Brothers Trading PLC Site Office Interior Finishing Work

GYPSUM WORK, INSTALLATION, FLOORING, OPENNING, PAINT & OTHERS


LABOR COST
Description Quantity Unit Price Total Price
No INTERNAL WALL CALDDING WORKS
1 Gypsum board (china board) 125.00 m2 250.00 31,250.00
2
2 Gypsum chalk 125.00 m 45.00 5,625.00
3 Installation & fitting 19 points 265.00 5,035.00
2
4 SPC flooring 31.00 m 160.00 4,960.00
5 Skirting (Zekolo) 34.00 ml 50.00 1,700.00
2
6 Paint 125.00 m 25.00 3,125.00
2
7 MDF mulluion cladding (18mm) 1.20 m 4,500.00 5,400.00
2
8 Logo (18mm-foam board) 2 m 3,500.00 7,000.00
2
9 Aluminum openning 12.15 m 1,150.00 13,972.50
Total 78,067.50
VAT 15% 11,710.13
Grand Total 89,777.63