You are on page 1of 1

RSD 3D WORK'S ARCHITECTS

PROJECT : PROPOSED 2-STOREY RESIDENTIAL BUILDING

OWNER : SPS ARTURO P. LUBOA & ANING LUBOA

LOCATION : LUBAS LA TRINIDAD BENGUET

Select a period to highlight at right. A legend describing the charting follows. Period Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)
%
PLAN PLAN ACTUAL ACTUAL PERCENT
ACTIVITY-SCOPE OF WORK MTLS LABOR ACCOMPLISHM
START DURATION START DURATION COMPLETE PERIODS-DAYS
NETS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
A PHASE-1
1 SEPTIC TANK 25,000.00 0%
2 1ST FLR. RETAINING WALL 35,000.00 0%
3 FOUNDATION,COLUMN & GRADE BEAM 17,000.00 0%
4 1ST FLR. SLAB 50,000.00 0%
5 2ND FLR. BEAM 20,000.00 0%
6 2ND FLR. SLAB 50,000.00 0%
7 RC STAIRCASE PARKING-1ST FLR. 15,000.00 0%
212,000.00
B
8 1ST FLR. CHB ENCLOSURE 70,000.00 0%
9 1ST FLR. P&S FIRST FIX 15,000.00 0%
10 1ST FLR. ELECTRIC FIRST & FINAL FIX 12,000.00 0%
11 1ST FLR. PLASTERING EX&INT'R 70,000.00 0%
12 1ST FLR. WATERPROOFING 20,000.00 0%
13 1ST FLR SKIMCOAT 20,000.00 0%
207,000.00
C
14 1ST FLR. CEILING EX&INT'R 75,000.00 0%
15 1ST FLR. TILLING EXT&INT'R 60,000.00 0%
16 1ST FLR. CARPENTRY WORKS 100,000.00 0%
17 1ST FLR. PAINT FINISH 70,000.00 0%
18 1ST FLR. FINAL FIX 35,000.00 0%
340,000.00
D PHASE-2 (2ND FLR)
19 2ND FLR. FOUNDATION,COLUMN 20,000.00 0%
20 3RD FLR. BEAM 20,000.00 0%
21 3RD FLR. SLAB 50,000.00 0%
22 RC STAIR 1ST-2ND FLR. 35,000.00 0%
23 2ND FLR. CHB 50,000.00 0%
24 2ND FLR. P&S FIRST & FINAL FIX 30,000.00 0%
25 2ND FLR. ELECTRICAL 1ST-FINAL FIX 12,000.00 0%
26 2ND FLR PLASTERING 40,000.00 0%
27 2ND FLR. WATERPROOFING 25,000.00 0%
28 2ND FLR. SKIMCOAT 20,000.00 0%
29 2ND FLR. CEILING 55,000.00 0%
30 2ND FLR. TILLING WORKS 60,000.00 0%
31 2ND FLR. CARPENTRY 90,000.00 0%
32 2ND FLR. PAINT FINISH 70,000.00 0%
33 2ND FLR. FINAL FIX 30,000.00 0%
607,000.00
E PHASE-3 (3RD FLR.)
34 3RD FLR. COLUMN & ROOF BEAM 20,000.00 0%
35 3RD FLR. CHB 40,000.00 0%
36 3RD FLR. ELECTRICAL 1ST & FINAL FIX 12,000.00 0%
37 3RD FLR. PLASTERING 40,000.00 0%
38 RC STAIR 2ND-3RD FLR. 15,000.00 0%
39 3RD FLR. WATER PROOFING 15,000.00 0%
40 3RD FLR. SKIMCOAT 15,000.00 0%
41 3RD FLR. CEILING 45,000.00 0%
42 3RD FLR. TILLING WORKS 40,000.00 0%
43 3RD FLR. CARPENTRY 40,000.00 0%
44 3RD FLR. PAIN FINISH 40,000.00 0%
322,000.00
45 ROOFING SYSTEM 100,000.00 0%
46 DOWNSPOUT & GUTTERS 25,000.00 0%
125,000.00
1,813,000.00

Note:

1. Accommodation, electricity, water, kitchen utensils, Gasul to be provided by owner.

23C Greenlane Rainbow Hills Subdivision Avelino St. Ext. Fairview Baguio City
Email: troytrojan85@gmail.com; Mobile: +639338131248