PTO – Demolition, General

CHECKPOINTS CHECK

1. Proper methodology determined?


2. Required PPE: hard hat, safety boots, PVC/leather gloves, ear protection, eye/face protection?

3. Load bearing points identified?

4. Sufficient propping, support work etc in place when required?

5. Props being checked on a daily basis?

6. Unsafe areas identified?

7. Services identified i.e. water, AC, electricity and required precautions taken?

8. Sufficient lighting levels?

9. Demolition areas suitably identified and demarcated?

10. Safe access?

11. Sufficient safety measure considered i.e. crash decks, catch nets etc?

12. Rubble chute in place if required?

13. Equipment being used in good condition?

14. Plant being used – safe and trained operators etc?

15. Demolition being conducted as per method statement and risk assessment?

OK All in order.
X A fault was found.
N/A Not applicable.

Person(s) Being Observed

Comments

Recommendations

Worker(s): Sign Date

Observer: Sign Date