You are on page 1of 25

Installation

NO. Name Detail Used for


Electric soldering
22. Some Soldering
iron

Knife for
23. Some
electrician Cutting wire

Each
24. Screw driver
2
L=100MM, L=150MM

if available no
SF6 gas leakage equipment leakage
25. detecting
test can be substituted
equipment
bysoapal.ds.

liming test
26.
equipment

27. Circuit tester

Each Insulation
28. Meggar 5000V, 1000V
resistance test

23
r
Installation
Iii
Table : 4.3 Consumable material supplied by CGL
Detall
NO. I ·- - Name
-,~- --- I -~---
~for
1. I Gas sealer I ANABOND 681 (Milky)
I 1
Tube I
"-.._,
Gas sear
1ng
I ,----r--.__
2. Three Bond (Red)
I Liquid gasket I
Ole 1
Bo~
1
3. I Sealing compound I ANABOND 680 (Translucent) I Tube Water Proof
1ng
4. I Joint compound I Jointal Z (Green) I Bottle
Terminal Pads
connection
.I
5. I O Ring 252 mm x 4.5 I I 3
SSS Flange
i: I, .:·
I: ·, ~-1.
:: ,1 Iii , ! * Note 1
iqj ' '
Ill Liquid gasket (Three Bond # 1101) is used for small

,II size gas pipe (6 mm dia.) connection.
:\ H
I ii Usually no connection is required, however, small
!I
., '
amount of liquid gasket is supplied just in case.
,!\ I
:'j'1i,
!'.:
Table : 4.4 Consumable material to be supplied by the purchaser
-.
NO. Name Detail Qty Used for -
11!l
1
1. Waste cloth White cloth Some Parts cleaning
-
:i)I ' '.11 I·
,, !'., 'I
.""I·
" '
i1ll1 1 1: \1
:1'
i I
::. 1··
2. Grain size Terminal pads
i' 11• Abrasive paper
I
----
I' 11 ,. .:.
No. 280, No. 400
Some connection
1[' ''
l,,J1 ,:,
\.·.·1' 1'1.:
-----
f 11' :I 3. Cleaning agent Parts cleaning
~1~ 11 i Some
1: ' ,:
'1).I[ i\11
'I i 4 Loctite
Some
.,r.1, 1 li11

,,, 1 '
',1, I
1· I Alternatively petrol or corbontetrachloride may be used.
11
24
Installation
4.5 INSTRUCTIVE INSTALLATION 4.5.2 UNPACKING
4.5.1 RECEIVING, STORING (1) Normally, unpacking should be made indoors or
near the installation. If unpacking is done outdoors,
Immediately upon the receipt of the equipments, the
the equipment should be protected from rainy
purchaser should check the material actually
weather conditions.
received against the packing list to be sure that all
parts have been received. Also an examination (2) Use a nail puller to open the crates. Do not allow
should be made for any damage sustained while the pole unit to be struck by the tool.
transportation. If damage is evident or there are
Particular care must be taken when removing the pole
visible signs of rough handling, put in a claim for
unit from their packing slots as it may be easily
damage with the carrier, and promptly notify the
chipped or damaged. Remove the poles as shown
nearest representative of CGL. All parts should be
below.
stored indoor unless the equipment is immediately
installed. If the storage period has exceeded NOTE: Packing case dimensions & material may
6 month, check the shipping assembly carefully for change as per design /environment friendly aspect
damage caused by moisture, dirt and rust. requirement.
It is mandatory to carry out through cleaning of all the mechanism assemblies & parts using cleaning agents,
blower (hot), clear cloth & the 'lubricate the mechanism assemblies parts· and check with respect to the guide
line indicated in the manual.
Procedure for unloading & unpacking
Crane hook p~sition over Aluminium flange top
Always use 4 Ton Capacity of Rope/
Belt for Lifting of Packing Case
A2) Pole Lifting - ~ 11·1,i
"""' ] t
.{ii '
1/J
Part b) procedure to dismantle poles
from packing case Bl) Open the Top Angles of Frame- 2 No with M16 Spanner
25
,;l_ j
I .L

Jill
~;l /, ,'~
',·,.·1
'!1
l '. j
I 1 :'(

Jil
!'.,

B2) Hold the Upper pole with Belt or Rope


and keep belt/rope adequately tightened

:i 11 t
B3) Loosen the lower side plate - 4 No Nuts with
M16 Spanner. Remove Plate.

B4) Loosen Middle angles-8 No Bolts with B5) Loosen Top Side Plate - 4 No Bolts with
M16 Spanner. Remove angles M16 Spanner. Remove _the plate.

>

IL ;·,
·1 f,,i:I
1'
ATTACH
M12NUTTO
THE STUD
SUPPORTH
CAUTION:
TAKECAR!e
PRESSURISED
POLE NOTTO
HIT (GAS VALVE,

. ' :; i
PIPECONNS,
&OP,RODI

1H
Enw,etoputORlng
(2521MllDll.4.5thkEP0M
1 -provlded1naccessonestiox1
• t,et,,teenSides.al!\angll
; ''\' ll•-1
f
f ':'
.1, ![ .i' :1
andTopplateolframt
lnthlgr'00\'9 pru'lided•

'"liJ'. i1 86) Keep all the poles on wooden plank first. & then get
11 _-
H support from accessories box & fix to the pole & lift the pole
'I ' :,
1

' ,10::· one by one .... Refer section 4.5.6.1


1ij 1::•tl
1' 1 \,l\lj
i·!\lliil
t11_ 1_
ii','I
:11 I
r 4.5.3 SETTING OF FOUNDATION BOLTS

-.:
1
1 :1
0 0
'I\,!" Install the foundation bolts according to the drawing

_f
Oo 00
I ]!;l
i :\'.!: o go G ·•
approved mutually.
Level out upper surface of the foundation. Give
, :Ii 0
G

. ~-
I.
•~ :1 , I
0 i, ·

,I
'. 1I l,! 1
I· I
0
()
e
0 G
• enough curing time for concrete.

I11••\•:·· o 0
0 e o 0
0 O O 0 0

i: '\)1'

l Ii
l,·1·1_·_.• 1.

:\11 '
·'1· ·1 I
1!'. (!
28

\: I' :
Installation

4.5.4 FIXING OF SUPPORTING STRUCTURE


Fit in the supporting structures / columns onto the
anchor bolts. Eye bolts will be helpful for lifting them
up. Direction of the structure must be carefully
checked. Fasten anchor nuts with spring washers
temporarily as final adjustment may come up.
CAUTION : Ensure no gap between structure &
Foundation

NUT (M24)

SPRING WASHER

4.5.5 FIXING OF FRAME


Remove the shipping covers of the frame and three seats of poles with the help of spirit leveL

protection covers as well. Fix the frame or,to the Recommended fastening torque is shown in

supporting structures. Fit and fasten eight M20 Appendix-8. After applying the fastening torque,

screws. Then fasten nuts with anchor bolts. Use shims level of pole mounting seats should be checked again.

if necessary under the support structure to level the

HEX SCREW
M20 x40 r
Fromf

27
t Installation
11111
1'
ii\ Ii
li!I ,,·_1.
Ii d 4.5.8 FIXING OF INTERRUPTING UNITS
LI h
iit1: t:\: 4.5.8.1 Matching lnclcallon of lnl9mlpllng unllB
The phase are marked on the each interrupting units
"II:
f ; :!;\
,.1,
A, B, C or R, Y, P. When viewed from front of
!L ' breaker NR is on the left. B/Y in middle and C/B
right side while mounting on the frame Match
interrupting units with match marks on housing. This
i \'·•_•
' is necessary as they are factory set.
\It1 I!;i".
I I'
1·1
!·''
\'
t
!; ~LI:.
i;, ·11,,
11 ! '
'-~· 1,[·_:,·,
!, 1,.1: ,
1·, ,i~, i• • )
1
·_. ,I "·
;:
!; , • \1\:
: I CAUTION :
TAKE CARE
:r b PRESSURISED
POLE NOTTO
ii i1r HIT (GAS VALVE,
,1 ri PIPE CONN$,
&OP,ROD)
Ensure to put O Ring
C/B (252mm ID x 4.Sthk EPDM
-provided in accessorles box)
/!JR B/Y, between Side Seal flange
I
and Top plate of frame
In the groove provided.
!'
f
!:, 1:4
1· ·-It
I 1:i ATTACH
,; j' I M12NUTTO
THE STUD
:i "j' ,!
ll1 i!1 >·I'
i1
': !1 '
f iJ,il
f,, 1i::
;1 ' 11;! 4.5.6.2 Atlach Terminal Pads
'\
1
\ii
1 11H1 Attach the terminal pads onto both upper and lower
'li!'.1
1
Joint compound must be used as instructed in
1 11:11
terminal flanges of the circuit breaker. The terminal
,' iil1 Appendix E.
,i tl:i 'i pads can be attached either side, front or rear of
1:.1·1:i'
1 il . however,
the breaker. The above can be done also after erection,
i i1ij
11 '1 !'\, the work is convenient when pole is down.
11, I
:\ 1! \1
l1i i II
1::1111 28
1:11 ,!
,,,'
. . . \'!
,......-
Installation
if
,,, STAINLESS BOLT
0
I
I
O
I <Cl')
,r
·• M12x45
STAINLESS WASHER
r
r -TERMINAL PAD
!!
Lower down the pole slowly on the appropriate place
4.5.6.3 Ult up lnterrupllng Unit
with gas connection portion at the bottom, facing to
Attach the support - H and nylon sling as shown in
rear of the breaker. Then fasten the, pole with M12
fig. Lift the interrupting unit vertically using nylon
nuts and M12x40 long screws as per the
slings. Remove the protection cover which protects
recommended fastening torque Refer APP. B.
operating rod. The interrupting unit is shipped in the
closed position. After the pole is lifted vertically up
4.5.6.4 Apply Sealing Compound
in the air, pull down the operating rod downward
Before fitting the interrupting unit, apply the sealing
i.e. to open position. Ensure to put O Ring (252mm
compound (Anabond/Silastic 680) to the fitting
ID X 4.5thk EPDM -provided in accessories box)
portion area of the frame . The sealing compound
between Side Seal Flange and Top plate of frame
is to be applied in a width of about 60 mm from the
in the groove provided as per procedure on page
inner diameter of the frame.
no.48.
--.i--.i..--APPROX60MM
- -- - - - - SEALING COMPOUND
29
Installation
i
I
,,I
\!
\\
" ,--------- -
----..._
'\
! ,1 ,.,--- ---.. ( U \
1I
i
/ n , \ r
_(ytl-~~i- -~
I
I
.
'Ej9 '\- __..., /
)
M12NUT
CRING '
CIRCLIP ' ......__ _ . . , , / / BARPIN
ir\ \
.!l I II
4.5.6.5 Connect Mechanical Linkage
Remove the bar-pin of the link first. Pull down or APPLY ON BOLT HEADS &
up, the operating rod and engage the bar pin. Fit CONNECTING SURFACE
the C-ring on the bar pin's groove as instructed in l /TTJJ:\ / SEALING COMPOUND
Appendix-C (Attachment of 'C' type retaining ring).
Then fix the interrupting unit with the frame with 6
(six) M12 nuts and -2 (two) M12x40 bolts.
Recommended fastening torque is shown in 4.5.7 CONNECTING OF GAS PIPE
Appendix - B. Degrease gas valve [E) inlet surface with toluol
damped white waste cloth.
Move / rotate the shaft of pole to align with the
links of mechanism as necessary for fixing the bar Make sure the sealing surfaces of the valve inlet
pin. and 'O' ring are free from any dust. Fit 'O' ring [P-7]
and apply three bond to the 'O' ring and connect
CAUTION : ENSURE POSITIVE ENGAGEMENT
,I\ : ,,
l', ;' '
the gas pipe to the gas valve inlet as shown below.
ii OF CIRCLIP IN THE GROOVE OF BAR PIN
(ROTATE TO CHECK) REF. DIA IN APP. C.
II
·1·,J. :
' '' !'
i,l\,11; 4.5.6.6 Apply Sealing Compound
For the outdoor use breaker, apply the sealing DILO VALVE MALE
compound (Anabond 680) all around the connecting ~ L V E (406) ,0 , RING (P 18)
.--r-::
I
i: surface of the frame and the flange. As well as the
-- /
,,J!
SEALING
bolt heads to avoid rain water ingress to a small . ,, coMPouND
I 'i,. ( )011..0 VALVE FEMALE ( '. n,REE aoND
L.
'' )
clearance surrounding the bolts above ref.
1
i,I'~II~Ii IT

Appendix F.
\
FEMALE 01LO
couPLING
--~ ,'
30
__ .,,,,,,,,..,,_,,:r:r~< •
Installation
D
*
D
.£ -__ --- _, ·--, @=VALVE (406) { (VALVE (406)
_ VALVE '0'(405)
x,
0 RING P18 _£+ GAS FEED PORT(403)
[408] · - ..., -
TEMPERATURE ~COVER(404)
COMPENSATED
GAS PRESSURE
GAS PRESSURE
GAUGE (402) u.
'\_
ADAPTER(713)
SWITCH (401)
'J..____LARGE DIA HOSE [714]
CD
I re, I :·I IE i I l
VACUUM PUMP
[712]
Note: • Depending on make, gas pressure switch & gauge may combined/separate.
FIG.9 CONNECTION OF GAS PIPE
REGULATOR HANDLE (718)
GASKET (723)
VAJ..VE 'P'(405) ~SV FEED PORT (403) VALVE OF GAS
i i! I
REGULATOR (719) CYLINDER (802)
SMALL DIA HOSE (717)
IT 1 I i i I ~l
7
'O'RlNG I
ADAPTOR 'D'(721 ADAPTOR 'D'(722) / SF6 GAS
I CYLINDER (801)
COVER(404'
BLANK CAP (803~
FIG.10
31
i~, T1-
1
' 1 ·1 1
1
,11:1 I Installation
4.5.10 CONFIRMATION OF SETTING PRESSURE OF
4.5.8 SF8 GAS FIWNG. GAS DENSITY SWITCH
(Applicable tor only saginomiya valve tor Dilo, refer Isolate pole section from gas pipe by disco
:,\ nnectu\g
ii appendix K) Toe Evacuation is to be done pole by
dilovalve
l pole to a vacuum level of 50 mm of Hg (70). Refer
Remove the blind cover of gas feed inlet.
Fig. [7]. Remove the cover A from gas teed port
[403] at the front side of mechanism housing. Open Connect a bell or circuit tester to the term·
inalsof
the gas valve [E] and [D] slightly and drive out the pressure switch.
air in the gas piping by SF6 gas in the interrupter
Slowly open the valve D and watch the pres sure
through gas teed port. After discharging the air in
when the contacts changeover as the pressure
the gas piping, attach adaptor [F] to filling port [403]
lowers. Repeat 2-3 times to check consistency.
and regulator to gas cylinder as shown in Fig [1 O].
Attach small dia hose with one end tightly to Be sure to place back the blind cover and valve
:J
regulator and the other end loosely to adaptor [D]. connection.
I :[ Open the valve on the cylinder and slowly open
l 1·: Criterion is listed in criteria section 5.4
valve on regulator, the gas will come out. Purge the
hose with gas and tighten the end on adaptor [D].
4.5.11 OPERATION TEST AND OTHER TESTS
Now open the valve [D] and valve on regulator. The
1 Perform operation tests at rated control voltage.
·, 1; 11
' I valve on regulator opens when turned clockwise.
1: 1' l>,~ i'i Confirm the closing time and opening time are
11
, , ' .iI In fact it is better to top up over & above an additional within the allowable range.
0.2kg so that any doubts about human error while
filling or gauge list count can be eliminated. 4.5.12 FINAL INSPECTION
Iii
Visually check overall appearance of the breaker.
:.I l\i '1
Fill up to the rated pressure and then close valve
If there are any abnormality. If something abnormal
,: [D]. Close valve regulator and gas cylinder.
l. i.e. the bolts are loosened or rusted part is found
t , '1,. '
! I~
' 1: Disconnect the coupling nut (female dilo valve) from on the breaker installed, those must be rectified or
I
·1:\ male housing (male dilo valve) & attach blanking
-~
I

corrected properly.
cap in its place tighten the joint carefully.
4.5.13 WEATHER SEALING
CAUTION : DURING SERVICE VH.VE [DJ MUST
Put the protection covers at the rear and bottom of
ti :f1:·1
1d ·1 ·I ALWAYS BE IN CLOSED CONDITION AND
1.' 111.' ,,, the Breaker After fixing covers apply sealant
j:, ; ii

1 :1 •
J: ' '.ll I: VH.VE [E] IN OPENED CONDITION. ANABOND 680 in the gaps & completely cover the
I,.~' 'f ,f!',., I'
1 · ture
i;:: i: ' 1;1 1: bolt head so as to prevent rain water and mois
I ,1, :, i
4.5.9 GAS LEAKAGE TEST
"'·\·• !II
i;:, I
from getting inside.
·:!I :1 \i Perform gas leakage test on each gas pipe jointed
I :! 11
:,1 1 ii :!
,II,,,
;1 ,1
'I at site.
,ii i
'\I' Use SF6 gas leakage detector or apply soapsuds.
\P:!I I
Check for bubbles for more than 30 seconds. Refer
section 6.5.3.
I, I
( Ii
1:11 1
\111,
Commissioning
SECTION 5 • COMMISSIONING
The circuit breaker operator should be knowledgeable of 'DC' power by pushing on the trip coils
both the power company's operating procedures and the amature I plunger inside the mechanism cabinet.
operations of the circuit breaker. The circuit breaker is
CAUTION : The SF6 lockout switch is by-passed
designed for operation at unattached locations, however,
during the emergency operation . Check the SF6 gas
there are recommendations for periodic observations to
pressure gauge for rated pressure before making an
assure the breaker will function reliably. Refer to "Patrolling"
emergency operation .
V inspection recommendations.
l CAUTION : Failure to follow breaker operating, installation
and maintenance instructions can result in property damage,
5.3.2 Loss of AC Power
In case the power supply of the motor is AC power
unscheduled outages, or loss of life. with the loss of 'AC' power the charged closing spring
will provide stored energy for operation. With the
5.1 MANUAL OPERATION breaker in the closed position, the charged closing
Operate the breaker manually as per procedure in spring will be capable of an O-C-O Operation. If the
section 6.6.1 and check for any abnormal rubbing . spring will provide a C-O operation. Without AC power,
the closing spring can be charged by manual
5.2 ELECTRICAL OPERATION operation using a hand jack as described in section
Electrical closing and opening operations are made 6.6.2. After manual charging of the spring normal
from the central control panel or the local control panel operation of the breaker with DC control power is
at the circuit breaker. SF6 gas pressure switch possible.
contacts will prevent the closing and will either block
or trip the breaker if the gas system pressure falls 5.4 CRITERIA TABLE FOR SITE TEST
below the lockout pressure. The controls schematic Test Item Criteria
received with the breaker should be reviewed to (1) Gas leakage :
determine what controls were ordered. The following 1 % / Year max. Shau Id be detected
items should be checked before electrically operating by soap bubble or gas
the breaker. leak detector
• Operation is in accordance with power company's (2) Gas density switch setting
procedure.
63GA Operate 6.5 /7 ± 0.3 (kg/cm 2) = PA
• SF6 gas system is at normal operating pressure.
Reset PA + (0.1 - 0.5) kg/cm 2
Gas System valves are in proper position.
145 kv 63GL Operate 6.0/6.5 ± 0.3 (kg/cm 2)
Normal pressure 7 /7.5kg/cm 2 } at 20°C Reset PB + (0.1 - 0.5) kg/cm 2
Alarm pressure 6.5/7 kg/cm 2
(3) Timing Test (at normal control voltage)
Lockout (or Auto Trip)
pressure 6/6.5 kg/cm 2 Opening less than 32ms
Gas pressure as per approved drawing. Closing less than 130ms
• Manual jack has been removed from the
mechanism and the trip and close prevention pins 5.5 INSULATION RESISTANCE
are removed. Wipe the insulators clean. Check the resistance of
main circuit using 5kV megger with circuit breaker in
• DC controls and AC auxiliary voltages are normal
open condition. The resistance should be greater than
and all control switches are closed. Ensure removal
1500 MOhm for both. Interrupter and support
of lock pins in closing & tripping mechanism assy.
porcelains. Check the insulation of aux. and control
5.3 EMERGENCY OPERATION
circuit by using 2kV breakdown tester. Refer checklist.
5.3.1 Loss of DC Power
The circuit · breaker can be opened without
33
1w 1,11 l~!Sp_ectlon and Maintenance
.1 SECTION 6 • INSPECTION AND MAINTENANCE
ii I
' I
l I 6.1 INSPECTION PROGRAM

~. i
A proper program of inspection and maintenance will
assure the reliability of the equipment. Maintain a
permanent record for each circuit breaker. The
I
inspection requirements vary depending on the length
,I
of time in service, severity and frequency of operation.
I!
!1
A recommended inspection maintenance program
;1 :1 11
has been divided into two categories identified as
11:1 :il
l ! ,\
Ii
follows.
Table 6.1 lnspecllon Program by Tlme In Service
i'i:.I :j':• I I
Inspection Frequency Description
-
,,,
Patrol- P Monthly External visual inspection of energized breaker.
Every External inspection , de-energized breaker,
Routine- R2
24 to 30 months minor adjustments, lubrication & Timing.
Internal inspection , breaker degassed, contacts
Operations as per
Operational - O inspected & commissioning tests. Recommend to be
Table 6.2
carried at under CG Supervision.
Table 6.2 - Operational Inspection (0) Based on Opera1lons
Type Operating Condition Inspection Period
:1
:, Inspection or
Small current interruptions O to 900 A
-•-• •-•-·--A ---~--
4,000 operations
------·-.~ - - · ___.......____ •--•-• .._.~,w - -
replacement of Rated load current switching 2,000 operations
I arc contacts Short circuit interruptions per phase 1O operations
I II Rated-40 KA
:,1 · ii
I ii Replacement of Approximate number of operations 5,000 operations
, ii
-
•· I (\
mechanism parts
:I i
I. Operational Inspection (0) should be done when any of the condition in Table 6.2 is met.
I!
ll
1 6.2 MAINTENANCE PRECAUTIONS ( 1) Open the circuit breaker and disconnectors at
11
i',, The electrical performance of the circuit breaker
both sides of the breaker, and apply grounds to
\:11I!i requires that the interior and insulation parts be clean the breaker terminals.
1: and dry. The interior of the breaker interrupters should (2 ) DO NOT OPERATE THE CIRCUIT BREAKER
!:1
!•1 not be exposed to inclement weather conditions. WHEN THE SF6 GAS PRESSURE IS BELOW
[i1
Whenever the interrupters are open, temporary THE LOCKOUT PRESSURE
111
II coverings should be available to prevent exposure to
dust, dirt and moisture.
(3) Open switches to breaker DC contro
·t;m
1,r ,Ir 1•.1 control.
refer to
Following are some detail of precautions which should
(4) For inspections within the interrupters, 5
:_i 1.·· 1.1'1! be observed. . . sF6ga ·
I 11 i
section (2.8) on precautions wrth arced
;i I ;1
34
Inspection and Maintenance
(5) At the time of internal inspection and / or
special care to avoid any damage. Do not reuse
inspection of the mechanism, insert close or trip O-rings.
prevention pin. Be sure to remove these pins
(12) Apply gas sealant (white colour) to the air side
upon completion of the inspection.
of the groove for O-ring and O-ring contact
(6) Do not disassemble the shaft sliding seals. surface.
(7) Cover interrupter openings with plastic sheeting (13) Tighten each bolt with proper torque.
or bags whenever active work is not being
(14) Perform gas leakage test after any seals are
performed.
opened .
(8) Use specified lubricant. Do not apply the lubricant
( 15) Compare the mechanical operation data obtained
on the insulators.
before and after the inspection to ensure orderly
(9) Thoroughly clean interior after inspection and operation of breaker.
maintenance.
(16) The moisture content of SF6 gas in the breaker
(10) Replace absorbent whenever interrupters are has to be below 300 ppm (volume).
opened. Replacement should be made
immediately before evacuation.
6.3 INSPECTION CHECK LIST
(11) Renew all the O-rings at the flanges which has The inspection check list identifies the recommended
been opened for inspection. Handle O-ring with action required for each type of inspection or
maintenance.
Table 6.3
Inspection Checklist
Type of the Inspection
System Inspection Item Action Required p R2 0
Structural Procelain contamination Clean X X
Procelain cracks, chips Replace X X
Clean with abrasive and
Terminal corrosion X X
regrease
Housing, frame and support Clean area and touch up w ith
X X
structures rusting paint or completely repaint
External hardware tightness Retorque all loose hardware X X
Grounding terminals Check tightness, retorque X X
Gas system Gas pressure Record X X X
Ambient Temperature Record X X X
Gas Value D-closed X X
Check valves positions X
Gas valve E-open X X
Check operating pressure -
Gas pressure switch X X X
reset
Leak test any disassembled
Leakage X
joints
35
Inspection and Maintenance
-"
System
Mechanism

Inspection Item
Operations counter

Action Required
Record X
P -
Type of the lnsp .
R2
X

ection
-- -;--
- 0-
Spring charge indication Check its working X
Trip and Closing coils Check by operation replace
X
X
Clean & relubricate (Refer
Lubrication below table) X X
Hardware & retaining rings Check for looseness retorque
or replace (Refer below table) X X
Shock absorber
Check for oil leakage X X
(Located in the horizontal rod ass'y)
Check setting dimensions -
Closing coil assembly X X
resetting
Trip coil assembly Check setting dimensions -
X X
resetting
Mechanism housing and base frame Check proper & effectively
door closed X
Gap between cam and roller Check setting dimensions -
X X
resetting
Door locks Check properly locked X
Interrupter Contacts Inspect for arc erosion,
X
replace as required
Nozzle Measure for erosion, X
Absorbent Replace X
Control Hardware Check for tightness X X
Housing Control wiring Termination secure X X
Availability of Rated control
Voltage and Motor voltage
during coil activation and X
motor charging and
commissioning
X X
Termination screws tight
Insulation check with 500V X X
megger (2 Meg ohm min.)
Weather seal Door gasket condition - X X
replace if aged
X
Water leaks
X
X
Shock-proof rubber of control panel X
Check for aging replace if
Thermostat X
jl
Setting
---
Heater X
Check functioning and X
.-
:1 measure resistance
i
36
l
_....---
Inspection and Maintenance
Type of the Inspection
Inspection Item Action Required p R2 0
-
system
Contact resistance of main circuit Measure resistance X X
Measure contact wipe at
Contact wipe X
mechanism
\ Operation test
Check closing and opening
times
X X
J Check charging time of
closing spring
X X
Lubrication points
Ratchet, Pawls springs, Sewell gear, Base frame/mounting frame barpins,
Grease HRA (horizontal rod assembly} in base frame/ mounting frame ,Hex shaft of
main frame, limit switch roller
Antipumping pin.closing spring guide.Trip coil moving core, closing coil &
Oil plunger, moving trip assembly, Bearing of trip latch, Close latch assembly,
tripping spring, shaft.
Tighten all hardware's with appropriate torque connected to different
Hardware tightness check assemblies & support structure & foundation bolt in GCB Refer appendix B
table 8.1
6.4 MATERIALS AND SPECIAL TOOLS 5. Multimeter
6.4.1 Palrolq Inspection 6. 100 A low resistance ohmmeter
Normally no tools or material are required since
7. Vacuum pump set (if not ordered from CGL)
objective of patrolling inspection is to maintain a
continuous "log" of breaker condition and identify any
6.4.3 Operational Inspection and Maintenance
abnormalities that may need maintenance.
All the special tools (Table 6.5) and consumable
supplied by CGL are required. In addition following
6.42 Routine lnapeclion and Maintenance
material is required.
All the spacial tools (Table 6.5) and consumable
1. Tools listed in section 6.4.2 1
supplied by CG are required.
Part Description Part# Q'ty
These tools and materials are supplied for installation 1. Mechanism grease Darina# 2
of the breaker. Microcarbon
t 2. Contact grease
3. Joint compound Jointal - Z (green)
I If they are not available, the customer is expected to
reorder. 4. Absorbent # 101 0.9 kg
5. O-ring for Gas feed #408
Tools, equipment and materials required to be
port P 18
arranged by customer.
6. O-ring for contact # 116 3
1. Hand tool set (metric wrenches and their sockets)
holder G 240
2. Filler gauges
7. Set of arcing contacts # 518, 521 3+3
3. Steel Rule
8. Nozzle # 111
4. Oscillograph timing equipment
9. Gas sealant Anabond 681
37
Inspection and Maintenance
---
Tools, equipment and material required to be supplied maintenance then they have to be evacuated b ,
by customer . .
filling the gas. This can be achieved by Using the
1) Hand tool set [metric wrenches and their sockets] vacuum pump. Set the evacuation apparatus as
follows :
2) Filler gauge
3) Mechanics scales Refer Fig .[9]. Attach adaptor M to valve port. Connect
4) SF6 gas one end of big hose to adaptor M and the other end
5) SF6 leak detector to vacuum pump. Open valves [DJ and [EJ. Start the
vacuum pump and watch the Gas Pressure Gauge
6) Leak detection fluid [soap solution]
After needles shows 76cm, run the pump for at least
7) Test timing kit
30 min . Close valve [DJ and switch off pump. Remove
8) Multimeter adaptor M- For gas filling refer section 4.5.8
9) Plastic sheets
6.5.5 Gas Leak Inspection [Refer to Fig. 11)
10)Plastic bags
All gas seal joints which have been disturbed
11))Torque wrenches for bolt size M10,M12,M16
whenever the breaker has been opened for internal
M20,M24 ReferTable B.1 .
inspection should be checked for leaks.
12)Socket,17,19, 24,30 mm
13)Abrasive-scotch brite preferred or 120 grit sand This can be done by using leak detection fluid soap
suds or SF6 gas leak measuring apparatus after the
paper
completion of gas filling .
14)Solvant cleaner Ethanol/Toluol/Thinner/Petrol/
Carbontetracloride [a] Check with test solution [Refer to Fig. 11 [al]. Daub
15)Loktite [242 blue or equivalent] test solution over the gas sealed connection. Check
for bubbles for more than 30 seconds. If no bubbles
16)1 00A DC contact resistance meter.
appear, wipe off the solution.
6.5 MAINTENANCE OF SF6 GAS SYSTEMS [bl Check with leak Detector [Refer Fig. 11 [bl]. Cover
!i
the joint to with plastic sheet and tie properly so that
6.5.1 Adding of SF6 Gas
the air can not escape. Allow the joint for minimum
Should the gas pressure fall below the rated pressure
four hours for collecting any leaked gas. Then
value shown by table 2.1, then gas has to be filled in.
Homogenize the air contained and insert the probe.
Set the filling apparatus by referring sec 4 .5.8 and fill
the gas to the rated pressure. This can be done even
6.5.6 Gas Pressure Switch Inspection (Refer to Fig. 7J
if the breaker is in live condition.
Valve is provided to isolate the temperature ·
compensated gas pressure switch [401], the gas
6.5.2 Removal of SF6 Gas nd
pressure gauge [402] and the gas piping [301] a
For internal inspection during operational inspection,
other forms of the breaker gas system.
it is necessary to remove the SF6 gas. Reference
Inspection of the gas pressure switch [401] operation
should be made to section 2.8.1 for precautions in
handling arced SF6 gas. The gas can be reclaimed can be done as follows .
by the use of a gas service trailer or SF6 gas
1) Close the valve E [406J and remove the cover A
reclaiming cart.
[404].
2) Connect electrical continuity instrument (e.g. bell
6.5.3 & 4 Evacuation and Gas Fllllng After Maintenance tacts of
or lamp] across the alarm and lockout con
If the poles have been opened any time during the
the gas pressure switch [401].
38
11111
. Inspection and Maintenance
) Release the gas from the gas piping [301] slowly
3 from prolonged exposure to excessive moisture during
through the valve D [405].
maintenance. The breaker interior should not be left
) Record pressure at which the alarm and lockout open to the environment and must be temporarily
4
switches contact makes. The required operating sealed when left for any extended period of time. If
pressure will vary with the temperature. Measure these precautions are observed and the evacuation
temperature and refer to graph Fig. B[C] for correct procedure in section 4.5.8 followed, the interior and
pressure. SF6 gas will be dry and maintained dry by the
absorbent installed in the breaker. The absorbent is
The permissible tolerance is ± 0.3 kg/cm• - g [4.3
located inside of the contact holder and should be
psig]
renewed at each internal inspection installations is
5) The switch [401] operation can be rechecked by described in appendix H.
closing the valve D [405] and opening the valve E
If there is any concern over possible excessive
[406] to refill the gas piping (301) and repeating
moisture in the gas, the gas feed port [403] may be
the steps 1) to 4) above. If operation is incorrect,
used for connection of a moisture measuring
rotate the star shaped disc to get the correct
instrument.
settings.
The SF6 moisture level should be monitored as
6) After the inspection is completed, attach the cover
Appendix I. If measurement exceeds this level,
[404] with the ring to the gas feed port [403].
rechecks should be made to assure no errors in
7) Be sure the valve D [405] is closed and the valve measuring procedure have been made. If the high
E [406] is open. moisture level persists, corrective action would be to
evacuate, replace the absorbent and dry the SF6 <;,as
6.5.7 Gas Moisture Control or use new dry gas.
It is important to protect the SF6 gas compartments
SF6GAS LEAK
MEASURING APPARATUS
(OPTIONAL)
DAUB SOLUTION ON EACH BOLT
BUBBLES
.......·.:. - ~
\
=•™~
......•....•.
...·.~..-..
~=-:
...·.~·..
SF6 GAS
.....·.:• SF6 GAS
SF6 GAS.
...:,
......
•• I I
.. .
·.·~. FLANGE
..-·...
::•.-.
GAS SEALER
'O'RING 'O" RING
DAUB SOLUTION HERE ALSO
INDICATES GAS LEAK PATH
(A) CHECK WITH LEAK TEST SOLUTION (B) CHECK WITH SF6 GAS LEAK
MEASURING APPARATUS (OPTIONAL)
FIG.U
L
39
l' ]I I I --..........a
,·~ ·)1" I
:,
Inspection and Maintenance
: -"1,
I I
I',
·1, 1.
,q
1
close prevention pin (529) must be inserted And
I '
6.5.8 Renewal of Absorbent
also be sure the trip prevention pin (528) i
I The absorbent is put into the contact holder on each inserted because the breaker is closed. s
/ l
interrupter unit. The absorbent should be replaced Ensure removal of said pins after work complition
whenever the interrupter unit is opened to inspect the With the hand jack (724 to 726) attached, turn the nut
contacts. The procedure for replacing the absorbent (726) counterclockwise with the ratchet wrench and
is described in Appendix H. The contact holder (108} socket (30mm) through the socket (727). After the
and the interrupter porcelain O-ring seal surface jack bar (724) becomes tight (approximately 0.5 turn
should be cleaned and applied with gas sealant as of the nut (726) against the bar pin in the lever B (510)
described in Appendix A. (This means that the pin A (514) is positioned to an
over-travelled position), remove the trip prevention
pin (528).
6.6 MECHANISM AND LINKAGE INSPECTION
!·[' 6.6.1 Manual Operation (Refer to Fig. 12 & 13) Refer to Fig. 5-1a; to release engagement between
\I
A hand jack is available for slow closing and opening the trip holding latch (512) and the pin A (514) of the
of the mechanism and breaker contacts. This lever B (511 ), push the trip plunger (526) on the trip
procedure provides an opportunity to check linkage coil assembly. The movements of the mechanism by
settings, contact engagements, and possible this action are as follows ;
identification of frictions areas. This procedure for 1) The plunger (526) pushes the trip trigger (513)
application of the hand jack is as follows.
2) The trip trigger (513) rotates clockwise, and
1. Open DC and AC power switches. disengages from the roller of the trip holding latch
(512).
2. Insert the close prevention pin (529) if the closing
spring (502) is charged 3) The trip holding latch (512) rotates clockwise, since
,, 3. Insert the trip prevention pin (528) if the breaker
the trip holding latch (512) blocks the counter
If, clockwise torque of the lever 8(510) by the trip
is in the closed position. Refer to Fig.13 for the
spring (501}through the lever A (510).
hand jack assembly.
4) The pin A (514) is disengaged from the trip holding
4. Remove Blank Cover (407)
latch (512). Continue the pushing until the above
5. Apply grease to the thread of the jack bar (724) movements are completed. Turn the nut (726)
6. Engage Nut (726) on to the jack bar (724) clockwise with the ratchet wrench with socket (30
11 mm) to open the breaker.
7. Position bearing (725) on to the nut (726)
At the complete open position, the jack bar (724)
8. Mount Jack Bar (724) on Bar Pin of the lever B
becomes free.
(511) through the bottom hole of Mechanism
Housing (400).
Manual Closing
9. A special Socket (727) which is operated by a CAUTION: If the closing spring (502) is charged, the
conventional Ratchet Wrench with its socket (30 close prevention pin (529) must be inserted.
mm) is provided to fit the nut (726). Turning Ensure removal of said pins after work complition
clockwise will close the breaker contacts. Turn the nut (726) counterclockwise with the ratchet
wrench until the trip trigger (513) engages the roller
Manual Opening
of the trip holding latch (512). Since this position is
CAUTION: If the closing spring (502) is charged, the
an over-travelled position, the nut (726) must be
40
_____....
Inspection and Maintenance

And FRONT VIEW OF MECHANISM


I) is

ion
ienut
, and
f>-'H'-'1 -~l
7 1tl ---- --+II Jf_~ --
i r the
Stum
(510)
to an
q
antion
CLOSING SPRING (502)

...___ _ ____, CLOSE PREVENTION ~522)_


tween
of the ' - - - - - - - CLOSING COIL (506)

,e trip " - - - - - - - - ! TRIP PREVENTION PIN (528)


srn by
- - - - - - - - TRIP COIL (507)

513) FIG . 12
turned clockwise to get the complete closed position. ratchet wheel (503) acts in charging direction only.
1, and
Af the complete closed position, the pin A (514)
g latch 6.6.3 Mechanism Lubrication
engages with the trip holding latch (512) and the jack
Lubrication of the mechanism is required during
bar (724) becomes free.
1,since routine inspections. The lubricant Darina # 2, available

ounter CAUTION: If the hand jack assembly is removed with from CGL is the only authorised grease for this

,he trip the breaker closed condition , be sure to insert the trip application. Relubrication requires removal of the old
prevention pin (528) while work of removing the Jack grease and applying fresh grease. Ref. Appendix- D.
assembly is in progress. Fig. 16 shows the points requiring lubricaiton. All
,aiding
points should be relubricated at operationa l
above
6.6.2 Manual charging of Closing Spring (Refer to Figs.
maintenance
t (726)
14 and 15)
ket (30 (1) The following items marked on Fig .16 are to be
In the event of no power supply for the motor, the
lubricated every 24-36 months.
closing spring (502) can be charged by fitting Socket
1) Bevel gears of Motor drive .
1r (724) (17mm)* Extension Bar • and Ratchet Wrench • as
shown in Appendix G to the hexagonal part of the 2) Inner surface of Spring Guide for the closing

ratchet shaft (518) as shown in Fig. 15. Turning the spring (502)

ratchet shaft (518) clockwise by the ratchet wrench• (This should be done with the closing spring (502)
ed, the
until the closing holding latch (504) of fig . 5-1 (A), charged so that access to guide surface is

,lition engages with the pin B (516) will fully charge the available. When the lubrication requires, take off
closing spring (502). the cover of the spring guide.)
ratchet
,e roller CAUTION : This manual charging tools can be used 3) Pivot pins of the trip holding latch (512)

sition is only for charging of the closing spring (502), and 4) Pin A (514)
iust be cannot be used for manual discharging of it, since the

41
j
'
J ! ' •'
•,•
1,.'
I
I
Inspection and Maintenance
\•~
\ I:
l I
1.,
:1
L
511 LEVER B
....
S 1 0 B A R P I N f i ' '\ ; \ . _•
\ i
•, 1 I
," - '? DETAIL 'X"
iiII
il 725 BEARING ~. . . , .
- \. 1:I 1
i
726 NUT
X
l.
400 MECHANISM HOUSING 7 / i I ' 724 JACK BAR
'---..,.,/ COVER
,,,.--..... BLANK ~ ,III
407 .,
'J'
_ _ _ _ _ . ,I
727 SOCKET :
RATCHET WRENCH
___.~I f 1
-- --
OPEN/
RATCHETWRENCHAND ITS SOCKET(30 MM) AE OPTIONAL
FIG. 13
I
Both these pins should be removed, cleaned and 1) At open position, measure and record SM1
lubricated. This work will require following material
CAUTION: If the closing spring (502) is charged , the
and tool.
close prevention pin (529) must be inserted .
Shaft C-ring (snap ring) 20 Qty. 2
Ensure removal of said pins after work complition
Snap ring plier 51 - 1 A Qty, 1
(2) Move the mechanism (500) with the hand jack
assembly to closed position in accordance with
6.6.4 Mechanism Adjustments
the manual closing procedure described in section
During routine maintenance travel, cam clearance
6.6.1.
and settings of the trip and closing coil assemblies
(3) At complete closed position, measure and record
should be inspected and adjusted if necessary.
SM-2, the trip prevention pin (528) should be
Mechanism Travel (Refer to Flg.17) inserted.
The mechanism travel (S.M.) is measured at the end (4) The mechanism travel (S.M) is given by following
of the rod end which is connected to the lever A(510). formula.
S.M. = SM1 - SM2
The travel is specified in Table 6.4.
42
- Inspection and Maintenance
SPRING OPRATING MECHANISM
RATCHETWRENCH* (OP- 5)
FIG.14
""'"'"'. .. l "'"'""'""'"".,
SOCKET' (.17MM. 0.7IN) (QP-1) .
=--.l. '~~'"--r-+;;--l I
MOTOR
I i + - - - - RATCHETWRENCW
'THESE ITEMS ARE OPTIONAL SEE APPENDIX- G
FIG. 15
Cam Clearance (Refer to Fig.17) gap (G) does not meet the specification, adjustment
With the mechanism (500) and breaker contacts in is made with Turnbuckle Connector between the trip
the open position and the closing spring (502) spring (501) and the lever A (510).
charged, measure the gap (G) between the cam (508)
Trip Coll Assembly (Refer to Fig. 18-(A)]
and the roller of the lever B (511).
With the mechanism in the closed position and the
CAUTION : Be sure the close prevention pin (529) is trip prevention pin (528) inserted measure the stroke
inserted during this inspection. "S.r of Moving Core (A) (525) and gap "G. T' between
the trip plunger (526) and the trip trigger (513) with a
I
The gap (G) specification is given in Table 6.4. If the
feeler gauge. The stroke "S.T'' of the moving core (A)
L 43
503RATCHET
WHEEL FRAME
CAMSHAFT 512 TRIP HOLDING LATCH
ROD 0
513TRIPTRIGGER
LATCH
NOTE:-
THE MARKO SHOWN THE PARTS
FOR WHICH THE GREASE SHOULD BE APPLIED
EVERY 24-36 months
i
OINNER SURFACE
OF SPRING GUIDE 515ANTIPUMPING LEVER
505 CLOSING TRIGGER
506 CLOSING COIL
0 BEVEL GEARS
COVER
502 CLOSING SPRING
DETAILED VIEW OF MOTOR
8(;_.__~ij $01,..10 CROSS -SECTIONAL VIEW OF TYPE BM SPRING OPERATION MECHANISM
-••4 ••·-·-•-·-·~· ----·-• -"'· _____,.. -·-·--•- - ·-------------- -------s--
~--{%;;!£:~-;:'=:;~~~-=~·-·. ~-- --- -- -~
lnsP.ectiQtLand . Maintena nce
TRIP SPRING (501)
n
::,
0
)
>
BASE FRAME TURN BUCKLE CONNECTER
(300) LEVERA(510)
TURN BUCKLE CONNECTER
TRIP SPRING
0
(501)
CLOSING SPRING
] (502)
511 LEVER B !
!
i
;
i
I
i'
I
--0
OPENING POSITION (CLOSING SPRING CHARGED)
FIG. 17
. 45
i 1· :\,; II
..
' l
! ; Inspection and Maintenance
rJf-11
i ! I
l·:. 1I
:tll I !
!ll
1
I l
I
___ ___________ [ :OR DOUBLE TRIP COIL:RRANGEMENT
i
I
/ 507 TRIP COIL i
I
: I / fl..... ! ~NUT(A)
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
STRQl<ES.T.
STATl~NARY_ /
CCjRE (A) STROKE S.T.
IL I
----.....__525 M YING
COREf<A)
,I _ _______________________________ J I
(A) TRIP COIL ASSEMBLY
,1
li
i! 519 ANTIPUMPING
I PIN
,L
11
527 STATIONARY CORE (B)
NUT(C)
506 CLOSING COIL.
STROKES.c.
(8) CLOSING COIL ASSEMBLY
FIG.18
48
A
) is detennined by measuring the gap between moving core (B) (527) and stationary Core (8). The
525
~e moving core (A) (525) and Stationary Core (A). specified dimension should meet Table 6.4. The
The specified dimensions should meet Table 5. stroke "S.C" is adjusted with loosening Nuts (B) and
Adjustrnentofthe stroke "ST is made with loosening driving Bolts (B).
Nuts (A) and driving Bolts (A). The gap "G.T" is
The Gap "G.C1" adjustment is made only when gap
adjusted by loosening Nut (B) and driving the plunger
is less than 2.0 mm (0.079 in). In this case, insert 0.5
( 26) to the correct dimension. After adjustments, the
5 mm thickness of Brass Washer (0.5-11 X22) between
nuts should be relocked. the stationary core (B) and the mechanism frame. If
the gap is over 3.0 mm (0.118 in), replace the closing
Closing Coll Assembly (Refer to Fig. 18- (B)]
coil assembly. The gap "G.C2" is adjusted with shifting
With the closing spring (502) charged and the closed
of the mounting bolts (not shown in Fig.18) of the
prevention pin (529) inserted, measure the stroke
antipumping pin assembly. The gap "GC3" is adjusted
•s.c· of Moving Core (B) (527), the gap "G.C1"
with shifting of the mounting bolts (not shown in
between the antipumping lever (515) and the closing
Fig.18) of the closing coil assembly.
trigger (505), the gap "G.C2" between the antipumping
Adjustable ranges of the gaps "G.C2" and "GC3" are
pin (519) and the antipumping lever (515) and the gap
•G.C3". The stroke "S.C." of the moving core (B) (527) maximum 1.0 mm (0.039 in) and maximum 1.25 mm
is detennined by measuring the gap between the (0.049 in) respectively.
Table 6.4 Measurement of Dimensions
Mark Standard Dimensions Referred Fig. No.
Item
S.T. 2.8-3.2 mm Fig.18 - (A)
Stroke of moving core of trip coil
Gap between plunger of trip G.T. 1.0-1.4 mm ditto
coil and trip trigger
Difference between stroke (S.T.) S.T. -G.T. 1 .6- 2.4 mm ditto
' '
'and gap (G.T.)
Fig.18-(B)
:Siroka of moving core of s.c. 4.5-5.5 mm
dosing coil
Gap between antipumping lever 2.0-3.0 mm ditto
G.C1
and closing trigger
Difference between stroke (S.C) 2.5-3.5 mm ditto
S.C.-G.C1
and gap (G.C 1)
,Gap between antipumping lever ditto
G.C2 1.0- 2.0 mm
and antipumping pin
Gap between antipumping lever ditto
G.C3 2.0-3.0 mm
closing trigger
2 Fig. 17
~ oke of spring operating · . S.M + mrri
100 -8
mechanism ' ' '
.._
ditto
:Gap between roller and cam
'•·
G 1.4 ± 0.3 mm
.,:;__ _, :
47
..l

You might also like