You are on page 1of 1

PTO - Lifting/Moving of Equipment (Concrete Bucket)

CHECKPOINTS CHECK

1. Operator trained, appointed and medically fit?


2. PPE for workers: hard hat, overalls safety boots?

3. Two-way radios available?

4. Banksmen to be available and wearing high-viz vests?

5. Correct rigging practices observed?

6. Area ready to receive equipment, concrete etc?

7. Whistles being used when loads are being lifted and slewed?

8. Correct slewing practices being observed?

9. Ensure no spillages from concrete bucket?

10. All lifting equipment and tackle inspected and recorded on checklists?

11. All lifting equipment and tackle suitable identified?

12. Banksmen trained and competent?

13. Good communication between banksmen and operator?

OK All in order.
X A fault was found.
N/A Not applicable.

Person(s) Being Observed

Comments

Recommendations

Worker(s): Sign Date

Observer: Sign Date