Wines Project

Barangay Road to Farm Map


Road Direction from Barangay Road via Bridge to
Kamagong & Laurel Farm

1 2 3

Barangay Road: First intersection after Bridge (Box Culvert): After the bridge, Crossing (Durian Trees): Turn
Wines Elementary School, turn RIGHT turn RIGHT on the next intersection LEFT on the next crossing

4 5 6

Finally, turn RIGHT to reach the


Turn RIGHT, follow the path ahead Turn RIGHT, follow the path ahead site (Module 2)
Wines Project

Kamagong Farm Update (Module 1)


Ghantt Chart (December 2022 – July 2023)
Installation and Erection of Steel Structures: 100%
(April 3, 2023-May 10, 2023)

H1 H2 H3
Installation of Roof Panels and Accessories-
30%

House
Activities: House 1 House 2
3

PU roof installation 100% 5% 5%

Ridge roll installation 100% 0% 0%

Ridge roll cover installation and


accessories 100% 0% 0%

 Waiting for the complete delivery of PU roof  House 2- lacking 9.35m PU roof, 120 pcs
 Ridge roll and ridge roll covers already at site  House 3- lacking 9.35m PU roof, 200 pcs
Installation of Wall Panels and Accessories-
85%

Activities: House 1 House 2 House 3

Installation of runners 100% 100% 100%

Installation of wall panels 100% 100% 100%

Installation of cable trays 100% 100% 100%

Application of silicon sealant 100% 100% 100%

Rectification of PU junction 50% 25% 25%

 H1-Completed rectification from the inside, and wall to roof. Lacking rectification from the outside (possible rat entry) and skirting (below)
 H2- Completed rectification from the inside (*Waiting for the arrival of PU roof)
 H3- Completed rectification from the inside (*Waiting for the arrival of PU roof)
Installation of ROXELL
Feeding System- 60%

House
Activities: 1
House 2 House 3

Unloading of Roxell equipment 100% 100% 100%

Feeder line hanger installation 100% 100% 100%

Overhead feeding system support 100% 100% 100%

Overhead feeding system installation 20% 0% 0%

House feeding system installation plus


0% 0% 0%
controls
 Waiting for back-up flock man (assembly of feeders)
 H1- Installed motors for feeder lines; drinker motors still in discussion with CENLO
 H2- Cannot start feeding system installation without roofing for House 2 and House 3
 H3- Cannot start feeding system installation without roofing for House 2 and House 3
Installation of SKOV
Ventilation System- 25%

House House
Activities: 1
House 2
3

Unloading of SKOV equipment 80% 50% 20%

Installation of ventilating fans 40% 0% 0%

Cooling pads/ gutter installation 0% 0% 0%


Tunnel door framing fabrication and
55% 55% 55%
installation

SKOV installation plus controls 10% 0% 0%

 SKOV equipment delivery is controlled in terms of installation schedule due to minimal spaces for safe keeping; LPC c/o Sir Alex
 Installed 4/6 blow fans, 2 were used as access for H1; H2&H3 needs roofing installation to be completed
 Cooling pads/ gutter installation waiting for c-purlins (2x6), status on-going PR
 Started cable pulling for blow fans at H1; waiting for roofing to complete for H2&H3 to start cable pulling
Installation of JANSEN
Nest System- 30%

House House
Activities: 1
House 2
3

Material hauling 90% 50% 50%

Lay-out of nest system 100% 0% 0%

Nest assembly 90% 0% 0%

Conveyor and flap motor Installation 85% 0% 0%

Controls 0% 0% 0%

 JANSEN equipment delivery is controlled in terms of installation schedule due to minimal spaces for safe keeping
 Markings, guide lay-out, etc for H1; H2&H3 needs roofing installation to be completed to start
 Nest assembly almost complete for H1 except for missing parts such as “metal sheet”; needs roofing at H2&H3 to start
Plumbing Works- 0%

House
Activities: House 1 House 2
3

 Waiting for approval of plans c/o


Water panel installation 0% 0% 0%
signatories

 Waiting for materials to arrive at site


Provisions for washing 0% 0% 0%
 Roxell (drinker line)materials needed for
plumbing system already at site
Water system for cooling pads
0% 0% 0%
Electrical Works- 25%

Activities: House 1 House 2 House 3

Installation of junction box and wires for


100% 100% 100%
switches

T8 assembly and lighting installation 10% 0% 0%

Installation of panel boards and wire


40% 0% 0%
arrangement for control room
Cable pulling 20% 0% 0%

Termination (All equipment) 0% 0% 0%

 T8 lightings are expected to arrive 3 rd week of June


 Roxell and MDP already installed at H1; H2&H3 needs roofing installation at least at control room to start
 Cable pulling for blow fans completed for H1; needs roofing at H2&H3 to start to avoid damages on wires due to rainc
Wines Project
Kamagong Farm

Mainlines (Plumbing and Electrical)


Perimeter and Site Developments
Decon and Staff House
Bridge
Mainline: Plumbing Mainline: Electrical

 CADEX- 100%
 Header Fabrication- 0%  Powerhouse- 95%
 Pump House- 0%  Service Entrance- 100%
 Pipe laying and connection- 0%  Application for DLPC- 10%
 Booster Pump Installation- 0%  Main Power Supply (Post)- 0%
 SOLARTECH- 90%  Main Line Termination- 0%
 Remaining works: Painting and Testing
Perimeter and Site Development

 Drainage System (Canal)- 85%


 Access Roads- 35%
 Perimeter Fence- 10%
 Perimeter Lights- 0%
 Septic Vaults- 60%
 Catch Basin- 0%
 Culverts- 0%
Decon Staff House

 Land Preparation & Foundation- 100%


 Land Preparation & Foundation- 100%
 CHB Piling & Column Concreting- 90%
 CHB Piling & Column Concreting- 65%
 Plastering & Floor Concreting- 0%
 Plastering & Floor Concreting- 20%
 Structural Truss Fabrication & Roofing- 40%
 Structural Truss Fabrication & Roofing- 40%
 Electrical & Plumbing Works- 0%
 Electrical & Plumbing Works- 0%
 Doors & Windows Installation- 0%
 Doors & Windows Installation- 0%
 Painting & Tiling Works- 0%
 Painting & Tiling Works- 0%