against overall PAF of 88.19% during the previous year.

The power station wise generation and PAF during the year
2022-23 are given in table below:

NAME OF POWER GENERATION ACTUAL ACTUAL PAF


STATIONS TARGET * (MU) GENERATION (MU) (%)
Baira Siul 736 628 88.05
Loktak 594 478 95.19
Salal 3726 3240 90.05
Tanakpur 522 535 86.21
Chamera-I 2305 1889 93.08
Uri 3142 2862 91.26
Rangit 353 332 90.31
Chamera-II 1553 1327 97.10
Dhauliganga 1278 1293 98.16
Dulhasti 2242 2083 92.01
Teesta-V 2812 2858 100.38
Sewa-II 549 508 99.84
Chamera-III 1151 1002 96.32
Chutak 221 167 61.83
TLDP-III 618 599 84.39
Nimoo-Bazgo 248 236 92.24
Uri-II 1713 1574 90.91
Parbati-III 737 652 54.31
TLDP-IV 758 735 86.64
Kishanganga 1713 1454 85.86
Parbati-II** 488 288 -
Total (Hydro) 27461 24740 88.75
Wind Power Project 94 77 -
Solar Power Project 106 90 -
Total 200 167 -
Total (NHPC) 27661 24907 88.75
Note:
*As per MoU FY 2022-23, Consolidated Generation Target is 32,611 MUs i.e. including Generation Target of NHPC
Limited & NHDC Limited. Actual generation for FY 2022-23 including generation of NHPC Limited & NHDC Limited is
30350 MUs.
** Actual Generation shown is infirm power.