You are on page 1of 35

Wines

Project
Kamagong Farm
Update (Module 1)
As of August 24, 2023
Module 1- House 1: Scope of Work 1/5
*Structural completed
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. ROOFING:

PU roof installation COMPLETED


Ridge roll installation COMPLETED
Ridge roll cover
installation and COMPLETED
accessories
2. WALL INSTALLATION:

Installation of runners COMPLETED


Installation of wall panels COMPLETED
Installation of cable trays COMPLETED
Application of silicon
sealant
COMPLETED
Rectification of PU
junction
COMPLETED
Module 1- House 1: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation COMPLETED

Overhead feeding system support COMPLETED


Overhead feeding system assembly
90% Finishing works
and installation
House feeding system installation
90% Control panel installed
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment COMPLETED

Installation of ventilating fans COMPLETED

Cooling pads/ gutter installation COMPLETED


Tunnel door framing fabrication and
installation
COMPLETED

SKOV installation plus controls 90% Control panel installed


Module 1- House 1: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation COMPLETED
1. JANSEN NEST SYSTEM

Layout COMPLETED

Assembly of parts (feet) COMPLETED

Assembly of parts (body) COMPLETED

Assembly of conveyor and


COMPLETED
installation
Installation of flaps and roofing COMPLETED

Installation of plastic slots COMPLETED


Module 1- House 1: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


COMPLETED
wires for switches
T8 casing assembly and lighting
COMPLETED
installation
Perimeter lighting COMPLETED

Control room assembly COMPLETED

Cable pulling and termination COMPLETED

2. PLUMBING WORKS

Water panel assembly and installation COMPLETED

Provision for washing 0% Planning stage Plan and materials

Water piping for cooling pads source COMPLETED


Module 1- House 1: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) COMPLETED

Rain water canal (outside) 80% On-going chb piling (rear)

Skirting (outside) COMPLETED


Partition between service area and
Skirting (inside) 99%
pen (right side)
Waste water septic tank 100%

Rain water septic tank 1/3 0%

Corrections On-going…
Module 1- House 2: Scope of Work 1/5
*Structural completed
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. ROOFING:

PU roof installation COMPLETED


Ridge roll installation COMPLETED
Ridge roll cover
installation and COMPLETED
accessories
2. WALL INSTALLATION:

Installation of runners COMPLETED


Installation of wall panels COMPLETED
Installation of cable trays COMPLETED
Application of silicon
sealant
COMPLETED
Rectification of PU
junction
COMPLETED
Module 1- House 2: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation COMPLETED

Overhead feeding system support COMPLETED


Overhead feeding system
assembly and installation
90% Done assembly Installation
House feeding system installation
90% Control panel installed Cable pulling and tapping
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment COMPLETED

Installation of ventilating fans completed

Cooling pads/ gutter installation COMPLETED


Tunnel door framing fabrication and
installation
COMPLETED

SKOV installation plus controls 90% Control panel installed Cable pulling and tapping
Module 1- House 2: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation completed
1. JANSEN NEST SYSTEM

Layout COMPLETED

Assembly of parts (feet) COMPLETED

Assembly of parts (body) COMPLETED

Assembly of conveyor and


COMPLETED
installation
Installation of flaps and roofing COMPLETED

Installation of plastic slots COMPLETED


Module 1- House 2: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


COMPLETED
wires for switches
T8 casing assembly and lighting
COMPLETED
installation
Perimeter lighting COMPLETED

Control room assembly COMPLETED

Cable pulling and termination COMPLETED

2. PLUMBING WORKS

Water panel assembly and installation COMPLETED

Provision for washing 0% Planning stage Plan and materials

Water piping for cooling pads source COMPLETED


Module 1- House 2: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) COMPLETED

Rain water canal (outside) 80% On-going chb piling (rear) Flooring

Skirting (outside) COMPLETED

Skirting (inside) COMPLETED


Rebars, formworks, and cover
Waste water septic tank 90%
concreting
Rain water septic tank 1/3 0%

Corrections 0%
Module 1- House 3: Scope of Work 1/5
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. ROOFING:

PU roof installation COMPLETED


Ridge roll installation COMPLETED
Ridge roll cover installation
and accessories
COMPLETED
2. WALL INSTALLATION:

Installation of runners COMPLETED


Installation of wall panels COMPLETED
Installation of cable trays COMPLETED
Application of silicon sealant COMPLETED
Rectification of PU junction 90%
Module 1- House 3: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation COMPLETED

Overhead feeding system support COMPLETED


Overhead feeding system
50% On-going
assembly and installation
House feeding system installation
50% Control panel installed Cable pulling and tapping
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment COMPLETED

Installation of ventilating fans COMPLETED

Cooling pads/ gutter installation COMPLETED


Tunnel door framing fabrication and
installation
COMPLETED

SKOV installation plus controls 80% Control panel installed


Module 1- House 2: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation 0%
1. JANSEN NEST SYSTEM Incomplete roofing

Layout 0%

Assembly of parts (feet) 20%

Assembly of parts (body) 0%

Assembly of conveyor and


0% Lacking of egg conveyor belt
installation
Installation of flaps and roofing 0%

Installation of plastic slots 0%


Module 1- House 3: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


COMPLETED
wires for switches
T8 casing assembly and lighting
COMPLETED
installation
Perimeter lighting COMPLETED

Control room assembly COMPLETED

Cable pulling and termination COMPLETED

2. PLUMBING WORKS

Water panel assembly and installation COMPLETED

Provision for washing 0% Planning stage Plan and materials

Water piping for cooling pads source COMPLETED


Module 1- House 3: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) COMPLETED

Rain water canal (outside) 80% On-going chb piling (rear) Flooring

Skirting (outside) COMPLETED

Skirting (inside) 45% Plastering


Rebars, formworks, and cover
Waste water septic tank 90%
concreting
Rain water septic tank 1/3 0%

Corrections 0%
Module 1- Auxiliary Buildings

SCOPE OF WORK STATUS REMARKS LACKING


Decontamination Area 60% Roofing & gutter c/o san josue
Staff House 60% Roofing & gutter c/o san josue
Feed House 80% Roofing only c/o admin
Day- Bin (Single) 0% Not yet
Day- Bin (Double) 0% Not yet
Pump House 0% Not yet
Power House 99%
Access Roads 90%
Wines
Project
Laurel Farm Update
(Module 2)
As of July 18, 2023
Module 2- House 1: Scope of Work 1/5 (August 4-6)
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. STRUCTURAL:

Layout and Anchor Bolt Setting COMPLETED


Erection & Assembly of Trusses and COMPLETED
Purlins
Installation of accessories Not yet
2. ROOFING:

PU roof installation 70% SINCE AUGUST 12 – NO PU PU ROOF


Ridge roll installation 70%
Ridge roll cover installation and
accessories
70%

3. WALL INSTALLATION:

Installation of runners 90%

Installation of wall panels 80% SINCE AUGUST 12 – NO PU PU WALL


Installation of cable trays 0%

Application of silicon sealant 0%

Rectification of PU junction 0%
Module 2- House 1: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment

Feeder line hanger installation

Overhead feeding system support


Overhead feeding system assembly
and installation
House feeding system installation
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment

Installation of ventilating fans

Cooling pads/ gutter installation

Tunnel door framing fabrication and


installation

SKOV installation plus controls


Module 2- House 1: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation
1. JANSEN NEST SYSTEM

Layout
Assembly of parts (feet)
Assembly of parts (body)
Assembly of conveyor and
installation
Installation of flaps and roofing

Installation of plastic slots


Module 2- House 1: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


wires for switches
T8 casing assembly and lighting
installation
Perimeter lighting

Control room assembly

Cable pulling and termination

2. PLUMBING WORKS

Water panel assembly and installation

Provision for washing

Water piping for cooling pads source


Module 2- House 1: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation
Flooring
Waste water canal (inside)
Rain water canal (outside)
Skirting (outside)
Skirting (inside)
Waste water septic tank

Rain water septic tank 1/3

Corrections
Module 2- House 2: Scope of Work 1/5 (August 7-on-going)
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. STRUCTURAL:

Layout and Anchor Bolt Setting COMPLETED


Erection & Assembly of Trusses and COMPLETED
Purlins
Installation of accessories Not yet
2. ROOFING:

PU roof installation NO AVAILABLE PU PU ROOF


Ridge roll installation

Ridge roll cover installation and


accessories
3. WALL INSTALLATION:

Installation of runners

Installation of wall panels NO AVAILABLE PU PU WALL


Installation of cable trays

Application of silicon sealant

Rectification of PU junction
Module 2- House 2: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment

Feeder line hanger installation

Overhead feeding system support


Overhead feeding system assembly
and installation
House feeding system installation
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment

Installation of ventilating fans

Cooling pads/ gutter installation

Tunnel door framing fabrication and


installation

SKOV installation plus controls


Module 2- House 2: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation
1. JANSEN NEST SYSTEM

Layout
Assembly of parts (feet)
Assembly of parts (body)
Assembly of conveyor and
installation
Installation of flaps and roofing

Installation of plastic slots


Module 2- House 2: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


wires for switches
T8 casing assembly and lighting
installation
Perimeter lighting

Control room assembly

Cable pulling and termination

2. PLUMBING WORKS

Water panel assembly and installation

Provision for washing

Water piping for cooling pads source


Module 2- House 2: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation
Flooring
Waste water canal (inside)
Rain water canal (outside)
Skirting (outside)
Skirting (inside)
Waste water septic tank

Rain water septic tank 1/3

Corrections
Module 2- House 3: Scope of Work 1/5
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. STRUCTURAL:

Layout and Anchor Bolt Setting COMPLETED


Erection & Assembly of Trusses and COMPLETED
Purlins
Installation of accessories

2. ROOFING:

PU roof installation NO AVAILABLE PU PU ROOF


Ridge roll installation

Ridge roll cover installation and


accessories
3. WALL INSTALLATION:

Installation of runners

Installation of wall panels NO AVAILABLE PU PU WALL


Installation of cable trays

Application of silicon sealant

Rectification of PU junction
Module 2- House 3: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment

Feeder line hanger installation

Overhead feeding system support


Overhead feeding system assembly
and installation
House feeding system installation
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment

Installation of ventilating fans

Cooling pads/ gutter installation

Tunnel door framing fabrication and


installation

SKOV installation plus controls


Module 2- House 3: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation
1. JANSEN NEST SYSTEM

Layout
Assembly of parts (feet)
Assembly of parts (body)
Assembly of conveyor and
installation
Installation of flaps and roofing

Installation of plastic slots


Module 2- House 3: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


wires for switches
T8 casing assembly and lighting
installation
Perimeter lighting

Control room assembly

Cable pulling and termination

2. PLUMBING WORKS

Water panel assembly and installation

Provision for washing

Water piping for cooling pads source


Module 2- House 3: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation
Flooring
Waste water canal (inside)
Rain water canal (outside)
Skirting (outside)
Skirting (inside)
Waste water septic tank

Rain water septic tank 1/3

Corrections
WINES – BRIDGE BOX CULVERT

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring/CARRAIGEWAY COMPLETED
NOT YET TURNOVER TO
WINGWALL COMPLETED THE BRIDGE IS NOW GOVERNMENT
ACCESSIBLE
COMLETED C/O MAM HELEN
REINFORCING BARS

CONCRETE BARRIER COMPLETED


Thank you…

You might also like