JADWAL PENDATANGAN MANPOWER

DECORATION - FASADE

1team/1floor/1mount

kebutuhan org / lantai untuk pekerjaan M.1 (November- M.2 (December-


No. URAIAN / lantai minimum volume pekerja / hari M.0 (October-23) M.3 (January-24) M.4 (February-24) M.5 (March-24) M.6 (April-24) M.7 (May-24) M.8 (June-24) M.9 (July-24) M.10 (August-24) M.11 (September-24) M.12 (October-24)
(10 hari) 23) 23)

1 MANPOWER DECORATION

A FLOOR FINISHES

1 Waterproofed+epoxy cement-based 18.654,00 621,80 5,00 12,00 12 12 12 12


2 Timber floor+dry cement+polishing 10.174,00 339,13 3,00 11,00 11 11 11 11 11 11 11
3 Dry cement mortar 23.261,00 775,37 5,00 16,00 16 16 16 16 16 16 16

4 Cement mortar polishing 1.612,00 53,73 5,00 1,00 1 1 1 1 1 1 1


5 FloorTile 38.230,00 1.274,33 5,00 25,00 25 25 25 25 25 25 25
6 Laminated flooring 10.174,00 339,13 2,00 17,00 17 17 17 17 17 17 17
7 Tresh Hold 142,80 4,76 0,50 1,00 1 1 1 1 1 1 1

B WALL FINISHES

1 Plastered finished 68.935,00 2.297,83 5,00 31,00 31 31 31 31 31 31


Acian 35.654,00 1.188,47 5,00 16,00 16 16 16 16 16 16
2 Wall Tile 35.654,00 1.188,47 5,00 16,00 16 16 16 16 16 16
3 Skirting 20.243,00 674,77 1,00 45,00 45 45 45 45 45 45

4 Skimcoat 45.638,00 1.521,27 2,00 51,00 51 51 51 51 51 51 51


5 Paint 21.151,00 705,03 5,00 9,00 9 9 9 9 9 9
6 etc 7.265,00 242,17 5,00 3,00 3 3 3 3 3 3 3 3 3 3 3 3

C CEILING FINISHES

1 Expose 33.983,00 1.132,77 2,00 38,00 38 38 38 38 38 38 38 38 38

2 Calsium & Gypsum Board 18.125,00 604,17 2,00 20,00 20 20 20 20 20 20 20 20 20


3 Drop Ceiling 7.592,00 253,07 2,00 8,00 8 8 8 8 8 8 8 8 8
4 Cailing Paint 51.193,00 1.706,43 2,00 57,00 57 57 57 57 57 57 57 57 57 57

D STAIRS FINISHES

1 Steel railing to staircase 585,20 19,51 1,00 1,00 1 1 1 1 1 1 1 1 1


2 Stair wall

3 Stair Ceiling
4 Stair Floor

5 Paint

2 MANPOWER FASADE

1 PLASTERWORK 738,00 24,60 5,00 1,00 1 1 1 1 1 1 1 1 1 1 1 1

2 SKIMCOAT TO CONCRETE WALL 36.456,00 1.215,20 5,00 16,00 16 16 16 16 16 16 16 16


3 EXTERNAL PAINT 37.194,00 1.239,80 2,00 41,00 41 41 41 41 41 41 41 41 41 41 41

TOTAL… 436,00 0 101 183 345 366 366 366 319 264 219 150 73 61

Jakarta, 10 September 2023


PT. AJI KONSTRUKSI UTAMA

MAHMUD
Project Manager