Durian Proj Update 6.6.23
Durian Proj Update 6.6.23
Durian Farm
Perimeter Fence
Main Gate
Main Entrance Road Concreting
Staff house
Steel Works 10 d
- Cutting/preparing of re-bars for footing 2d 6/6/2023 6/7/2023 100% Completed
- Cutting/repairing of re-bars for column 2d 6/8/2023 6/9/2023 100% Completed
- Ties making for column 2d 6/10/2023 6/12/2023 100% Completed
- Cutting/repairing of re-bars for tie beam 2d 6/13/2023 6/14/2023 100% Completed
- Stirrups making for tie beam 2d 6/15/2023 6/16/2023 100% Completed
Installations 16 d
- Installation of re-bars for footing 4d 6/17/2023 6/21/2023 10% In Progress
- Installation of re-bars for column 3d 6/22/2023 6/24/2023 7% In Progress
- Installation of ties for column 3d 6/26/2023 6/28/2023 7% In Progress
- Installation of re-bars for tie beam 3d 6/29/2023 7/1/2023 5% In Progress
- Installation of stirrups for tie beam 3d 7/3/2023 7/5/2023 5% In Progress
Masonry Works 23 d
- Pouring of concrete for footing 4d 7/6/2023 7/10/2023 5% In Progress
- Pouring of concrete for column 5d 7/11/2023 7/15/2023 2% In Progress
- Pouring of concrete for tie beam 4d 7/17/2023 7/20/2023 0% Not Started
- CHB 6" piling every 3 meters of span 6d 7/21/2023 7/27/2023 0% Not Started
- Filling mortar in CHB 6" piling 2d 7/28/2023 7/29/2023 0% Not Started
- Plastering both sides with a 16 mm thickness 2d 7/31/2023 8/1/2023 0% Not Started
Installation of 4
Lines of Barbed
4d
- Preparation and measurement for barbed wire 2d 8/2/2023 8/3/2023 0% Not Started
- Installation of barbed wire on top of the fence 2d 8/4/2023 8/5/2023 0% Not Started
Perimeter Fence
Number of manpower required for each activity:
Task Duration (Days) Manpower Required
Steel Works 10 2 Steelworkers, 4 Laborers
- Cutting/preparing of re-bars for footing 2 1 Steelworker, 1 Laborer
- Cutting/repairing of re-bars for column 2 1 Steelworker, 1 Laborer
- Ties making for column 2 1 Steelworker, 1 Laborer
- Cutting/repairing of re-bars for tie beam 2 1 Steelworker, 1 Laborer
- Stirrups making for tie beam 2 1 Steelworker, 1 Laborer
Installations 16 2 Steelworkers, 4 Laborers
- Installation of re-bars for footing 4 1 Steelworker, 2 Laborers
- Installation of re-bars for column 3 1 Steelworker, 2 Laborers
- Installation of ties for column 3 1 Steelworker, 2 Laborers
- Installation of re-bars for tie beam 3 1 Steelworker, 2 Laborers
- Installation of stirrups for tie beam 3 1 Steelworker, 2 Laborers
Masonry Works 23 4 Masons, 6 Laborers
- Pouring of concrete for footing 4 2 Masons, 4 Laborers
- Pouring of concrete for column 5 2 Masons, 4 Laborers
- Pouring of concrete for tie beam 4 2 Masons, 4 Laborers
- CHB 6" piling every 3 meters of span 6 2 Masons, 4 Laborers
- Filling mortar in CHB 6" piling 2 2 Masons, 2 Laborers
- Plastering both sides with a 16 mm thickness 2 2 Masons, 2 Laborers
Installation of 4 Lines of Barbed Wire 4 2 Laborers
- Preparation and measurement for barbed wire 2 1 Laborer
- Installation of barbed wire on top of the fence 2 2 Laborers
Perimeter Fence
Main Gate