARDS WE CAN
ENCOUNTER AND THE
SOLUTIONS ON HOW TO
ELIMINATE THE RISK.
2 GATHER TOOLS AND SLIPS, TRIPS, FALLS, B 3 B3 BE AWARE OF THE B 2 B2 ACCEPTABLE
EQUIPMENT AND INSPECT HAZARDS IN THE WORK SURROUNDINGS, REMOVE
MAST FOR ANYTHING AREA, DAMAGED ANYTHING THAT DOES NOT
LAYING ON ARE NOT EQUIPMENT, UNCERTIFIED NEED TO BE IN THE AREA,
PROPERLY INSTALLED EQUIPMENT, DROPS, VISUALLY INSPECT ALL
BEFORE LIFT IMPROPER RIGGING OF EQUIPMENT, AND ASSURE
EQUIPMENT IN MAST, CERTIFIED, DO A 360 DEGREES
MISSING BOLTS, LOOSE MAST CHECK AND INSPECTION
BOLTS SHACKLES WITHOUT WITH ALL PERSONEL ASSURE
PINS, PINS WITHOUT NOTHING LAYING INSIDE ARE
KEEPERS, HOMEMADE ON MAST, AND ALL SAFETY
TOOLS PRECAUTIONS IN PLACE AND
PROPER. USE ONLY THE RIGHT
TOOLS FOR THE JOB. HOME
MADE TOOLS ARE STRICLY
PROHIBITED

If the residual risk is High, the job shall not proceed

F0858 (0) Original – Rig Files Copy – Area Office Page 1 of 4


ADVANCED RISK ASSESSMENT (ARA)
3 POSITION CRANES MISCALCULATION ON B 4 B4 ASSURE BANKSMAN PRESENT, A 3 A3 ACCEPTABLE
SPOTTING THE CRANE, LINE RIGGER ONE TO SPOT CRANES,
OF FIRE, CAUGHT IN APPROVED LIFT PLAN AND
BETWEEN, TRAFFIC, UNEVEN CALCULATIONS; CLEAR THE
GROUND AREA WHILE CRANES MOVING
IN, BARRACADE AROUND THE
CRANES AFTER SPOTTED.
ENSURE GROPUN IS EVEN AND
STURDY TO SUPPORT CRANE
WEIGHT, ONLY RIGGER 1 TO
POSITION CRANES

4 RIG UP SLINGS ON CRANE IMPROPER EQUIPMENT, B 3 B3 ASSURE RATED AND B 2 B2 ACCEPTABLE


HOOK AND ATTACH TO DAMAGED EQUIPMENT, INSPECTED SLINGS, RIGGER
DERRICK WITH THE GENIE PINCH POINTS, DROPS, LINE ONE TO PICK THE
OF FIRE, FALLING, CAUGHT APPROPRIATE SLINGS FOR THE
IN BETWEEN, GENIE JOB, WATCH HAND PLACMENT,
DAMAGED WQUIPMENT, USE DON’T STAND UNDER CRANE
GENIE TO ACCESS POINT OF HOOK OR GENIE BASKET, USE
ATTACHING SLINGS TO BANKSMAN FOR GENIE,100%
MAST. TIED OFF, ASSURE GENIE
CHECKLIST DONE AND RESCUE
PLAN IN PLACE BEFORE USE

5 LIFT MAST SWING WITH DROPPED OBJECTS, LINE OF C 4 B4 VISUAL CHECK ON ALL B 2 B2 ACCEPTABLE
CRANES TO POSITION AND FIRE,BAD SIGNALS, EQUIPMENT THAT HAS THE
PIN MAST TO SUB BASE SWINGING POTENTIAL TO DROP .ONLY
SHOES LOAD,OVERLOADING RIGGER ONE GIVING SIGNALS,
CRANES, BAD USE ONLY SANAD AND AGREED
COMMUNICATION, CAUGHT CRANE SIGNAL TO SIGNAL
IN BETWEEN, FALLING, CRANES, STAY CLEAR OF
TRAFFIC LOAD, 100% TIED OFF, GOOD
COMMUNICATION, TATHERED
HAMMERS, PROPER CRANE
POSITION AND CAPACITY.
ENSURE CRANE OPTRS ARE
CERTIFIED AND EXPERIENCED

Falsifying signatures in this document will results in immediate dismissal

F0858 (0) Original – Rig Files Copy – Area Office Page 2 of 4


6 RAISE MAST CROWN DROPS, LINE OF FIRE, BAD C 4 B4 MAKE SURE ALL LOOSE A 2 A2 ACCEPTABLE
SECTION AND SET ON COMMUNICATION, IMPROPER EQUIPMENT SLING ARE TIGHT
DERRICK STAND SIGNALS, EXEEDING RATING PROPERLY PRIOR LIFTING
OF CRANE, TRAFFIC, CAUGT OPERATION. ASSURE RIGGER
IN BETWEEN, IMPROPER ONE GIVING SIGNALS, STAY
STAND POSITION CLEAR OF LOAD, BANKSMAN
FOR FORKLIFT, ONLY
REQUIRED PERSONEL IN AREA,
ASSURE DERRICK STAND
LEVEL AND IN PROPER
POSITION BEFORE SETTING
DERRICK ON TOP

7 UNHOOK SLINGS WITH DROPS, LINE OF FIRE, PINCH B 2 B2 WATCH OUT FOR PINCH A 2 A2 ACCEPTABLE
GENIE, AND RIG DOWN POINTS, DROPS, FALLING, POINTS, NO BODY INDER
CRANES BAD COMMUNICATION, SECTION WHERE SLINGS/
STRUCK BY, SHACKLES ARE BEEN
REMOVED, 100% TIED OFF,
CLEAR ARE UNDER GENIE AND
CRANE, WEAR PROPER
GLOVES, BE AWARE OF SLING
POSITION, GOOD

Risk Matrix Hazard Identification (Check all that apply)


Likelihood Moving
Risk Rating Mechanical Biological Temperature
A B C D E Objects Pressure
1 Low
2 Medium
SEVERITY

3 Dropped
Noise Electrical Chemical
4 Objects Radiation
5 High

List below the Personal Protective Equipment Required for this Job

SAFETY GLASSES, STEEL TOE BOOTS, HARD HAT, IMPACT GLOVES, HARNESSES-LANYARDS, FLAGGING VEST

List below specific tools and quantity required to perform this Job
F0782 (2)
Original – Rig FilesCopy – Area OfficeCopy - Operator
ADVANCED RISK ASSESSMENT (ARA)

SLINGS, SHACKLES, TETHERED HAMMERS,

Work Group Preparing ARA


Names Position Signature

SIGN-OFF
I confirm that the job steps listed in this JSA are specific to the task and that the
Job Supervisor: controls and mitigations hereby identified are sufficient to conduct the job safely.
Rig Manager/ Toolpusher
Job Title: Name: CHRIS BISHOP
Rig Manager/ Toolpusher
Signature : Signature:

Falsifying signatures in this document will results in immediate dismissal

F0858 (0) Original – Rig Files Copy – Area Office Page 4 of 4