You are on page 1of 1

TOP HEAD

Description Start Finish Completed Remaining


Remove Pipe
Distributor
Remove Top Grid
Install Temporary
Platform

BED #13
Description Start Finish Completed Remaining
Vacuum Catalyst
Remove Pipe
Distributor
Borescope/PT/LT

Remove Grid #2

BED #14
Description Start Finish Completed Remaining
Vacuum Catalyst
Remove Pipe
Distributor
Borescope/PT/LT

Remove Grid #3

BED #15
Description Start Finish Completed Remaining
Vacuum Catalyst
Remove Pipe
Distributor
Borescope/PT/LT

Remove Grid #4

BED #16
Description Start Finish Completed Remaining
Vacuum Catalyst
Remove Pipe
Distributor
Borescope/PT/LT

Remove Grid #5

BED #17