Professional Documents
Culture Documents
Case Study Group 3 Tetra Tech PDF
Case Study Group 3 Tetra Tech PDF
MOS 3331B
Group 3
Discuss the evolution of the risk management and compliance process at Tetra Tech EC
Tetra Tech EC incurred many changes regarding the ownership of the company and
the projects it takes on. In 1992, two large projects resulted in the loss of tens of millions
protect assets, given the risky industry. Instead of engaging in risk avoidance, Don
In 1993, a Task Initiation Procedure (TIP) was created for risk management and
compliance. This procedure included three simple steps: first the procedure was
understood, then risks were identified, and finally a risk management plan was defined
for each risk. There were five broad areas of issues (site conditions, technical
planning elements. The project managers were to consider the issues and identify the
Unlike other companies, Tetra Tech EC’s risk management approach allowed them to
take on any level of risk, “there is absolutely no risk we can’t deal with”. The risk
management and compliance process began six months before Tetra Tech EC placed
bids; the client requests were reviewed, then risks were evaluated, communication with
the client allowed for negotiation, and a bid was then placed. Once the plan was created
and reviewed by specialists, the projects began execution. If there was any deviation
from the plans, the project was placed on hold as re-planning of the project and a
functioning as planned, peer reviews transpired after each sub-project, project reviews
occurred quarterly, and semi-random quality and compliance audits occurred yearly.
When TIP was initially introduced, in 1993, project managers thought it was a waste-of-
time and unnecessary. However, over time they realized that such naive questions could
lead to the emergence of risks that were previously overlooked. The process was
eventually understood and accepted. Although, as the years progressed, the regulations
and process grew so much that interference began to occur regarding innovation and
client satisfaction. In 2006, a new approach began which suggested that regulations call
for constant updates based on changing circumstances. This new approach made it easy
After the fourth of July incident, incentives to report incidents and near misses
started; this increased the incidents reported that would have been ignored otherwise. A
chain of supervisors and discipline lead people to warrant that incidents weren’t
forgotten. Incident reports also taught many lessons and continue to change
procedures regularly. The evolution of the risk management process is evident. A strict
process implemented by the COO in the 1990s was required to be followed precisely.
Whereas, in 2006, employees were able to plan and alter projects to how they see fit
their specific projects. As a result, the evolution placed more power in the hands of the
Elaborate on risk assessment as per the Task initiation Procedure (TIP) and oversight
processes
Tetra Tech EC’s organizational structure resembles a dedicated project team. The
organization and employees are there to support the project. Essentially everyone
working towards the same end goal is the motivation behind a project team. Don
Rogers recognizes that and can use it to incentivize the employees. Moreover, Tetra
Tech EC has a culture that supports open and free communication. Employees are
encouraged to speak their minds and bring their concerns straight to management.
Hence, due to everyone’s common goal, one employee's error may impact the whole
project and eventually, the final result. Creating an open communication culture as well
Case Study 5
as outlining previous mistakes and their repercussions aids employees in voicing their
concerns. Thus, the task Initiation Procedure was created for this reason.
The purpose of The Task Initiation Procedure, TIP, is to understand the project,
identify risks, and define the risk management plan for each risk. Tetra Tech EC clearly
outlines the 5 main areas as well as 11 planning elements. When hiring new personnel,
they are explained the importance of the TIP and how to plan it at every step. They are
trained to stop working and take the time to discover a new solution to avoid putting
the project at risk. The TIP ensures that the company can deal with a variety of
unforeseen risks in an efficient manner, clearly outline the steps needed to reach the
The TIP is similar to the Risk Breakdown Structure, RBS, mentioned in Chapter 7.2.
In an RBS, the macro risks are first identified and then the specific areas are checked.
Each team submits an individual risk report to management to identify as many risks as
possible and have contingency plans in place. Risk Profiles are also conducted by having
individuals not experienced on the project voice their concerns. This allows the
employees to see the project from a new perspective and consider risks that may have
been overlooked.
Tetra Tech EC has several measures in place in order to mitigate various risks. As
previously mentioned, they can stop the process and implement solutions they
identified when performing a risk analysis. One unique advantage for Tetra Tech EC is its
Case Study 6
ability to come up with contingency plans when the problem arises. They are able to do
so by renegotiating the contract to fit the solution. This allows employees to slow down
and complete another risk analysis when implementing their new solution rather than
rushing through it. Implementing new solutions on the spot may further create adverse
risks that can negatively impact the end result. Therefore, performing an additional risk
analysis enables them to update their project plan with the new solution and mitigate
Compare and contrast Tetra Tech EC’s lessons learned approach with common
Tetra Tech EC’s lesson learned approach is an approach where they learned from
their mistakes instead of repeating or forgetting them. At Tetra Tech, employee morale
is high, as each employee must report any major or minor incident instead of covering it
up. An example of this would be a case that happened at Tetra Tech EC. An object was
found that suspended a project and had to be destroyed using the protocol, however,
employees moved it to a different location instead. The employees were tired, wanted to
go home, and the specified day was the last day before a long weekend. This resulted in
costing the company $1.5 million and the workers involved to resign. In fact, what they
should have done was stop, replan, and tell the client that the project must continue
after the issue is resolved. Managers at Tetra Tech EC had to survey and investigate the
work done to figure out the lesson learned and not make the same mistake again. The
Case Study 7
workers were tired and had no idea about a whole set of other regulatory criteria that
had to be met. Hence, the lesson learned from this case was to teach these regulatory
lessons in the field specifically to those who will execute the plan. Tetra Tech EC also
introduced incentives to report near misses and incidents. Issues that arose on the job
were reported and the root cause was discovered. As a consequence, incident reports
were required documentation in the project review protocol. These incident reports
Another approach used in the textbook is the protocol approach where protocols are
established and set to prevent issues and complications from occurring in the first place.
An example of this would be Practice 7.4: Risk Management at the Top of the World.
Numerous deaths have occurred due to the risks of extreme mountain climbing; this
resulted in having set protocols to follow to avoid risks and obstacles. Some of these
protocols were climbers acclimating their bodies to high altitude conditions, needing to
use oxygen masks and bottles during the final ascent to reduce light-headedness and
conditions might cause a risk. Another massive risk is the mental and physical fatigue of
making the final climb of mount Everest. This climb is called the “death zone” as the
body and mind quickly start deteriorating beyond 26,000 ft. The greatest risk is not
reaching the summit but making it back to the camp. Due to this, a contingency plan
Case Study 8
was established in case the weather changes or an accident happens. Guides established
a predetermined time that climbers had to return to camp by, no matter how close they
were to the summit. Many climbers have died due to not following these rules and
protocols. This stresses the importance of having set protocols to follow that would
Looking at these two approaches, the lesson learned approach would be more
as well. The lesson learned approach already has rules and guidelines that need to be
met in any circumstance. Near misses and incidents, whether major or minor, must be
reported and investigated to gain a lesson learned and avoid that mistake again. If a
project is to be completed that might have a risk similar to the one previously made, the
lesson learned must be discussed and talked through before starting the project.
How has Tetra Tech overcome challenges faced by project oriented firms? Compare with
The main challenge for project-oriented firms is risk mitigation; Tetra Tech has
overcome these challenges through their Task Initiation Procedure (TIP), the philosophy,
Implementation of TIP: “Tetra Tech EC does everything the same way.” Tetra Tech uses
TIP to deal with every project. Firstly, Tetra Tech EC utilizes TIP to identify the potential
risks and mitigate these risks. Through the initial stage of TIP, Tetra Tech EC starts to
Case Study 9
identify the risks and approaches the clients, making sure that both sides fully
understand the potential risks of the project. The employees of Tetra Tech EC are trained
that, “In the end, it will cost the client and the firm more to continue than if you didn’t
stop and restart.” When an accident happens, Tetra Tech EC follows TIP and stops the
project immediately, and re-plans before starting until everything goes on the right
track. Being transparent with the clients about their approach from the start allows Tetra
Tech EC to have more room to negotiate the terms later, in the event an accident does
occur. The clients of Tetra Tech EC share the risks and uncertainty throughout the
project, which decreases the risk of losing money for Tetra Tech EC. When the project is
operating, Tetra Tech EC adapts three processes to monitor the projects and ensure the
projects are working as planned. The processes are peer-reviews, project reviews and
the audits. In the review processes, project managers, discipline leads, and executives
review the projects to ensure that everything is working as the plan. After the reviews,
there are two audit groups to review the projects and to monitor the projects. The
reviews and audit processes mitigate the risks and increase the satisfaction of the
clients.
The Philosophy: Unlike most of the other project-oriented companies, the company
philosophy Tetra Tech EC follows, welcomes employees to bring the bad news and
treats bad news sensitively. Only if the bad news is uncovered, then Tetra Tech EC can
company’s success. Instead of covering and forgetting the mistakes, Tetra Tech EC
makes sure to learn from them. Employees are encouraged to report the mistakes that
they made to prevent them from making the same mistakes in the future.
To compare Tetra Tech EC's case with the Snapshot from Practice 7.3: From Dome
to Dust, the companies in both cases harnessed the idea of risk mitigation. In the
snapshot story, the company prepared for three months to plan the demolishing. During
the planning and preparation processes, Loizeaux’s company not only planned each
details of the project to get success, they considered the potential risks that the
demolishing could cause including the damage to surrounding buildings and nearby
people. To mitigate the risks, they built a fence to contain flying concrete, they also
hired security personnel to cordon off roughly 1,000 ft area from the building to prevent
people and pets from stepping in the area. After the building was demolished,
Loizeaux’s company started to clean up and control dust immediately after the
explosion. They also planned to utilize the crushed concrete, 1/3 of the crushed concrete
was used to build a football stadium, the other parts were used to build roadbeds and
foundations throughout the Seattle area. Regarding Tetra Tech EC, the company
implements TIP to plan the project and mitigate risks, Loizeaux’s company in the
snapshot also planned prior to the explosion and tried to mitigate risks.