You are on page 1of 1

KSBH 15 KSBH 16

LIMIT OF WORKS

LIMIT OF WORKS
T00 ISSUE FOR TENDER 12/4/17

PILING TENDER DRAWING

CADANGAN PEMBANGUNAN PLOT C8 YANG


MENGANDUNGI:
LIMIT OF
WORKS a. 2 BLOK PEJABAT 12 TINGKAT

ZONE 9 b. RUANG PEJABAT YANG MENYAMBUNGKAN


2 BLOK PEJABAT DI TINGKAT 2, 3, 5, 6 DAN 10
c. KEMUDAHAN-KEMUDAHAN BANGUNAN SEPERTI :
i. MUSOLLA DI TINGKAT 1
ii. KAFETERIA DI TINGKAT 1

ZONE 6
DAN PEMBANGUNAN AKAN DATANG
(KOMERSIAL) SERTA TEMPAT LETAK KERETA
BAWAH TANAH 2 TINGKAT DAN SATU ARAS PODIUM,
DI ATAS LOT PT50853,
KWASA DAMANSARA, SEKSYEN U4,
40160 SHAH ALAM,
SELANGOR DARUL EHSAN

ZONE 3 UNTUK TETUAN KWASA UTAMA SDN BHD

KSBH 5A

KSBH 2 ZONE 10

LIMIT OF WORKS
KSBH 5 JUB SEKUTU SDN. BHD.

KSBH 6A
ZONE 5 JURUTERA PERUNDING
KUASA TENAGA SDN. BHD.

KSBH 3A KEMASEPAKAT SDN. BHD.

ZONE 2 KSBH 4AZONE 8


KSBH 2A

CMKS CONSULTANCY SDN BHD

KWASA UTAMA SDN BHD

ZONE 1 ZONE 4 ZONE 7


KSBH 3
KSBH 1 KSBH 4
RSP ARCHITECT SDN. BHD.

1. ALLOWABLE PILE CAPACITY: − 7. FOR TENDER PURPOSE, PROVISIONAL LENGTH SHALL REFER 9. TOP OF PILECAP (T.O.P) SHALL REFER TO C&S COLUMN
600mm DIA. G80 CLASS ’B’ SPUN PILE = 2600 kN
450mm DIA. G80 CLASS ’B’ SPUN PILE = 1550 kN
TO ZONING PLAN. & STUMP LAYOUT. PILE LENGTH EST. PILE ZONE 4 20m ZONE 8 45m PILING & PILECAP LAYOUT PLAN
8. THE FOLLOWING PILE TESTS SHALL BE CARRIED OUT: − 10. T.O.P OF LIFTCORE TO CONFIRM WITH M&E ENGINEER.
2. PILES SHALL BE HYDRAULICALLY JACKED TO FOLLOWING LOAD: − A. INSTRUMENTED PRELIMINARY MAINTAIN LOAD TEST (3xWL): −
ZONE LENGTH
600mm DIA. G80 CLASS ’B’ SPUN PILE = 6600 kN 600mm DIA. G80 CLASS ’B’ SPUN PILE = 2 NOS.
11. ALL CENTERLINE OF COLUMN/STUMP SHALL BE INLINE ZONE 5 30m ZONE 9 38m
WITH PILECAP CENTER. ZONE 1 13m
450mm DIA. G80 CLASS ’B’ SPUN PILE = 3300 kN 450mm DIA. G80 CLASS ’B’ SPUN PILE = 1 NOS. 12. WELDING OF JOINTS SHALL ADHERE TO SPECIFICATION
3. ACTUAL PILE PENERATION SHALL BE RECORDED DURING PILE B. MAINTAIN LOAD TEST ON WORKING PILES (2xWL): − REQUIREMENT.
ZONE 6 21m ZONE 10 25m
INSTALLATION. 600mm DIA. G80 CLASS ’B’ SPUN PILE = 4 NOS. 13. MINIMUM PILE DISTANCE SHALL BE 2.5 TIME PILE DIA. ZONE 2 23m (PRE−BORE 10m) 1:40 CWL
4. MAX. ALLOWABLE DEVIATION OF PILES SHALL NOT EXCEED 450mm DIA. G80 CLASS ’B’ SPUN PILE = 2 NOS. (PRE−BORE 6m) 22 MAR 2017 CSW
75mm. C. HIGH STRAIN DYNAMIC LOAD TESTS (PDA TESTS): − ZONE 7 40m
5. TEST PILE LOCATION SHALL BE DETERMINED BY ENGINEER.
6. PILING RECORDS SHALL BE SUBMITTED TO ENGINEER ON
WEEKLY BASIS.
600mm DIA. G80 CLASS ’B’ SPUN PILE = 50 NOS.
450mm DIA. G80 CLASS ’B’ SPUN PILE = 10 NOS.
ZONE 3 23m FOR TENDER M269 A TD
M269/KU/
GT/LP/01 T00