COMMENT RESOLUTION SHEET

PROJECT : EPC REVITALIZATION PROJECT OF RCC RU VI BALONGAN


Document No : U2004-015-G67-MO01-T-0496
Title : REQUISITION FOR SCAFFOLDING WORK
Rev :0

NO. PERTAMINA Comment CSO Answer


In CSO Requisition, the total amount of scaffolding to be installed for work
activity is based on the amount of M3 and material cost (from installation to
What is the contract strategy for this Req ? Generally the pre t/a scaffold demolition) for installation work during pre T/A and correction work during
1 contract is based on cost per M3 & t/a scaffolding is based on a reimbursable T/A and demolition after completion of T/A.
man / material rate (daywork).

There is not sufficient information or detail to bid this work in this doc. In the CSO Requisition document, only the work activities were described, and
the quantity have been calculated through on-site confirmation with a bidder.
2

Work packs prepared by the preparation team or by the mechanical contractor In CSO, scaffold installation work will be done together with the team that
would detailthe precise scaffold requirements, location, elevation, approx performs the mechanical works, so that the required location, size, time, etc.,
dimensions etc. will be decided to increase work efficiency and to minimize the loss.
The scaffold contractor would be responsible for installing the most economic
scaffold for each specific work pack to provide safe access for the work to be The CSO will check the site according to the work activity and install the most
carried out. This could be for example a scaffold erected from grade, a hanging efficient and safe form of scaffolding.
scaffold, a scaffold erectedfrom an existing structure or platform or an
extension to an existing scaffold.
3 What type of scaffold is proposed ? COS will use TUBE & FITTING basically. Quick fix type is only partially used in
Conventional tube & fittings or quick fix type ? the ground area where safety is secured
What is the proposed method for transporting the scaffold materials to the
work front(crane, hoist, pulley wheel etc) ? In COS, the basic method is to use a crane to move and load materials to the
location where scaffolding is required. The pully wheel is used for scaffolding
installation work on the upper part of the place where the material is loaded

Before removing the breeching, internal scaffold required up to main stack Already addad
splice. Remove top stack section, remove internal scaffold, remove lower stack 7) CO Boiler Maintenance Work - Scaffolding work for all activities external and
section internal area.
4 a) Before removing the breeching, internal scaffold required up to main stack
splice. Remove top stack section, remove internal scaffold, remove lower stack
section

Already changed
7) CO Boiler Full Module Replace Work - Scaffolding work for all activities
5 external area.
d) Prepare connection flange for removal on all boiler modules

Already confirmation
DWG

Already addad
7) CO Boiler Maintenance Work - Scaffolding work for all activities external and
internal area.
7 b) Install combustion chamber internal scaffold, to provide access for
temporary tie beam installation prior to removing lower module

Already addad
7) CO Boiler Maintenance Work - Scaffolding work for all activities external and
internal area.
8
c) Replace burner bodies (external) and burner tiles (internal)
COMMENT RESOLUTION SHEET
PROJECT : EPC REVITALIZATION PROJECT OF RCC RU VI BALONGAN
Document No : U2004-015-G67-MO01-T-0496
Title : REQUISITION FOR SCAFFOLDING WORK
Rev :0

Already removed
7) CO Boiler Maintenance Work - Scaffolding work for all activities external and
internal area.
9
d) Clean steam drum