Module 1- House 1: Scope of Work 1/5
*Structural completed
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. ROOFING:

PU roof installation COMPLETED


Ridge roll installation COMPLETED
Ridge roll cover
installation and COMPLETED
accessories
2. WALL INSTALLATION:

Installation of runners COMPLETED


Installation of wall panels COMPLETED
Installation of cable trays COMPLETED
Application of silicon
sealant
COMPLETED
Rectification of PU
junction
COMPLETED
Module 1- House 1: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation COMPLETED

Overhead feeding system support COMPLETED


Overhead feeding system assembly
90% Finishing works Installation of motors
and installation
House feeding system installation
80% Cable pulling done Termination
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment COMPLETED

Installation of ventilating fans COMPLETED

Cooling pads/ gutter installation COMPLETED


Tunnel door framing fabrication and
installation
COMPLETED

SKOV installation plus controls 95% Selector Switch


Module 1- House 1: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation COMPLETED
1. JANSEN NEST SYSTEM

Layout COMPLETED

Assembly of parts (feet) COMPLETED

Assembly of parts (body) COMPLETED

Assembly of conveyor and


COMPLETED
installation
Installation of flaps and roofing COMPLETED

Installation of plastic slots COMPLETED


Module 1- House 1: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


COMPLETED
wires for switches
T8 casing assembly and lighting
COMPLETED
installation
Perimeter lighting COMPLETED

Control room assembly COMPLETED

Cable pulling and termination COMPLETED

2. PLUMBING WORKS

Water panel assembly and installation COMPLETED

Provision for washing COMPLETED

Water piping for cooling pads source COMPLETED


Module 1- House 1: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) COMPLETED

Rain water canal (outside) 80% On-going chb piling (rear)

Skirting (outside) COMPLETED

Skirting (inside) COMPLETED

Waste water septic tank COMPLETED

Rain water septic tank 1/3 0%

Corrections On-going…
Module 1- House 2: Scope of Work 1/5
*Structural completed
SCOPE OF WORK STATUS REMARKS MATERIAL LACKING
1. ROOFING:

PU roof installation COMPLETED


Ridge roll installation COMPLETED
Ridge roll cover
installation and COMPLETED
accessories
2. WALL INSTALLATION:

Installation of runners COMPLETED


Installation of wall panels COMPLETED
Installation of cable trays COMPLETED
Application of silicon
sealant
COMPLETED
Rectification of PU
junction
COMPLETED
Module 1- House 2: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation COMPLETED

Overhead feeding system support COMPLETED


Overhead feeding system
assembly and installation
70% Done assembly Cable installation
House feeding system
40% Control panel installed Cable pulling and tapping
installation plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment COMPLETED

Installation of ventilating fans COMPLETED

Cooling pads/ gutter installation COMPLETED


Tunnel door framing fabrication and
installation
COMPLETED

SKOV installation plus controls COMPLETED


Module 1- House 2: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation COMPLETED
1. JANSEN NEST SYSTEM

Layout COMPLETED

Assembly of parts (feet) COMPLETED

Assembly of parts (body) COMPLETED

Assembly of conveyor and


COMPLETED
installation
Installation of flaps and roofing COMPLETED

Installation of plastic slots COMPLETED


Module 1- House 2: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


COMPLETED
wires for switches
T8 casing assembly and lighting
COMPLETED
installation
Perimeter lighting COMPLETED

Control room assembly COMPLETED

Cable pulling and termination COMPLETED

2. PLUMBING WORKS

Water panel assembly and installation COMPLETED

Provision for washing COMPLETED

Water piping for cooling pads source COMPLETED


Module 1- House 2: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) COMPLETED

Rain water canal (outside) 80% On-going chb piling (rear) Flooring

Skirting (outside) COMPLETED

Skirting (inside) COMPLETED


Rebars, formworks, and cover
Waste water septic tank 90%
concreting
Rain water septic tank 1/3 0%

Corrections 0%
Module 1- House 3: Scope of Work 1/5

SCOPE OF WORK STATUS REMARKS MATERIAL LACKING


1. ROOFING:

PU roof installation COMPLETED


Ridge roll installation COMPLETED
Ridge roll cover installation
and accessories
COMPLETED
2. WALL INSTALLATION:

Installation of runners COMPLETED


Installation of wall panels COMPLETED
Installation of cable trays COMPLETED
Application of silicon sealant COMPLETED
Rectification of PU junction COMPLETED
Module 1- House 3: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation COMPLETED

Overhead feeding system support COMPLETED


Overhead feeding system
50% On-going assembly at House 2
assembly and installation
House feeding system On-going: laying of male
20%
installation plus controls feeders
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment COMPLETED

Installation of ventilating fans COMPLETED

Cooling pads/ gutter installation COMPLETED


Tunnel door framing fabrication and
installation
COMPLETED

SKOV installation plus controls COMPLETED


Module 1- House 2: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation 0%
1. JANSEN NEST SYSTEM Conveyor belt
*Layout of nest is delayed due to lack of
Layout 0%
materials (conveyor belt)
*To push through installation may cause
Assembly of parts (feet) 20%
repetitive adjustments and alignments
*We opted to focus all energy to finish
Assembly of parts (body) 0%
House 2 installations instead
Assembly of conveyor and
0%
installation
Installation of flaps and roofing 0%

Installation of plastic slots 0%


Module 1- House 3: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


COMPLETED
wires for switches
T8 casing assembly and lighting
90% 37 units of T8 LED tubes
installation
Perimeter lighting COMPLETED

Control room assembly COMPLETED

Cable pulling and termination 90% On-going light laying (T8) Finishing

2. PLUMBING WORKS

Water panel assembly and installation COMPLETED

Provision for washing COMPLETED

Water piping for cooling pads source COMPLETED


Module 1- House 3: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) COMPLETED

Rain water canal (outside) 80% On-going chb piling (rear) Flooring

Skirting (outside) COMPLETED

Skirting (inside) COMPLETED


Rebars, formworks, and cover
Waste water septic tank 90%
concreting
Rain water septic tank 1/3 0%

Corrections 0%
Module 1- Auxiliary Buildings

SCOPE OF WORK STATUS REMARKS LACKING


Decontamination Area 40% Roof
Staff House 50% Roof
Feed House 60% Roof, flooring (checkered plate)
Day- Bin (Single) 0%
Day- Bin (Double) 0%
Pump House 0%
Power House 99%
Access Roads 90%
Wines
Project
Laurel Farm Update
(Module 2)
As of August 7, 2023
Module 2- House 4: Scope of Work 1/5

SCOPE OF WORK STATUS REMARKS MATERIAL LACKING


1. STRUCTURAL:

Layout and Anchor Bolt Setting COMPLETED


Erection & Assembly of Trusses and 20% Assembly of trusses
Purlins
Installation of accessories

2. ROOFING:

PU roof installation Roofing, 3 trailer trucks


Ridge roll installation

Ridge roll cover installation and


accessories
3. WALL INSTALLATION:

Installation of runners

Installation of wall panels

Installation of cable trays

Application of silicon sealant

Rectification of PU junction
Module 2- House 4: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation

Overhead feeding system support


Overhead feeding system assembly
and installation
House feeding system installation
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment

Installation of ventilating fans

Cooling pads/ gutter installation

Tunnel door framing fabrication and


installation

SKOV installation plus controls


Module 2- House 4: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation
1. JANSEN NEST SYSTEM

Layout
Assembly of parts (feet)
Assembly of parts (body)
Assembly of conveyor and
installation
Installation of flaps and roofing
Installation of plastic slots
Module 2- House 4: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


wires for switches
T8 casing assembly and lighting
installation
Perimeter lighting

Control room assembly

Cable pulling and termination

2. PLUMBING WORKS

Water panel assembly and installation

Provision for washing

Water piping for cooling pads source


Module 2- House 4: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) 50%

Rain water canal (outside) 60%

Skirting (outside)
Skirting (inside)
Waste water septic tank

Rain water septic tank 1/3

Corrections
Module 2- House 5: Scope of Work 1/5

SCOPE OF WORK STATUS REMARKS MATERIAL LACKING


1. STRUCTURAL:

Layout and Anchor Bolt Setting COMPLETED


Erection & Assembly of Trusses and 70% 18 erected with purlins
Purlins
Installation of accessories

2. ROOFING:

PU roof installation

Ridge roll installation

Ridge roll cover installation and


accessories
3. WALL INSTALLATION:

Installation of runners

Installation of wall panels

Installation of cable trays

Application of silicon sealant

Rectification of PU junction
Module 2- House 5: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation

Overhead feeding system support


Overhead feeding system assembly
and installation
House feeding system installation
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment

Installation of ventilating fans

Cooling pads/ gutter installation

Tunnel door framing fabrication and


installation

SKOV installation plus controls


Module 2- House 5: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation
1. JANSEN NEST SYSTEM

Layout
Assembly of parts (feet)
Assembly of parts (body)
Assembly of conveyor and
installation
Installation of flaps and roofing
Installation of plastic slots
Module 2- House 5: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


wires for switches
T8 casing assembly and lighting
installation
Perimeter lighting

Control room assembly

Cable pulling and termination

2. PLUMBING WORKS

Water panel assembly and installation

Provision for washing

Water piping for cooling pads source


Module 2- House 5: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation
Flooring
Waste water canal (inside)
Rain water canal (outside)
Skirting (outside)
Skirting (inside)
Waste water septic tank

Rain water septic tank 1/3

Corrections
Module 2- House 6: Scope of Work 1/5

SCOPE OF WORK STATUS REMARKS MATERIAL LACKING


1. STRUCTURAL:

Layout and Anchor Bolt Setting COMPLETED


Erection & Assembly of Trusses and COMPLETED
Purlins
Installation of accessories

2. ROOFING:

PU roof installation Roofing, 1 trailer truck


Ridge roll installation

Ridge roll cover installation and


accessories
3. WALL INSTALLATION:

Installation of runners

Installation of wall panels

Installation of cable trays

Application of silicon sealant

Rectification of PU junction
Module 2- House 6: Scope of Work 2/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ROXELL FEEDING SYSTEM

Unloading of Roxell equipment COMPLETED

Feeder line hanger installation

Overhead feeding system support


Overhead feeding system assembly
and installation
House feeding system installation
plus controls
2. SKOV VENTILATION SYSTEM

Unloading of SKOV equipment

Installation of ventilating fans

Cooling pads/ gutter installation

Tunnel door framing fabrication and


installation

SKOV installation plus controls


Module 2- House 6: Scope of Work 3/5

SCOPE OF WORK STATUS REMARKS LACKING


*Partition Installation
1. JANSEN NEST SYSTEM

Layout
Assembly of parts (feet)
Assembly of parts (body)
Assembly of conveyor and
installation
Installation of flaps and roofing
Installation of plastic slots
Module 2- House 6: Scope of Work 4/5
SCOPE OF WORK STATUS REMARKS LACKING
1. ELECTRICAL WORKS

Installation of junction box and


wires for switches
T8 casing assembly and lighting
installation
Perimeter lighting

Control room assembly

Cable pulling and termination

2. PLUMBING WORKS

Water panel assembly and installation

Provision for washing

Water piping for cooling pads source


Module 2- House 6: Scope of Work 5/5

SCOPE OF WORK STATUS REMARKS LACKING


1. CIVIL WORKS

Foundation COMPLETED

Flooring COMPLETED

Waste water canal (inside) 50%

Rain water canal (outside) 60%

Skirting (outside)
Skirting (inside)
Waste water septic tank

Rain water septic tank 1/3

Corrections
Module 2- Auxiliary Buildings

SCOPE OF WORK STATUS REMARKS LACKING


Decontamination Area
Staff House
Feed House
Day- Bin (Single)
Day- Bin (Double)
Pump House 1 pumphouse for 2 modules
Power House 99% 1 powerhouse for 2 modules