Professional Documents
Culture Documents
Method Statement Example
Method Statement Example
TABLE OF CONTENTS
A. PURPOSE
B. SCOPE
C. REFERENCES
D. ABBREVIATIONS AND DEFINITIONS
E. ROLES AND RESPONSIBILITIES
F. HEALTH, SAFETY AND ENVIRONMENTAL PROCEDURE
G. MANPOWER
H. SURVEY AND STAKE OUT
1. Scope
2. References
3. Tools and Equipment
4. Prior Activities
5. Procedure
I. EXCAVATION AND BACKFILLING WORKS
1. Scope
2. References
3. Materials
4. Tools & Equipment
5. Procedure
J. FORMWORKS, REINFORCEMENT AND CONCRETING WORKS
1. Scope
2. Fabrication and Installation of Forms
2.1 Formwork Design
2.2 Ties
A. Purpose
The purpose of this method statement is to cover the activities involved in general
civil works in the project considering the quality and safety requirements and to
2
specify the requirements of civil construction including excavation, filling, and allied
activities complying with the contract document, and scope of work and approved
drawings/documents.
B. Scope
This Method Statement applies to all the civil works - Excavation including ground
preparation, setting out, backfilling, soil compaction, & concreting - related to the
construction of Substation as per project requirements, referring with approved
structural drawings.
C. References
1. Approved drawings
1. MS – Method Statement
2. ITP – Inspection Test Plan
3. AFI – Availability for Inspection
4. RFA – Request for Approval
5. PPE –Personal Protective Equipment
6. FDT – Field Density Test
7. WP –Work Permit
8. JHA – Job Hazard Analysis
2. Project In Charge –
3. Project Engineer –
5. Electrical Engineer –
3
6. Safety Officer –
7. QA/QC Engr. –
8. Surveyor –
9. Foreman –
10. Draftsman –
F. WORK PERMITS
2. Safety Barriers and Site sign boards will be installed prior to the work
commencement.
1. Before commencing of any work, the required and applicable work permits
shall be checked and ensure all requirements of WP are complied.
2. All workmen and staff shall wear the mandatory and job specific PPE. Pre-
task briefing shall be conducted on every day before starting the work.
Experienced and HSE inducted workmen shall be deployed for the work. All
personnel shall be cautioned while working near any live lines such as power
cable, water lines, drainage lines, etc.
H. HOUSEKEEPING
1. Housekeeping is the act of keeping the working environment clean from all
unnecessary waste materials. The equipment/tools/materials required for the
work shall be stored /stacked in such a manner so as to give a safe working
atmosphere to the workforce at site.
I. MANPOWER
4
2. Project-in-Charge
1
3. Project Engineer
1
4. Project Site Engineer
2
5. Electrical Site Engineer
1
6. Safety Officer
2
7. Foreman
2
8. Surveyor
1
9. Instrument/Rodman
2
10. Warehouseman
1
11. Admin Officer
1
12. Welder
4
13. Scaffolder
4
14. Mason/Carpenter
8
15. Steelman
2
16. Helper
6
17. Backhoe Operator
3
18. Boom truck Driver
2
19. Dump Truck Driver
3
1. Scope
1.1 This Method Statement describes a proper work procedure shall be carried out
during the excavation stage as per specification and contract drawings.
2. References
5
3. Materials
4.1 Excavator
4.2 Six Wheel Minidump Truck
5. Work Procedure
5.2 Excavation
5.2.1 The area to be excavated shall be properly marked and clear before
starting the works.
1. Scope
2. References
3. Materials
3.1 Concrete
6
fc’=4,000 psi @ 28 days for footings, Pedestals & Beams
(Tower Only)
fc’=3,000 psi @ 28 days for footings, Pedestals & Beams
3.2 Portland Cement: Type I
3.3 Coarse aggregates
2.2 Ties
Ties will be placed at such intervals that will not allow any movement or
deformation of the formwork beyond the specified tolerance limits. Forms for
small section elements, i.e, columns, shall be tied externally.
Through-ties shall be used for big area forms.
Formwork for footings, sides of beams, pedestal and other formworks not
supporting the concrete weight shall be removed.
7
2.3.3 The formwork removal procedure should be supervised by the
Site engineer to ensure that quality of hardened concrete in
structural member, i.e. it should be free from or has minimum
casting defects such as honeycombing, size and shape defects
etc. These defects in concrete influence the strength and
stability of structure. Thus immediate repair works can be done
or the members can be rejected.
3. REINFORCEMENT
3.1.1 Number and spacing of supports will be such that there is no sagging of
the stacked bars.
3.1.2 Stacked rebar will be covered with tarpaulins or such other means and
protected from mud, oil or any other thing that causes damage.
The reinforcement will be cut and bent in accordance with the approved bar bending
schedules. The bending of reinforcements will be done on the bending machine,
producing a gradual and even motion. Bars will be bent cold and at specified radii
3.3.1 The rebar received from the supplier will be inspected. All defective
materials will be repaired or replaced by the supplier.
3.3.2 The storage of rebar will be arranged above ground on padded supports,
using timber pieces or sand bags. The rebar will be covered with dark light
proof material to prevent rusting.
8
3.5.1 The reinforcement will be accurately fixed in the required position. The
bars intended to be on contact at passing points will be securely tied together.
3.5.2 After fixing, the reinforcement will be inspected for type, size, and
accuracy of placing. The areas where the coating will be found to be damaged
it will be repaired as per approved method statement.
4. CONCRETING
Out of the available transit mixer trucks, at least one will be kept as stand by. Before
the departure of the loaded transit mixer, the delivery ticket will be handed over to the
driver.
Before discharging the concrete at the point of delivery, the driver will provide the
Quality Control Engineer the delivery ticket identifying the material for each batch of
concrete.
Unless adequate protection is provided, concrete will not be placed during rain.
Immediately after placement, concrete will be protected from premature drying and
excessively hot temperatures and will be maintained with minimum moisture loss at
relatively constant temperature for a period necessary for the hydration of the cement
and hardening of the concrete. The curing of concrete will be carried out by pouring
or continuous sprinkling of water. After forms are removed, the concrete will be cured
up to the end of prescribed period.
9
4.6 Quality Control
4.6.2 Samples for conducting tests for determining the compressive strength
on concrete will be taken according to the specifications.
4.6.3 Concreting will be carried out using the approved design mixes and that
specified for the structure. The concrete from approved sources only will be
used for all concreting works.
5. TESTING OF CONCRETE
5.1 A third party laboratory as approved by the Contractor will be appointed to carry
out tests on concrete as may be applicable as per project specification.
5.2 Temperature, slump, unit weight and air content of fresh concrete shall be
measured at the point of pour, prior to placement in forms. Concrete not conforming
to the requirements of the specification shall be rejected. Test sample cylinders will be
collected in accordance with project specifications.
Refer to the site safety policy for general safety controls. One of the main aspects of this
procedure is Safety and Health Control. This is to control occurrence of injuries as well as
damage to equipment and properties during the entire construction period.
1. Tool Box meetings shall be conducted on every day before the start of the work.
2. Experienced workmen only shall be deployed for the work.
3. All personnel shall be cautioned while working near the pipes/ cables.
4. Hazard identification shall be done during toolbox meetings especially for heat.
In order to ensure a safe working environment during the entire construction period, the
following safety measures will be implemented.
10
6. All lifting equipment as well as its accessories such as sling wire, nylon sling,
shackles, chain blocks, crane hook and latch shall be inspected periodically.
1. PPE shall be issued to all workers such as safety shoes, hard hat, working gloves, ear
plugs, safety goggles and safety belt and or safety harness for workers who will be
assigned in elevated places.
2. Wearing of the basic PPE shall be enforced fully.
L. `
11