Unit : MNT
Project : New Ulaan Baatar International Airport construction project
A-1 UTILITY BOX CULVERT WORK SUM 1.00 3,150,619,028.72 1.00 3,073,487,798.58 1.00 0.00 1.00 3,073,487,798.58 97.6%
A-2 DRAINAGE WORK SUM 1.00 2,912,896,000.00 1.00 789,628,780.00 1.00 49,072,700.00 1.00 838,701,480.00 28.8%
A-3 ADDITIONAL WORKS SUM 1.00 348,920,380.00 1.00 344,270,100.24 1.00 4,770,670.00 1.00 349,040,770.24
A-4 TOTAL NET AMOUNT SUM 1.00 6,412,435,408.72 1.00 4,207,386,678.82 1.00 53,843,370.00 1.00 4,261,230,048.82
A-5 VAT SUM 1.00 641,243,540.87 1.00 420,738,667.88 1.00 5,384,337.00 1.00 426,123,004.88 66.5%
A-6 SUBTOTAL SUM 1.00 7,053,678,949.59 1.00 4,628,125,346.70 1.00 59,227,707.00 1.00 4,687,353,053.70 66.5%
B-1 ADD VARIATION ORDERS SUM 1.00 1.00 0.00 1.00 0.00 1.00 0.00 0.0%
B-2 VAT SUM 1.00 1.00 0.00 1.00 0.00 1.00 0.00 0.0%
B-3 SUBTOTAL SUM 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 0.0%
C-1 NET AMOUNT SUM 1.00 6,412,435,408.72 1.00 4,207,386,678.82 1.00 53,843,370.00 1.00 4,261,230,048.82 66.5%
C-2 VAT SUM 1.00 641,243,540.87 1.00 420,738,667.88 1.00 5,384,337.00 1.00 426,123,004.88 66.5%
C-3 TOTAL SUM 1.00 7,053,678,949.59 1.00 4,628,125,346.70 1.00 59,227,707.00 1.00 4,687,353,053.70 66.5%
D-1 LESS RETENTION (5%) SUM 1.00 1.00 231,406,267.33 1.00 2,961,385.35 1.00 234,367,652.68
D-2 ADD RETENTION RELEASE SUM 1.00 1.00 1.00 0.00 1.00
E-1 LESS BACKCHARGE FOR MATERIAL ETC. SUM 1.00 1.00 292,412,884.19 1.00 0.00 1.00 292,412,884.19
E-2 VAT SUM 1.00 1.00 29,201,530.48 1.00 0.00 1.00 29,201,530.48
E-3 SUBTOTAL SUM 1.00 0.00 1.00 321,614,414.68 1.00 0.00 1.00 321,614,414.68 0.0%
G ADD ADVANCED PAYMENT(9%) SUM 1.00 315,061,902.80 1.00 315,061,902.80 1.00 0.00 1.00 315,061,902.80
LESS ADVANCED PAYMENT RECOVERY
H SUM 1.00 1.00 315,061,902.80 1.00 0.00 1.00 315,061,902.80
(20% / OVER 20% OF PROGRESS)
ADD ADVANCED PAYMENT(10%)
I SUM 1.00 291,289,600.00 1.00 291,289,600.00 1.00 0.00 1.00 291,289,600.00
for VO_Drainage Works
LESS ADVANCED PAYMENT RECOVERY
J for VO_Drainage Works SUM 1.00 1.00 45,550,907.60 1.00 10,795,994.00 1.00 56,346,901.60
(20% / OVER 20% OF PROGRESS)
ACTUAL PAYMENT TOTAL SUM 1.00 7,053,678,949.59 1.00 4,320,143,357.09 1.00 45,470,327.65 1.00 4,365,613,684.74 61.9%
Date :
Site Engineer
A. Request for Interim Payment : Utility Box Culvert Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
0.0%
1 Box Culvert Work sum 1.00 2,842,007,308.72 2,894,767,064.58 0.00 2,894,767,064.58 101.9%
2 Manhole and Manhole Cover sum 1.00 240,276,075.00 178,720,734.00 0.00 178,720,734.00 74.4%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
A. Request for Interim Payment : Utility Box Culvert Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
0.0%
0.0%
TOTAL OF UBC SUM 1.00 3,150,619,028.72 1.00 3,073,487,798.58 1.00 0.00 1.00 3,073,487,798.58 97.6%
A. Request for Interim Payment : Utility Box Culvert Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
0.0%
1.1 Box culvert CT-1, Quantity 38nos, Length=25m m 950.00 1,892,788 1,798,148,600.00 938.30 1,776,002,980.40 0.00 0.00 938.30 1,776,002,980.40 98.8%
1.2 Box culvert CT-2, Quantity 3nos, Length=25m m 75.00 1,893,055 141,979,125.00 74.10 140,275,375.50 0.00 0.00 74.10 140,275,375.50 98.8%
1.3 Box culvert CT-3, Quantity 1nos, Length=22.55m m 22.55 1,958,765 44,170,150.75 21.74 42,583,551.10 0.00 0.00 21.74 42,583,551.10 96.4%
1.4 Box culvert CT-4, Quantity 1nos, Length=22.65m m 22.65 2,020,123 45,755,785.95 22.65 45,755,785.95 0.00 0.00 22.65 45,755,785.95 100.0%
1.5 Box culvert CT-5, Quantity 1nos, Length=25.9m m 25.90 1,920,403 49,738,437.70 25.90 49,738,437.70 0.00 0.00 25.90 49,738,437.70 100.0%
Box culvert CT-6, Quantity 2nos, Length=11.78-
1.6 nr 2.00 36,469,897 72,939,794.00 1.93 70,386,901.21 0.00 0.00 1.93 70,386,901.21 96.5%
16.1m
Box culvert CT-7, Quantity 4nos, Length=12.84-
1.7 nr 4.00 25,505,194 102,020,776.00 3.86 98,450,048.84 0.00 0.00 3.86 98,450,048.84 96.5%
8.13m
Box culvert CT-8, Quantity 1nos, Length=8.83-
1.8 nr 1.00 48,502,201 48,502,201.00 2.96 143,566,514.96 0.00 0.00 2.96 143,566,514.96 296.0%
24.76m
Box culvert CT-9, Quantity 2nos, Length=18.92-
1.9 nr 2.00 33,782,747 67,565,494.00 2.00 67,565,494.00 0.00 0.00 2.00 67,565,494.00 100.0%
6.47m
1.10 Box culvert CT-10, Quantity 1nos, Length=29.72m m 29.72 1,892,014 56,230,656.08 28.65 54,206,201.10 0.00 0.00 28.65 54,206,201.10 96.4%
1.11 Box culvert CT-11, Quantity 1nos, Length=30m m 30.00 1,933,706 58,011,180.00 28.92 55,922,777.52 0.00 0.00 28.92 55,922,777.52 96.4%
1.12 Box culvert CT-12, Quantity 1nos, Length=20.99m m 20.99 1,892,655 39,726,828.45 20.23 38,288,410.65 0.00 0.00 20.23 38,288,410.65 96.4%
1.13 Box culvert CT-13, Quantity 1nos, Length=12.53m m 12.53 1,896,806 23,766,979.18 12.53 23,766,979.18 0.00 0.00 12.53 23,766,979.18 100.0%
1.14 Box culvert CT-14, Quantity 1nos, Length=13.23m m 13.23 1,898,015 25,110,738.45 13.23 25,110,738.45 0.00 0.00 13.23 25,110,738.45 100.0%
1.15 Box culvert CT-15, Quantity 2nos, Length=24.37m m 48.74 1,893,741 92,300,936.34 48.74 92,300,936.34 0.00 0.00 48.74 92,300,936.34 100.0%
1.16 Box culvert CT-16, Quantity 1nos, Length=16.78m m 16.78 1,896,061 31,815,903.58 16.78 31,815,903.58 0.00 0.00 16.78 31,815,903.58 100.0%
1.17 Box culvert CT-17, Quantity 1nos, Length=25.56m m 25.56 1,893,361 48,394,307.16 24.64 46,652,415.04 0.00 0.00 24.64 46,652,415.04 96.4%
1.18 Box culvert CT-18, Quantity 1nos, Length=17.46m m 17.46 1,895,788 33,100,458.48 16.83 31,906,112.04 0.00 0.00 16.83 31,906,112.04 96.4%
1.19 Box culvert CT-19, Quantity 1nos, Length=15.55m m 15.55 1,896,636 29,492,689.80 14.99 28,430,573.64 0.00 0.00 14.99 28,430,573.64 96.4%
1.20 Box culvert CT-20, Quantity 1nos, Length=22.8m m 22.80 1,457,731 33,236,266.80 21.98 32,040,927.38 0.00 0.00 21.98 32,040,927.38 96.4%
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
A 2 Manhole and Manhole Cover 0.00 0 240,276,075.00 0.00 178,720,734.00 0.00 0.00 178,720,734.00 74.4%
2.1.1 Manhole Type-PI-1 nr(s) 2.00 2,924,427 5,848,854.00 1.60 4,679,083.00 0.00 0.00 1.60 4,679,083.20 80.0%
2.1.2 Manhole Type-PI-2 nr(s) 11.00 6,767,641 74,444,051.00 8.80 59,555,241.00 0.00 0.00 8.80 59,555,240.80 80.0%
2.1.3 Manhole Type-PI-3 nr(s) 1.00 26,188,950 26,188,950.00 0.80 20,951,160.00 0.00 0.00 0.80 20,951,160.00 80.0%
2.3 Box Culvert Opening Cover 0.00 0.00 0.00 0.00 0.0%
2.3.1 Concrete cover Type -T1 nr 90.00 86,710 7,803,900.00 30.00 2,601,300.00 0.00 0.00 30.00 2,601,300.00 33.3%
2.3.2 Concrete cover Type -T2 nr 88.00 139,265 12,255,320.00 30.00 4,177,950.00 0.00 0.00 30.00 4,177,950.00 34.1%
3.1 Step (Field Type RC30L-300) W=300mm x 300mm nos 1,267.00 53,935 68,335,645.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Total sum 0.00 0 3,150,619,028.72 1.00 3,073,487,798.58 1.00 0.00 1.00 3,073,487,798.58 97.6%
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
B Drainage Work
0.0%
1 Storm Water Drainage Work _Airside sum 1.00 2,145,379,000.00 789,628,780.00 49,072,700.00 838,701,480.00 39.1%
2 Storm Water Drainage Work_Landside sum 1.00 752,245,000.00 0.00 0.00 0.00 0.0%
3 Incidental Civil Work sum 1.00 15,272,000.00 0.00 0.00 0.00 0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
0.0%
TOTAL OF DRAINAGE SUM 1.00 2,912,896,000.00 1.00 789,628,780.00 1.00 49,072,700.00 1.00 838,701,480.00 28.8%
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
B 1 Storm Water Drainage Work _Airside 2,145,379,000.00 789,628,780.00 49,072,700.00 838,701,480.00 39.1%
0.0%
1.1 V Shaped Channel (VCH) 0.00 0.00 0.00 0.00 0.0%
V-shaped channel; including earth work for
excavation, backfilling and removal surplus
0.00 0.00 0.00 0.00 0.00 0.0%
material, concrete (18N/mm2), expansion joint,
gravel and all necessary formwork.
0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Channel Type -VA1
1.1.1 m 1,379.00 166,000 228,914,000.00 0.00 35.00 5,810,000.00 35.00 5,810,000.00 2.5%
Width =4,500 mm
Channel Type -VA2
1.1.2 Width = 4,500 mm (Service Road Crossing, m 5.00 287,000 1,435,000.00 0.00 0.00 0.00 0.00 0.0%
Reinforced concrete)
0.00 0 0.00 0.00 0.00 0.00
1.2 Trapezoidal Channel (TCH) 0.00 0 0.00 0.00 0.00 0.00
Trapezoidal channel; including earth work for
excavation, backfilling and removal surplus
material, reinforced concrete (18N/mm2), 0.00 0 0.00 0.00 0.00 0.00
expansion joint, gravel and all necessary
formwork.
0.00 0 0.00 0.00 0.00 0.00
Channel Type -TA1
1.2.1 Width = 300 mm, Depth = 300 mm m 0.00 0 0.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 1.0 m
Channel Type -TA2
1.2.2 Width = 500 mm, Depth = 500 mm m 456.00 132,000 60,192,000.00 42.00 5,544,000.00 32.20 4,250,400.00 74.20 9,794,400.00 16.3%
Excavation Depth (Average) = 1.5 m
Channel Type -TA3
1.2.3 Width = 500 mm, Depth = 600 mm m 523.00 147,000 76,881,000.00 386.12 56,759,640.00 49.30 7,247,100.00 435.42 64,006,740.00 83.3%
Excavation Depth (Average) = 1.5 m
Channel Type -TA4
1.2.4 Width = 1000 mm, Depth = 600 mm m 0.00 0 0.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 1.5 m
Channel Type -TA5
1.2.5 Width = 1000 mm, Depth = 700 mm m 640.00 221,000 141,440,000.00 432.36 95,551,560.00 52.20 11,536,200.00 484.56 107,087,760.00 75.7%
Excavation Depth (Average) = 2.3 m
Channel Type -TA6
1.2.6 Width = 1000 mm, Depth = 900 mm m 0.00 0 0.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 1.8 m
Channel Type -TA7
1.2.7 Width = 1000 mm, Depth = 1000 mm m 1,022.00 277,000 283,094,000.00 184.40 51,078,800.00 60.00 16,620,000.00 244.40 67,698,800.00 23.9%
Excavation Depth (Average) = 2.8 m
Channel Type -TA8
1.2.8 Width = 1000 mm, Depth = 1100 mm m 0.00 0 0.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 3.3 m
Channel Type -TA9
1.2.9 Width = 1000 mm, Depth = 1400 mm m 327.00 352,000 115,104,000.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 4.1 m
Channel Type -TA10
1.2.10 Width = 1500 mm, Depth = 1100 mm m 693.00 355,000 246,015,000.00 527.01 187,088,550.00 0.00 0.00 527.01 187,088,550.00 76.1%
Excavation Depth (Average) = 2.4 m
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
Earth Ditch Protection Type - EPA-3
Width =500mm, Thickness = 25cm
1.4.3 m 0.00 0 0.00 0.00 0.00 0.00 0.00
Average Depth = more than 2.0m and less than
3.0m
0.00 0 0.00 0.00 0.00 0.00 0.00
1.5 Pipe Culvert (RCP) 0.00 0 0.00 0.00 0.00 0.00 0.00
Pipe culvert; including earth work for excavation,
backfilling and removal surplus material,
reinforced concrete (24N/mm2) or concrete (18 0.00 0 0.00 0.00 0.00 0.00 0.00
N/mm2), expansion joint, levelling concrete,
gravel and all necessary formwork.
0.00 0 0.00 0.00 0.00 0.00 0.00
Pipe Type -PA1
1.5.1 φ= 500 mm (90°concrete foundation) m 37.00 115,000 4,255,000.00 26.74 3,075,100.00 0.00 0.00 26.74 3,075,100.00 72.3%
Excavation Depth (Average) = 1.8 m
Pipe Type -PA2
1.5.2 φ= 600 mm (90°concrete foundation) m 8.00 187,000 1,496,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Excavation Depth (Average) = 1.5 m
Pipe Type -PA3
1.5.3 φ= 900 mm (90°concrete foundation) m 9.00 473,000 4,257,000.00 6.75 3,192,750.00 0.00 0.00 6.75 3,192,750.00 75.0%
Excavation Depth (Average) = 2.5 m
Pipe Type -PA4
1.5.4 φ= 1000 mm (90°concrete foundation) m 1,435.00 204,000 292,740,000.00 1,299.72 265,142,880.00 0.00 0.00 1,299.72 265,142,880.00 90.6%
Excavation Depth (Average) = 2.5 m
Pipe Type -PA5
φ= 1000 mm (360°reinforced concrete
1.5.5 m 131.00 543,000 71,133,000.00 116.00 62,988,000.00 0.00 0.00 116.00 62,988,000.00 88.6%
foundation)
Excavation Depth (Average) = 5.0 m
Pipe Type -PA6
1.5.6 φ= 1200 mm (90°concrete foundation) m 212.00 170,000 36,040,000.00 111.30 18,921,000.00 0.00 0.00 111.30 18,921,000.00 52.5%
Excavation Depth (Average) = 2.6 m
Pipe Type -PA7
1.5.7 φ= 1500 mm (180°concrete foundation) m 0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 3.5 m
Pipe Type -PA8
φ= 1500 mm (360°reinforced concrete
1.5.8 m 0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00
foundation)
Excavation Depth (Average) = 4.2 m
0.00 0 0.00 0.00 0.00 0.00 0.00
1.6 Pipe Culvert Head Wall (RCP Wall) 0.00 0 0.00 0.00 0.00 0.00 0.00
Pipe culvert head wall; including earth work for
excavation, backfilling and removal surplus
0.00 0 0.00 0.00 0.00 0.00 0.00
material, concrete (18N/mm2), gravel and all
necessary formwork.
0.00 0 0.00 0.00 0.00 0.00 0.00
Pipe Type -PA1
1.6.1 nr 1.00 1,001,000 1,001,000.00 0.00 0.00 0.00 0.00
φ= 500 mm (90°concrete foundation)
Pipe Type -PA2
1.6.2 nr 2.00 1,001,000 2,002,000.00 0.00 0.00 0.00 0.00
φ= 600 mm (90°concrete foundation)
Pipe Type -PA3
1.6.3 nr 2.00 1,001,000 2,002,000.00 0.00 0.00 0.00 0.00
φ= 900 mm (90°concrete foundation)
PA6 was changed to
Pipe Type -PA6
1.6.4 nr 6.00 1,001,000 6,006,000.00 0.00 2.00 2,002,000.00 2.00 2,002,000.00 PA7 unit price shall
φ= 1200 mm (90°concrete foundation)
change
Pipe Type -PA7
1.6.5 nr 0.00 0 0.00 0.00 0.00 0.00 0.00
φ= 1500 mm (180°concrete foundation)
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
Pipe Type -PA8
1.6.6 nr 0.00 0 0.00 0.00 0.00 0.00 0.00
φ= 1500 mm (360°concrete foundation)
0.00 0 0.00 0.00 0.00 0.00 0.00
1.7 U-Shaped Channel (UCH) 0.00 0 0.00 0.00 0.00 0.00 0.00
U-shaped channel; including earth work for
excavation, backfilling and removal surplus
material, reinforced concrete (24 N/mm2) or
0.00 0 0.00 0.00 0.00 0.00 0.00
concrete (18 N/mm2), levelling concrete, cover;
grating or checkered plate, expansion joint and all
necessary formwork.
0.00 0 0.00 0.00 0.00 0.00 0.00
Channel Type -UA1
Width =600mm, Depth =802 ~1386 mm
1.7.1 m 0.00 0 0.00 0.00 0.00 0.00 0.00
Reinforced concrete (24 N/mm2), Cover: Grating
(T-25)
Channel Type -UA2
Steep Drainage, Width =500 mm, Depth =500
1.7.2 mm m 43.00 7,519,000 323,317,000.00 0.00 0.00 0.00 0.00 0.0%
Concrete (18 N/mm2), Cover: Checkered Plates
(2m per one place)
0.00 0 0.00 0.00 0.00 0.00 0.00
1.8 Box Culvert (C-BOX) 0.00 0 0.00 0.00 0.00 0.00 0.00
Box culvert; including earth work for excavation,
backfilling and removal surplus material,
reinforced concrete (24N/mm2), Levelling 0.00 0 0.00 0.00 0.00 0.00 0.00
concrete, gravel, expansion joint and all
necessary formwork.
0.00 0 0.00 0.00 0.00 0.00 0.00
Box culvert (AW4-2)
1.8.1 m 81.00 771,000 62,451,000.00 0.00 0.00 0.00 0.00 0.0%
Width = 1300 mm, Height = 1400 mm
Box culvert (AE5-2)
1.8.2 m 0.00 0 0.00 0.00 0.00 0.00 0.00
Width = 1300 mm, Height = 1300 mm
0.00 0 0.00 0.00 0.00 0.00 0.00
1.9 Retaining Wall 0.00 0 0.00 0.00 0.00 0.00 0.00
Retaining wall; including earth work for
excavation, backfilling and removal surplus
material, reinforced concrete (24N/mm2) bases, 0.00 0 0.00 0.00 0.00 0.00 0.00
Levelling concrete, gravel, expansion joint and all
necessary formwork.
0.00 0 0.00 0.00 0.00 0.00 0.00
Wing Wall (AE5-2 Inflow)
1.9.1 Joint for Box Culvert & Trapezoidal Channel nr 0.00 0 0.00 0.00 0.00 0.00 0.00
Width = 0.5 m Height = 2.9 m
Wing Wall (AE5-2 Outflow)
1.9.2 Joint for Box Culvert & Trapezoidal Channel nr 0.00 0 0.00 0.00 0.00 0.00 0.00
Width = 0.5 m Height = 3.2 m
L Shaped Retaining Wall (AW4-2 Inflow)
1.9.3 Joint for Box Culvert & Trapezoidal Channel nr 1.00 12,580,000 12,580,000.00 1.00 12,580,000.00 0.00 0.00 1.00 12,580,000.00 100.0%
Width = 0.4 m H = 4.7 m
L Shaped Retaining Wall (AW4-2 Outflow)
1.9.4 Joint for Box Culvert & Trapezoidal Channel nr 1.00 10,823,000 10,823,000.00 1.00 10,823,000.00 0.00 0.00 1.00 10,823,000.00 100.0%
Width = 0.4 m H = 4.3 m
0.00 0 0.00 0.00 0.00 0.00 0.00
1.10 Parapet Wall 0.00 0 0.00 0.00 0.00 0.00 0.00
Parapet wall; including earth work for excavation,
backfilling and removal surplus material,
0.00 0 0.00 0.00 0.00 0.00 0.00
reinforced concrete (24N/mm2) bases, expansion
joint and all necessary formwork.
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
0.00 0 0.00 0.00 0.00 0.00 0.00
Parapet Wall (AW4-2, Inflow)
1.10.1 nr 1.00 1,206,000 1,206,000.00 1.00 1,206,000.00 0.00 0.00 1.00 1,206,000.00 100.0%
Wall Height = 2.7 m
Parapet Wall (AW4-2, Outflow)
1.10.2 nr 1.00 1,206,000 1,206,000.00 1.00 1,206,000.00 0.00 0.00 1.00 1,206,000.00 100.0%
Wall Height = 2.3 m
0.00 0 0.00 0.00 0.00 0.00 0.00
1.11 Manholes (M-AW, M-AE) 0.00 0 0.00 0.00 0.00 0.00 0.00
Manhole; including earth work for excavation,
backfilling and removal surplus material,
reinforced concrete (24N/mm2), Lean concrete, 0.00 0 0.00 0.00 0.00 0.00 0.00
sand bedding, manhole covers, and all necessary
formwork and steel ladder rungs and hook.
0.00 0 0.00 0.00 0.00 0.00 0.00
Manhole Type - MA-1
1.11.1 nr 4.00 480,000 1,920,000.00 1.00 480,000.00 0.00 0.00 1.00 480,000.00
H≦1.4 m bar arrangement: single σck=24 N/mm
Manhole Type - MA-2
1.11.2 H>1.4 m bar arrangement: double σck=24 nr 6.00 1,607,000 9,642,000.00 2.00 3,214,000.00 1.00 1,607,000.00 3.00 4,821,000.00 50.0%
N/mm
Manhole Type - MA-3
1.11.3 nr 9.00 2,395,000 21,555,000.00 4.50 10,777,500.00 0.00 0.00 4.50 10,777,500.00 50.0%
H>2.8 m special shape σck=24 N/mm
0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
B 2 Storm Water Drainage Work_Landside 0.00 0 752,245,000.00 0.00 0.00 0.00 0.00 0.00 0.0%
0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
2,1 Earth Ditch (ED) 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Earth ditch; including earth work for excavation,
0.00 0.00 0.00 0.00 0.00 0.00 0.0%
backfilling and removal surplus material.
0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Channel Type - ED-1
2,1,1 m 2,960.00 10,000 29,600,000.00 0.00 0.00 0.00 0.00
Width = 500 mm, Average Depth = 710 mm
Channel Type - ED-2
2,1,2 m 0 0.00 0.00 0.00 0.00 0.00
Width = 600 mm, Average Depth = 910 mm
Channel Type - ED-3
2,1,3 m 27.00 35,000 945,000.00 0.00 0.00 0.00 0.00
Width = 800 mm, Average Depth = 1,520 mm
0 0.00 0.00 0.00 0.00 0.00
2,2 Earth Ditch Protection (EDP) 0 0.00 0.00 0.00 0.00 0.00
Earth ditch protection; including earth work for
excavation, backfilling and removal surplus
0 0.00 0.00 0.00 0.00 0.00
material, concrete (18N/mm2), expansion joint,
gravel and all necessary formwork.
0 0.00 0.00 0.00 0.00 0.00
Channel Type - EDP-1
2,2,1 Width = 500 mm, Average Depth = 800 mm m 727.00 92,000 66,884,000.00 0.00 0.00 0.00 0.00
Thickness t = 150 mm
Channel Type - EDP-2
2,2,2 Width = 600 mm, Average Depth = 910 mm m 10.00 120,000 1,200,000.00 0.00 0.00 0.00 0.00
Thickness t = 150 mm
Channel Type - EDP-3
2,2,3 Width = 800 mm, Average Depth = 1,520 mm m 15.00 190,000 2,850,000.00 0.00 0.00 0.00 0.00
Thickness t = 150 mm
0 0.00 0.00 0.00 0.00 0.00
2,3 Pipe Culvert (RCP) 0 0.00 0.00 0.00 0.00 0.00
Pipe Culvert; including earth work for excavation,
backfilling and removal surplus material,
0 0.00 0.00 0.00 0.00 0.00
reinforced concrete (24N/mm2), Lean concrete,
sand bedding, and all necessary formwork.
0 0.00 0.00 0.00 0.00 0.00
Pipe Type -RCP-1
2,3,1 φ= 500mm (90°concrete foundation) m 272.00 82,000 22,304,000.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) = 1626 mm
Pipe Type -RCP-3
2,3,2 φ= 800mm (90°concrete foundation) m 370.00 172,000 63,640,000.00 0.00 0.00 0.00 0.00
Excavation Depth (Average) =2,210 mm
2,4 Pipe Culvert Head Wall (HWP) 0 0.00 0.00 0.00 0.00 0.00
Head Wall; including earth work for excavation,
backfilling and removal surplus material, concrete 0 0.00 0.00 0.00 0.00 0.00
(18N/mm2), gravel and all necessary formwork.
0 0.00 0.00 0.00 0.00 0.00
Wall Type - HWP-1
2,4,1 φ = 500 mm (90°concrete foundation), nr 21.00 846,000 17,766,000.00 0.00 0.00 0.00 0.00
Average Height = 1,587mm
Wall Type -HWP-3
2,4,2 φ = 800 mm (90°concrete foundation), nr 1.00 1,276,000 1,276,000.00 0.00 0.00 0.00 0.00
Average Height =2,135mm
0 0.00 0.00 0.00 0.00 0.00
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
2,5 U- SHAPED CHANNEL HEAD WALL (HWUCH) 0 0.00 0.00 0.00 0.00 0.00
Head Wall; including earth work for excavation,
backfilling and removal surplus material, concrete 0 0.00 0.00 0.00 0.00 0.00
(18N/mm2), gravel and all necessary formwork.
0 0.00 0.00 0.00 0.00 0.00
Wall Type HWUCH- 1:
2,5,1 nr 3.00 588,000 1,764,000.00 0.00 0.00 0.00 0.00
W =300mm, Average Height =1,162mm
Wall Type HWUCH- 2:
2,5,2 nr 2.00 633,000 1,266,000.00 0.00 0.00 0.00 0.00
W =500mm, Average Height = 1.293mm
0 0.00 0.00 0.00 0.00 0.00
2,6 U Shaped Channel (UCH) 0 0.00 0.00 0.00 0.00 0.00
U-Shaped Channel; including earth work for
excavation, backfilling and removal surplus
material, reinforced concrete (24N/mm2), Lean
0 0.00 0.00 0.00 0.00 0.00
concrete, sand bedding, Grating covers, and all
necessary formwork and steel ladder rungs and
hook.
0 0.00 0.00 0.00 0.00 0.00
Channel Type - UCH- 1
2,6,1 m 213.00 151,000 32,163,000.00 0.00 0.00 0.00 0.00
W =300mm, H =530 ~906mm
Channel Type - UCH- 2
2,6,2 m 256.00 161,000 41,216,000.00 0.00 0.00 0.00 0.00
W =500mm, H =630 ~756mm
Channel Type - UCH- 3
2,6,3 m 194.00 212,000 41,128,000.00 0.00 0.00 0.00 0.00
W =600mm, H =650 ~1081mm
0 0.00 0.00 0.00 0.00 0.00
2,7 U Shaped Channel L-Gutter (UCHL) 0 0.00 0.00 0.00 0.00 0.00
U-Shaped Channel; including earth work for
excavation, backfilling and removal surplus
material, reinforced concrete (24N/mm2), Lean
0 0.00 0.00 0.00 0.00 0.00
concrete, sand bedding, Concrete covers, and all
necessary formwork and steel ladder rungs and
hook
0 0.00 0.00 0.00 0.00 0.00
Channel Type - UCHL -1
2,7,1 m 162.00 299,000 48,438,000.00 0.00 0.00 0.00 0.00
W =300mm, H =451~1505mm
Channel Type - UCHL -2
2,7,2 m 296.00 494,000 146,224,000.00 0.00 0.00 0.00 0.00
W =500mm, H =750mm
0 0.00 0.00 0.00 0.00 0.00
2,8 Manhole 0 0.00 0.00 0.00 0.00 0.00
Manhole; including earth work for excavation,
backfilling and removal surplus material,
reinforced concrete (24N/mm2), Lean concrete, 0 0.00 0.00 0.00 0.00 0.00
sand bedding, manhole covers, and all necessary
formwork and steel ladder rungs and hook.
0 0.00 0.00 0.00 0.00 0.00
Manhole Type MA- 1
2,8,1 H≦1.4m(Average Height =911mm) bar nr 4.00 10,485,000 41,940,000.00 0.00 0.00 0.00 0.00
arrangement: single σck=24N/mm
Manhole Type MA - 2
2,8,2 H>1.4m (Average Height =1815mm) bar nr 17.00 11,273,000 191,641,000.00 0.00 0.00 0.00 0.00
arrangement: double σck=24N/mm
0 0.00 0.00 0.00 0.00 0.00
2,9 Access Road Pipe Culvert 0 0.00 0.00 0.00 0.00 0.00
B. Request for Interim Payment : Drainage Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
Pipe Culvert φ= 1500mm (90°concrete
foundation)
Pipe Culvert; including earth work for excavation,
2,9,1 backfilling and removal surplus material, m 0 0.00 0.00 0.00 0.00 0.00
reinforced concrete pipe (30 Mpa), joint material,
Lean concrete, sand bedding, and all necessary
Head Wall φ = 1500 mm (90°concrete
formwork.
foundation)
Head Wall; including Floor, Cut Off Wall, earth
2,9,2 work for excavation, backfilling and removal nr 0 0.00 0.00 0.00 0.00 0.00
surplus material, reinforced concrete (30 Mpa),
Stone Pitching work, gravel and all necessary
formwork. 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
B 3 Incidental Civil Work 0 15,272,000.00 0.00 0.00 0.00 0.00 0.0%
0 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
3,1 Storm Water Drainage
Total sum 0.00 0 2,912,896,000.00 1.00 789,628,780.00 1.00 49,072,700.00 1.00 838,701,480.00 28.8%
C. Request for Interim Payment : Additional Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
C Additional Works
0.0%
1 LP Steel Support nrs 16.00 3,727,270 59,636,320 17.00 63,363,590 0.00 0 17.00 63,363,590 106.3%
0 0 0.00 0.00 0
2 Bituminous Double Coating sqm 18,264.00 12,790 233,596,560 17,608.99 225,219,010 373.00 4,770,670 17,981.99 229,989,680 98.5%
0 0 0.00 0 0 0.0%
3 Box Culvert (C-BOX) m 81.00 687,500 55,687,500 81.00 55,687,500 0.00 0 81.00 55,687,500 100.0%
0 0.00 0 0.0%
0 0.00 0 0 0.0%
0.00 0 0 0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
C. Request for Interim Payment : Additional Works / September of 2015
Project : New Ulaan Baatar International Airport construction project Unit : MNT / VAT Excluded
BILL NO. WORK DESCRIPTION UNIT SUBCONTRACT PREVIOUS THIS MONTH ACCUM.
REMARKS
Q'ty UNIT RATE AMOUNT Q'ty AMOUNT Q'ty AMOUNT Q'ty AMOUNT
0.0%
0.0%
TOTAL OF DRAINAGE SUM 1.00 348,920,380 1.00 344,270,100 1.00 4,770,670 1.00 349,040,770 100.0%
Variation List /September of 2015
Project : New Ulaan Baatar International Airport construction project (Unit : MNT / VAT Excluded)
Total 0
Backcharge List / September of 2015
Project : New Ulaan Baatar International Airport construction project (Unit : MNT / VAT Excluded)
Total 292,412,884.19
Penalty List / September of 2015
Project : New Ulaan Baatar International Airport construction project (Unit : MNT / VAT Included)
Total 700,000.00
Detail of deduction for Advanced Payment / September of 2015
Project : New Ulaan Baatar International Airport construction project
Deduction of AP conditionOver 20% of Progress / Deduction 20% of Interim Payment (Unit : MNT / VAT Included)
20% of Contract Price Accu. Executed Value Exceeding Amount Deduction Amount 20% of
No. Month Remark
(A) (B) over 20% (C)=(B)-(A) Interim Payment (C)
2016 AP Deductions
Total 56,346,901.60
Quantity Calculation / September of 2015
10 1 Box Culvert: Including formwork , falsework, Unit Q'ty Unit price Amount 5.0% 23.0% 43.0% 29.0% 5.0% 23.0% 43.0% 29.0% 5.0% 23.0% 43.0% 29.0%
rebar work , scaffolding, concrete, curing , Q'ty Sum Q'ty Sum Q'ty Sum
expansion joint, slip bar, box out opening (M) (M) (M)
etc. Lean Bottom Wall Slab Top Slab Lean Bottom Wall Slab Top Slab Lean Bottom Wall Slab Top Slab
3 Miscellaneous Work Unit Q'ty Unit Price Amount Previous This month Accum.
Step (Field Type RC30L-300) W=300mm x
3.1 300mm nos 1,267 53,935 68,335,645 -
68,335,645
UBC Bituminous Double Coating Quantity / September of 2015
TYPE
Quantity Unit Price Segment Area Amount
Segment
(VAT
Structure Surface excl.) This This
No. Type Num. Length Width Height Previous Accum. Previous Accum. Previous This Month Accum.
Area Month Month
1 A-1 CT-3 1 22.66 4.88 3.30 260.14 12,790.00 1 0 1 260 0 260 3327150 0 3327150
2 A-2 CT-10 1 29.70 4.88 3.30 340.98 12,790.00 1 0 1 340.979 0 341 4361121 0 4361121
3 A-3 CT-7 1 10.84 3.30 128.85 12,790.00 1 0 1 128.848 0 129 1647966 0 1647966
Segment A
4 A-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
5 A-5 CT-11 1 31.36 4.88 3.30 359.98 12,790.00 1 0 1 359.978 0 360 4604123 0 4604123
6 A-6 CT-6 1 12.21 3.30 180.72 12,790.00 1 0 1 180.724 0 181 2311465 0 2311465
7 B-1 CT-12 1 20.98 4.88 3.30 240.79 12,790.00 1 0 1 241 0 241 3079742 0 3079742
8 B-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment B 9 B-3 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
10 B-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
11 B-5 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
12 C-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
13 C-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment C
14 C-3 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
15 C-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
16 D-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
17 D-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment D
18 D-3 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
19 D-4 CT-2 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
20 E-1 CT-7 1 10.84 3.30 128.85 12,790.00 1 0 1 128.848 0 129 1647966 0 1647966
21 E-2 CT-13 1 12.52 4.88 3.30 143.70 12,790.00 1 0 1 144 0 144 1837861 0 1837861
22 E-3 CT-6 1 12.21 3.30 180.72 12,790.00 1 0 1 180.724 0 181 2311465 0 2311465
Segment E
23 E-4 CT-4 1 22.64 4.88 3.30 259.91 12,790.00 1 0 1 260 0 260 3324213 0 3324213
24 E-5 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
25 E-6 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
26 F-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
27 F-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment F 28 F-3 CT-14 1 13.23 4.88 3.30 151.82 12,790.00 1 0 1 152 0 152 1941816 0 1941816
29 F-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
B 30 F-5 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
o 31 G-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
x
32 G-2 CT-2 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
C 33 G-3 CT-9 1 14.06 3.30 162.81 12,790.00 1.00 0.00 1 163 0 163 2082385 0 2082385
Box
u Segment G 34 G-4 CT-15 1 24.35 4.88 3.30 279.54 12,790.00 1 0 1 280 0 280 3575291 0 3575291
Culvert
l 35 G-5 CT-8 1 15.24 3.30 241.19 12,790.00 1.00 0.000 1 241 0 241 3084820 0 3084820
v
e
r
t
C
Box
u Segment G
Culvert
l
v
36 G-6 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
e
r 37 G-7 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
t 38 H-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
39 H-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment H
40 H-3 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
41 H-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
42 I-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
43 I-2 CT-16 1 16.76 4.88 3.30 192.40 12,790.00 1 0 1 192 0 192 2460857 0 2460857
44 I-3 CT-8 1 15.24 3.30 241.19 12,790.00 1 0 1 241 0 241 3084820 0 3084820
Segment
45 I-4 CT-15 1 24.35 4.88 3.30 279.54 12,790.00 1 0 1 280 0 280 3575291 0 3575291
I
46 I-5 CT-9 1 14.06 3.30 162.81 12,790.00 1 0 1 163 0 163 2082385 0 2082385
47 I-6 CT-2 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
48 I-7 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
49 J-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
50 J-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment J
51 J-3 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
52 J-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
53 K-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
54 K-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
Segment K
55 K-3 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
56 K-4 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
57 L-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
58 L-2 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
59 L-3 CT-17 1 25.56 4.88 3.30 293.43 12,790.00 1 0 1 293 0 293 3752954 0 3752954
Segment L
60 L-4 CT-7 1 10.84 3.30 128.85 12,790.00 1 0 1 128.848 0 129 1647966 0 1647966
61 L-5 CT-18 1 17.44 4.88 3.30 200.26 12,790.00 1 0 1 200 0 200 2561289 0 2561289
62 L-6 CT-7 1 10.84 3.30 128.85 12,790.00 1 0 1 128.848 0 129 1647966 0 1647966
63 M-1 CT-1 1 25.00 4.88 3.30 287.00 12,790.00 1 0 1 287 0 287 3670730 0 3670730
64 M-2 CT-19 1 15.55 4.88 3.30 178.51 12,790.00 1 0 1 179 0 179 2283194 0 2283194
Segment
65 M-3 CT-8 1 15.24 3.30 241.19 12,790.00 1 0 1 241.19 0 241 3084820 0 3084820
M
66 M-4 CT-20 1 25.90 4.88 3.30 297.33 12,790.00 1 0 1 297 0 297 3802876 0 3802876
67 M-5 CT-5 1 22.79 4.88 3.30 261.63 12,790.00 1 0 1 262 0 262 3346237 0 3346237
SHNM B.culvert 68 1 176.00 12,790.00 1 0 1 176 0 176 2251040 0 2251040
SHNM B.culvert 69 1 373.00 12,790.00 0 1 1 0 373 373 0 4770670 4770670
Subtotal 1 69 1,492.40 17,608.99 68 0 69 17,609 373 17,982 225,219,010 4,770,670 229,989,680
LP steel support / September of 2015
Q'ty Amount
LP Support Unit Q'ty Unit Price Amount
Previous This month Accum. Previous This month Accum.
H-beam LP
nos 16 3,727,270 59,636,320 17 0 17 63,363,590 - 63,363,590.00
support
Work Quantity / September of 2015
2,8 Box Culvert (C-BOX) Q'ty
Project : New Ulaan Baatar International Airport construction project Period ending 25 September 2015
Project : New Ulaan Baatar International Airport construction project Period ending 25 September 2015