You are on page 1of 8

PROJECT PRESENTATION UPDATES

Durian Farm
 Perimeter Fence
 Main Gate
 Main Entrance Road Concreting
 Staff house

 PERIOD : JUNE 6, 2023


Perimeter Fence
Gantt Chart
Project Name: Masonry CHB Fence Construction & Installation of 4 Lines of Barbed Wire on Top of the Masonry CHB Fence: Perimeter Length = 183 meters
Start Date: June 06, 2023

End Date: August 05, 2023

Project Duration: 53 Calendar Days

Task Start Date Duration (Days) End Date


Steel Works 6/6/2023 10 6/16/2023
- Cutting/preparing of re-bars for footing 6/6/2023 2 6/7/2023
- Cutting/repairing of re-bars for column 6/8/2023 2 6/9/2023
- Ties making for column 6/10/2023 2 6/12/2023
- Cutting/repairing of re-bars for tie beam 6/13/2023 2 6/14/2023
- Stirrups making for tie beam 6/15/2023 2 6/16/2023
Installations 6/19/2023 16 7/5/2023
- Installation of re-bars for footing 6/17/2023 4 6/21/2023
- Installation of re-bars for column 6/22/2023 3 6/24/2023
- Installation of ties for column 6/26/2023 3 6/28/2023
- Installation of re-bars for tie beam 6/29/2023 3 7/1/2023
- Installation of stirrups for tie beam 7/3/2023 3 7/5/2023
Masonry Works 7/6/2023 23 8/1/2023
- Pouring of concrete for footing 7/6/2023 4 7/10/2023
- Pouring of concrete for column 7/11/2023 5 7/15/2023
- Pouring of concrete for tie beam 7/17/2023 4 7/20/2023
- CHB 6" piling every 3 meters of span 7/21/2023 6 7/27/2023
- Filling mortar in CHB 6" piling 7/28/2023 2 7/29/2023
- Plastering both sides with a 16 mm thickness 7/31/2023 2 8/1/2023
Installation of 4 Lines of Barbed Wire 8/2/2023 4 8/5/2023
- Preparation and measurement for barbed wire 8/2/2023 2 8/3/2023
- Installation of barbed wire on top of the fence 8/4/2023 2 8/5/2023
Perimeter Fence
ID Activity Name Duration Start Finish Progress % Status

Steel Works 10 d
- Cutting/preparing of re-bars for footing 2d 6/6/2023 6/7/2023 100% Completed
- Cutting/repairing of re-bars for column 2d 6/8/2023 6/9/2023 100% Completed
- Ties making for column 2d 6/10/2023 6/12/2023 100% Completed
- Cutting/repairing of re-bars for tie beam 2d 6/13/2023 6/14/2023 100% Completed
- Stirrups making for tie beam 2d 6/15/2023 6/16/2023 100% Completed
Installations 16 d
- Installation of re-bars for footing 4d 6/17/2023 6/21/2023 10% In Progress
- Installation of re-bars for column 3d 6/22/2023 6/24/2023 7% In Progress
- Installation of ties for column 3d 6/26/2023 6/28/2023 7% In Progress
- Installation of re-bars for tie beam 3d 6/29/2023 7/1/2023 5% In Progress
- Installation of stirrups for tie beam 3d 7/3/2023 7/5/2023 5% In Progress
Masonry Works 23 d
- Pouring of concrete for footing 4d 7/6/2023 7/10/2023 5% In Progress
- Pouring of concrete for column 5d 7/11/2023 7/15/2023 2% In Progress
- Pouring of concrete for tie beam 4d 7/17/2023 7/20/2023 0% Not Started
- CHB 6" piling every 3 meters of span 6d 7/21/2023 7/27/2023 0% Not Started
- Filling mortar in CHB 6" piling 2d 7/28/2023 7/29/2023 0% Not Started
- Plastering both sides with a 16 mm thickness 2d 7/31/2023 8/1/2023 0% Not Started
Installation of 4
Lines of Barbed
4d
- Preparation and measurement for barbed wire 2d 8/2/2023 8/3/2023 0% Not Started
- Installation of barbed wire on top of the fence 2d 8/4/2023 8/5/2023 0% Not Started
Perimeter Fence
Number of manpower required for each activity:
Task Duration (Days) Manpower Required
Steel Works 10 2 Steelworkers, 4 Laborers
- Cutting/preparing of re-bars for footing 2 1 Steelworker, 1 Laborer
- Cutting/repairing of re-bars for column 2 1 Steelworker, 1 Laborer
- Ties making for column 2 1 Steelworker, 1 Laborer
- Cutting/repairing of re-bars for tie beam 2 1 Steelworker, 1 Laborer
- Stirrups making for tie beam 2 1 Steelworker, 1 Laborer
Installations 16 2 Steelworkers, 4 Laborers
- Installation of re-bars for footing 4 1 Steelworker, 2 Laborers
- Installation of re-bars for column 3 1 Steelworker, 2 Laborers
- Installation of ties for column 3 1 Steelworker, 2 Laborers
- Installation of re-bars for tie beam 3 1 Steelworker, 2 Laborers
- Installation of stirrups for tie beam 3 1 Steelworker, 2 Laborers
Masonry Works 23 4 Masons, 6 Laborers
- Pouring of concrete for footing 4 2 Masons, 4 Laborers
- Pouring of concrete for column 5 2 Masons, 4 Laborers
- Pouring of concrete for tie beam 4 2 Masons, 4 Laborers
- CHB 6" piling every 3 meters of span 6 2 Masons, 4 Laborers
- Filling mortar in CHB 6" piling 2 2 Masons, 2 Laborers
- Plastering both sides with a 16 mm thickness 2 2 Masons, 2 Laborers
Installation of 4 Lines of Barbed Wire 4 2 Laborers
- Preparation and measurement for barbed wire 2 1 Laborer
- Installation of barbed wire on top of the fence 2 2 Laborers
Perimeter Fence
Main Gate

Status: Not Started

Reason: All welders were


maximize at Wines Project
Main Entrance Road Concreting

Status: Not Started

Reason: The Road is in use


Staff house

Status: Lack of Materials c/o procurement and CAO


• Switches
• Outlets
• Lightings
• Metal furring framing for ceiling
• Ceiling board

You might also like