You are on page 1of 89

ARCHITECTURAL

SPECIFICATION

University of Melbourne
PS‐002428 New Accommodation for
Melbourne Centre for Behaviour

Project Project number: Address:

22.130 800 Swanston Street, Parkville Campus, Carlton VIC 3053

Issued Issue Date: Issued for:

06/08/2023 Tender Issue (T1)

This document is a strictly confidential communication to and solely for the use of the recipient and may not be
reproduced or circulated without Millar Architects’ prior written consent. If you are not the intended recipient, you
may not disclose or use the information in this documentation in any way.
TABLE OF CONTENTS

Table of Contents .............................................................................................................................................................. 2


SECTION 00200 SUPPLEMENTARY CONDITIONS ....................................................................................................... 3
DOCUMENT 00630 WARRANTY SCHEDULE ................................................................................................................ 5
DOCUMENT 00650 CERTIFICATES OF INSURANCE ................................................................................................... 6
DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT ....................................................................... 7
DOCUMENT 00819 Ohs & eNVIRONMENTAL REQUIREMENtS ................................................................................. 18
SECTION 01400 QUALITY ASSURANCE ..................................................................................................................... 20
SECTION 02050 DEMOLITION ...................................................................................................................................... 21
SECTION 03530 CONCRETE SCREEDS (GRANOLITHIC) .......................................................................................... 25
SECTION 05080 METAL FINISHES - SHOP-APPLIED ................................................................................................. 28
SECTION 05500 METALWORK ..................................................................................................................................... 30
SECTION 07810 FIREPROOFING ................................................................................................................................. 38
SECTION 08200 DOORS AND DOOR FRAMES ........................................................................................................... 41
SECTION 08520 METAL WINDOWS AND GLAZING .................................................................................................... 45
SECTION 08710 DOOR HARDWARE ........................................................................................................................... 50
SECTION 08800 GLASS AND GLAZING ....................................................................................................................... 52
SECTION 08815 GLASS SPLASHBACKS ..................................................................................................................... 57
SECTION 09250 PLASTERBOARD ............................................................................................................................... 59
SECTION 09260 DRY WALL PARTITIONS ................................................................................................................... 62
SECTION 09500 SUSPENDED CEILINGS / Fixed ceilings ........................................................................................... 64
SECTION 09650 RESILIENT FLOORING (VINYL) ........................................................................................................ 67
SECTION 09685 MODULAR CARPET (TILE)................................................................................................................ 69
SECTION 09720 WALLCOVERING (Paper, Fabric etc)................................................................................................. 73
SECTION 09910 PAINTING ........................................................................................................................................... 75
SECTION 10400 IDENTIFICATION SIGNS ................................................................................................................... 78
SECTION 10520 FIRE EXTINGUISHERS...................................................................................................................... 81
SECTION 12300 MANUFACTURED CASEWORK - SHOP BUILT ................................................................................ 83
SECTION 12720 COMMERCIAL FURNITURE / WORKSTATIONS .............................................................................. 86
APPENDICES .................................................................................................................................................................. 89

Page 2 of 89 TABLE OF CONTENTS


SECTION 00200 SUPPLEMENTARY CONDITIONS

1. The Project
Refurbishment and fitout of existing offices at the University of Melbourne Parkville Campus.

2. The Contract
Fixed lump sum not subject to rise and fall.

3. List of Conditions of Contract


Refer to standard University of Melbourne Contract.

4. Tender Price Schedule


Refer to standard University of Melbourne Tender documents.

5. Tender Documents
Refer to standard University of Melbourne Tender Documents.

6. Alternative Proposals
Submit tenders in accordance with the tender documents.

7. Exclusions / Assumptions
No exclusions or assumptions will be assumed or accepted unless specifically noted as part of the tender
submission.

8. Permission to Visit the Site


Refer to standard University of Melbourne Tender documents.

9. Definitions
For the purposes of this Specification the following definitions shall apply:
 Project Manager shall be the Superintendent (University of Melbourne Project Officer)
 Builder shall be the Contractor
 Proprietor shall be University of Melbourne
 Architect shall be Millar Architects

10. Works Program/ Schedule


Refer to University of Melbourne RFT for Construction Program/dates. Tenderer’s are to advise whether they
can achieve the below timelines in their tender submission and submit a Gantt chart program showing the
breakdown of each trade/task to achieve handover by the specified date.

11. Project Staging Requirements


N/A.

12. Contractor’s Security


Refer to standard University of Melbourne Contract.

13. Liquidated Damages


Refer to standard University of Melbourne Contract.

14. Building Surveying Inspection Fees


Refer to standard University of Melbourne Contract.

15. Documents to be Submitted Following Engagement


Following engagement, the successful Contractor must provide the following within 14 working days and prior
to commencement of any works on site:
 A detailed Construction Management Plan;
 Occupational Health and Safety Manual and Procedures;
 Project Program (Gantt chart) in accordance with the ‘Schedule’ requirements for delivery under the
Contract;
 A Waste Management Plan (which shall be reviewed and updated as required) for the recycling and
minimisation of waste materials generated by the project including metal, timber, paper, glass plaster,
polystyrene and concrete generated by building or project work in accordance with 0800
SUPPLEMENTARY CONDITIONS OF CONTRACT.

16. Noisy and Disruptive Works


All noisy/disruptive works must be completed outside normal working hours, including the following:
 Core holes to slabs;
 Slab cutting/trenching/chasing;

Page 3 of 89 SECTION 00200 SUPPLEMENTARY CONDITIONS


 All works involving a noisy machinery/equipment;
 Any mechanical services corridor rough-in that will disrupt adjacent tenants / users.
Tenderer’s MUST make allowance for all relevant our of hours works within their submission. Access must be
arranged with University Security staff 24 prior to commencement of any out of hours works.

17. ‘RED LIST’ / HAZARDOUS MATERIALS


The Contractor must not use any building materials that contain any of the following:
 Asbestos
 Cadmium
 Chlorinated Polyethylene and Chlorosulfonated Polyethlene43
 Chlorofluorocarbons (CFCs)
 Chloroprene (Neoprene)
 Formaldehyde (added)
 Halogenated Flame Retardants44
 Hydrochlorofluorocarbons (HCFCs)
 Lead (added)
 Mercury
 Petrochemical Fertilizers and Pesticides45
 Phthalates
 Polyvinyl Chloride (PVC)

18. Existing Amenities Use


The Contractor is permitted to use the existing amenities on each relevant building level/space during the
project. However, regular cleaning by the Contractor will be required.

19. Pre-nominated Contractors / Suppliers (Note: Contractors must submit a copy of pre-nominated
contractors quotations with their Tender submission)
 Supply and installation fo AV services – Citadel Technology.
 All furniture suppliers – refer to furniture schedule for supplier details.
 All FF/E – refer to FF/E schedule for supplier details.
 Door hardware – Lockwood.

20. Works By Others


N/A.

21. Tender Enquiries


Refer all Tender enquiries to University of Melbournes.

21. Contractor Parking


Refer to University of Melbourne Tender documents

22. Waste Management Plan


The Contractor is to provide a comprehensive waste management program to ensure that during demolition
and construction the project team must divert wasted materials from landfill into reuse or recycling to the
following levels:
Material Minimum: Diverted/Weight
Metals : 95%
Paper and Cardboard : 95%
Soil, and biomass : 100%
Rigid Foam, carpet & insulation : 90%
All others - combined weighted average : 80%
*Hazardous materials in demolition waste, such as lead-based paint, asbestos, and polychlorinated biphenyls
(PCBs), are exempt from percentage calculations.

Note: dockets of deliveries of material to recycling centres will be required

END OF DOCUMENT

Page 4 of 89 SECTION 00200 SUPPLEMENTARY CONDITIONS


DOCUMENT 00630 WARRANTY SCHEDULE

Warranty Requirements
A. The builder or other approved warrantors are to provide written warranties where so specified elsewhere in this
specification.
B. Each warranty is to be in approved form and will specifically include the provisions required in writing.
C. Warranty periods are to commence from the date of the Notice of Practical Completion.
E.

SECTION NO. SECTION NAME CLAUSE NO. Period of Time


05080 METAL FINISHES, SHOP-APPLIED 107 7 years
07810 FIREPROOFING 108 5 years
08200 DOORS AND DOOR FRAMES 107 5 years
08520 METAL WINDOWS AND GLAZING 107 9 years
08710 DOOR HARDWARE 106 5 years
08800 GLASS AND GLAZING 107 10 years
09250 PLASTERBOARD 106 5 years
09500 SUSPENDED CEILING 107 10 years
09685 MODULAR CARPET (TILE) 108 7 years
09720 WALLCOVERING 108 7 years
09910 PAINTING 108 7 years
12300 MANUFACTURED CASE WORK 107 5 years
12720 COMMERCIAL FURNITURE / 109 5 years
WORKSTATIONS
10400 IDENTIFICATION SIGNS 108 10 years
12720 WORKSTATIONS 109 8 years
15810 AIR DISTRIBUTION DUCTWORK 109 Complies with Standards
16350 ELECTRICAL INSTALLATIONS 107 10 years
16515 LOW VOLTAGE LIGHTING 107 10 years
16710 COMMUNICATION CABLING 107 10 years

END OF DOCUMENT

Page 5 of 89 DOCUMENT 00630 WARRANTY SCHEDULE


DOCUMENT 00650 CERTIFICATES OF INSURANCE

Submit each certificate to the principal via the architect before commencement of work.

A. ASBESTOS CLEARANCE CERTIFICATE

B. PUBLIC LIABILITY INSURANCE.

C. WORKER’S COMPENSATION AND EMPLOYER’S LIABILITY.

END OF DOCUMENT

Page 6 of 89 DOCUMENT 00650 CERTIFICATES OF INSURANCE


DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT

1. Information to Sub-contractors, Suppliers and Installers


Advise sub-contractors and suppliers and installers of material of the requirements of these Supplementary
Conditions of Contract.

2. Amount of Security
See DOCUMENT 00200 INFORMATION FOR TENDERERS, Annexure or Appendix to General Conditions of
Contract.

3. Interpretation of Drawings
Check dimensions on site before proceeding with the work of the contract. Notify architect of omission or
conflict in drawings and their relation to specifications.

4. Construction Progress Bar Graph (Gantt Chart)


Within 7 calendar days after the date of Letter of Acceptance of tender, submit to the Principal a detailed Gantt-
chart program of the plan of progress. For each item of work provide graph showing planned progress with
planned monthly quantities and with space or other provision for entering actual progress. The architect may
require the builder to provide an amended bar graph within 7 days of being requested to do so.
Submit Gantt-chart program (bar graph style program) at with each progress claim showing actual progress.
Program must include:
 Inclement weather allowance – N/A
 Shop drawing issue dates – minimum 10 days
 CHMP process – allow for demolition proposal approval and archaeological survey – Contractor to
nominate relevant allowance/contingency

5. Sub-contractors and Suppliers


Within 7 days of receipt of the Letter of Acceptance, supply to the architect a complete list of sub-contractors
and suppliers proposed for the works. The principal, through the architect, reserves the right to reject any so
listed.

6. Waste Management Plan


Within 14 calendar days after the date of Letter of Acceptance, submit to the architect a comprehensive waste
management program to ensure that during demolition and construction the project team must divert wasted
materials from landfill into reuse or recycling to the following levels:
Material Minimum: Diverted/Weight
Metals : 95%
Paper and Cardboard : 95%
Soil, and biomass : 100%
Rigid Foam, carpet & insulation : 90%
All others – combined weighted average : 80%

*Hazardous materials in demolition waste, such as lead-based paint, asbestos, and polychlorinated biphenyls
(PCBs), are exempt from percentage calculations.
Note: dockets of deliveries of material to recycling centres will be requested.

7. Contractor’s Responsibility
The Contractor shall be responsible for ensuring that all operations and methods of construction, materials and
workmanship are safe, sufficient, and in accordance with the Contract documents. No inspection by the
Superintendent/Architect, and no instruction given or Certificate issued by the Superintendent/Architect shall be
deemed to imply that the Superintendent/Architect has assumed or taken over any part of the Contractor’s
responsibility as defined above.

The Contractor shall be solely responsible for the execution and completion of the Contract including all sub-
contracted and nominated suppliers/sub-contractors works, which shall be coordinated so that the Works
proceed without delay. The Contractor shall ensure that, in addition to items of the Works specifically
mentioned in the relevant sections, each trade shall assist, leave holes for, cut away for, do chasing and drilling
for, make good after, and arrange each work sequence with every other trade, in such a manner as to promote
the best interests of the Works as a whole.

8. Statutory Requirements Applicable to Building Industry


The Contractor shall ensure continuity of cover for themselves and their Sub-Contractors and shall, when
called upon to do so, provide documentation to demonstrate that:

 The Statutory requirements of Work Cover, Occupational Health and Safety regulations, Payroll Tax
(where applicable) and Construction Industry Long Service Leave, PAYG Taxation, GST and
Redundancy Payment Central Fund are being met.
 The provision of Workers Superannuation schemes, where agreed between employees / unions and
employers, are being met.

Page 7 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


The Contractor shall keep records of their sub-contractors in accordance with the Victorian Building Industry
Agreement. Police checks will be required of all contractors and sub-contractors.

9. Industrial Relations
The Contractor shall work in accordance with the conditions of the appropriate State Building Industry
Agreement. Further the Contractor shall 8ecognize the following Code of Conduct and undertake to maintain a
good industrial record and to ensure that the Contractor and all Sub-Contractors engaged by the Contractor
will:

 Adhere to awards and formal industrial agreements;


 Adhere to National Wage Case Principals;
 Prohibit “all-in” or “cash-in-hand” payments;
 Ensure good safety practice in accordance with relevant legislation awards and the procedures
contained in the Building Industry Agreements;
 Refuse claims for payment for lost time due to industrial action unless exceptional circumstances exist
on genuine safety issues or fundamental breaches of contract or employment by employers in
accordance with the building industry Agreement. This remains the responsibility of the Contractor and
is not to be reimbursed for the duration of the Contract.

10. Site Allowance


The Contractor shall make due allowances, including union allowances, and include in their tender, all site
allowances applicable to this project and any associated on-costs.

11. Infrastructure Upgrade Costs


All infrastructure upgrade costs including but not limited to sewerage, water and power connections shall be
paid by the Proprietor separate from this Contract. The Contractor is responsible for all tapping fees and for
obtaining all alterations and road opening permits.

12. Materials
Unless otherwise specified, materials used throughout these Works shall be new, of good quality and be in
general conformity with the most recent Specifications and Codes of Practice laid down by the Standards
Association of Australia, where such exists or any amendments thereto. Defective materials shall be
immediately removed from the site or otherwise treated as directed by the Superintendent/Architect.
The stacking and disposal of materials and plant shall be orderly and done so as not to impose undue loadings

13. Timely Ordering


The contractor will order all products and materials in a timely manner so as to be available on site when
required and not to delay construction.

The contractor will be charged a re-design fee by the architect for alternate product selection and approval of
products that have not been ordered in time.

14. Temporary Buildings


Provide temporary accommodation – Contractor’s Office, toilets/amenities, storage sheds and other worker’s
amenities as required where approved on site. Workers’ amenities shall be provided in accordance with
appropriate regulations. Maintain temporary buildings in good and clean conditions and clear away on
completion.

15. Scaffolding
For the safe and proper execution of the work, the Contractor shall provide and erect all necessary staging and
free-standing scaffolding in compliance with the relevant State Scaffolding Regulations. Obtain all necessary
permits. Protect adjoining works and adjoining property. Any damage shall be made good at the Contractor’s
expense.

16. Existing and Temporary Services


Provide, maintain and remove at completion or when no longer required all temporary services necessary for
the Works, including those of nominated Sub-Contractors. Make separate connections to the appropriate
service mains and install all required meters, valves, piping, wiring, switchboards and similar items. Pay all
charges in connection with these installations and their use until Practical Completion.
Existing services (such as drains, watercourses, public utility and other services) if encountered, obstructed, or
damaged in the course of performing the work under the Contract, shall be dealt with as follows;

IF THE SERVICE IS TO BE CONTINUED: repair, divert, relocate as required.


IF THE SERVICE IS TO BE ABANDONED: cut and seal or disconnect.

17. Temporary Crossing and Wet Weather Access


Provide all temporary crossovers etc, as required by the Responsible Authority and as necessary to protect
existing roads, kerb, etc. Remove on completion.

Page 8 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


18. General Waterproofing and Drainage
Surplus water shall be removed from exposed portions of the site to keep the same reasonably dry. Remove
water from any holes or excavations immediately before pouring concrete.

The Contractor is to assume full responsibility for the general water tightness of the Building. The Contractor
must also promptly and without cost to the Proprietor, amend, correct, repair and/or restore any portion of the
Building which permits or has permitted the entry of water or damp or in the opinion of the
Superintendent/Architect is likely to do so.

19. Indemnity of Principal


A. Indemnify, and keep indemnified the principal against claim, demand, action, suit or proceeding that
may be brought or made against the principal by any other person who has entered into a contract with
the principal to execute work associated with the project.
B. Submit evidence of such insurance in respect of loss, damage or expense incurred by that other person
by reason of an act, default or neglect of the builder in the performance of his obligations under the
contract or arising out of or as a consequence of delay by the builder in executing or failing to complete
work under the contract and also from costs and expenses that may be incurred by that other person in
connection with such claim, demand, action, suit or proceeding.
C. Do not proceed with work under the contract until evidence of licencing, indemnities and insurances
required herein, is submitted in writing to the architect.

20. Approvals, Services, Fees and Tax


A. The following documents have been submitted by the principal, via the architect and fees paid for:
Planning permit and/or D.A.
Building Approval. Application submitted by principal but to be issued in the name of the contactor.
B. Responsibility for the approvals in ‘A’ above to be assumed by the contractor on behalf of the principal.
C. Be responsible for the identification and protection of existing services and connection /disconnection of
services, water, sewerage, drainage, electricity and gas etc. Apply for such permits, pay for fees and
charges levied by relevant bodies for such connections. Issue necessary notices to such bodies. Obtain
and pay for scaffolding permit.
D. Pay tax on items where such tax is applicable. If tax is not applicable, request from the principal, via the
architect, a tax exemption certificate for use when ordering specified materials.
E. Pay fees, where applicable, relating to workplace health and safety acts, Regulation, Code of Practice,
Australian Standards and other state or local government policy, acts regulations etc.

21. Site Control


A. Be responsible for activities on the site including providing access for authorised persons and restricting
access by unauthorised persons. Take necessary precautions to secure the assets of the principal.
B. Be responsible for providing controls to protect workers, working at height, in confined space, in
excavations and trenches, using hazardous substances/chemicals and other tasks and activities
identified by legislation or contained in the builders hazard and risk register, maintained at the project,
that may create a risk to the occupational health and safety of workers and other persons at or near the
workplace.
C. Except as otherwise provided in the contract, delivery of materials for the works, space for storage of
same and for building sheds, office and workshops will be allowed only as directed by the builder. Do
not store waste building materials and flammable liquids in the building.
D. Take proper precautions to keep hazardous chemicals/substances, poisons and other injurious
substances in places secured against access by unauthorised persons, properly labelled and not stored
in food containers or drinking vessels.
E. Confirm that the site is not in an area affected by vermin, noxious pests, eg fire ants, termites etc. Refer
to relevant authority for guidance.

22. Compliance with Ordinances, etc.


Comply throughout with the requirements of relevant sections of the Building Code of Australia.
Whenever work or type of plant or machinery, etc. is required either by the specification or by the relevant
statutory authority, provide full details of such work, plant, etc. to the relevant statutory authority and make such
applications, etc. as may be required within 2 weeks of receipt of Letter of Acceptance.
In such cases, approval given by the architect to data submitted by the builder will not necessarily imply that
such data meet the requirements of the relevant statutory authority.

23. Site Amenities and Meetings


A. Provide statutory and necessary amenities and sanitary facilities for site workers where such are not
already available in suitable locations. Maintain in working condition and clean daily. Comply with
legislative requirements.
B. Provide accommodation on the site of sufficient size to hold regular site meetings of building foreman,
architect and consultants with table and chairs, lighting, heating and packet of ‘Tim Tams’.
C. Arrange for site meetings to occur at regular intervals throughout the contract period. Advise architect
and consultants of meeting times, keep accurate records of each meeting, and issue to each attendee a
copy of the record within 3 days of each meeting. Preliminary minutes to be issued for acceptance by all
parties prior to final issue.
Page 9 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
24. Temporary Fire Extinguishers
Maintain fully charged, and accessible fire extinguishers and other plant and equipment as are necessary for
the care and safety of the works, as required by local fire authority and/or NCC.

25. Telephone and Fax


Provide a telephone service and means of graphic communication and pay costs of installation, rental, calls
and removal as required.
Provide fax machine under similar conditions.

26. Light and Power


Provide temporary electric light and power supply during construction and pay charges connected therewith to
AS 3102 Electrical installations, construction and demolition sites. Provide sufficient of each as required for
execution of work specified.
Ensure permanent power is compliant with AS/NZS 3000 Electrical installations (known as the electrical wiring
rules)

The contractor is to take a photograph and record the meter reading at site handover and provide this proof to
the Project Manager/Architect within 14 days.
The Contractor is to reimburse the owner for all power usage during the contract period.

27. Water
Provide potable drinking water and adequate signage if relevant to identify same, and maintain a temporary
water supply sufficient for executing the work under the contract. Disconnect and clear away same on
completion and pay costs and charges in connection therewith. Provide tapping of main supply if required.

The contractor is to take a photograph and record the meter reading at site handover and provide this proof to
the Project Manager/Architect within 14 days.
The Contractor is to reimburse the owner for all water usage during the contract period.

28. Project Identification Sign


Provide and fix a project identification sign in accordance with the drawing supplied by the architect and
amendment thereto and erect same on the site as directed and maintain same in good condition throughout the
currency of the contract. The sign is to remain the property of the builder. Remove same from the site on
completion of the works.

Fix architect’s sign (supplied by Architect) to site entrance. Remove same from site and return to architect on
completion of works.

29. Commencement of Work


Notwithstanding that possession of the site has been given to the builder, the builder is not permitted to
commence work on the site until he has provided:
A. Security required by the Conditions of Contract, as stated in the Annexure to the Conditions of Contract.
B. Insurances: refer Clause 6 above and DOCUMENT 00650 CERTIFICATES OF INSURANCE.
C. Verify the existence of site pegs and check that they are complete. If needed data is missing, advise
proprietor to have a licensed surveyor replace them in their correct positions. Maintain site pegs in good
condition and ensure their visibility.
D. Ensure the set out of the works is executed by a licensed land surveyor and submit documentation to
the architect.
E. Secure the site to prevent access by unauthorised persons and install signage “DANGER entry by
authorised persons only” installed on boundaries.

30. Adjacent Premises


Ensure where access to an adjacent property is required that the written approval of the owner, not the tenant,
is obtained prior to entry, and the permit as signed and witnessed, details the scope, time and arrangements to
protect owner or other persons at or near the property and that the work is carried out without damage to, and
with a minimum of nuisance or annoyance to, the occupants of adjacent premises.
Provide a thorough digital photographic record of surfaces of existing buildings adjacent to the site.

31. General Attendance on Sub-contractors


General attendance includes taking delivery, assisting to unload, storing and protecting sub-contractor’s
materials and for allowing sub-contractors ample working space, free use of water, electricity (unless otherwise
described), scaffolding, hoists and ordinary plant, etc., and messing and sanitary accommodation and for
cutting away, building in and protecting finished work and making good. Refer Document 00870 SCHEDULES
AND TABLES Part III.

32. Precautions in Carrying Out Work Under the Contract


Unless otherwise specified in the contract, observe, in the absence of statutory requirement to the contrary, the
relevant current Australian Standard published by SAI Global relating to storage, transport, use of materials,
explosives, fire precautions in arc or flame cutting flame heating and arc or gas welding operations, plant and
equipment, work processes and safety precautions.
Page 10 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT
33. Joining Up to Existing Buildings
Where the method of joining up of old and new work is not otherwise specified, the cutting away and joining up
is to be carried out in a manner approved by the architect and made good by relevant trades to match existing
adjacent work.

34. Interference with Existing Services


Prior to commencing construction work on site, the builder is to contact Dial Before You Dig or service
provider(s), or contact service owners to obtain and distribute to all relevant subcontractors and suppliers,
details of existing services and is to ensure all requirements for working on, or near any relevant service
provider service(s) are complied with, without exception during the works on the site. Notify and provide the
architect with an existing services plan, indicating the location, depth and type of connection, disconnection or
interference with existing services.
Repair, to the satisfaction of the architect, damage which occurs to services during currency of the contract.

35. Damaged Services


Where existing services at or adjacent to the site are in non-optimum condition, arrange for an inspection by
the architect and the officer-in-charge of the area responsible for such service. At such meeting, record the
condition and follow instructions when issued in writing by the architect.

36. Solid, Liquid and Gaseous Contaminants


A. Be aware of legal and other requirements for the proper storage, decanting, use and/or disposal of
solids, liquid and gaseous contaminants and
B. Be responsible for the proper disposal of solids, liquid and gaseous contaminants.
C. Discharge gaseous contaminants in such a manner that they will be sufficiently diluted with fresh air that
the toxicity will be reduced to an acceptable level.
D. Subject to statutory and local requirements, liquid contaminant may be diluted with water to a level of
quality acceptable in the sewer system or contained in approved vessels for disposal at sites approved
by the relevant authority.
E. Dispose of solid contaminants by removal from the site to locations approved by the relevant authority
and obtain certificates of disposal to demonstrate compliance.

37. Non-Rippable Material


General:
Where the methods of measurement require differentiation of non-rippable material, the following criteria
apply. Machine classification to AS 2868.

Confined excavation:
Definition: Excavation of trenches and to broader areas less than 1000 m2 in extent.

Classification:
Classify material as non-rippable if any of the nominated classes of crawler excavator fitted with a heavy duty
bucket, cannot rip at a production rate (in situ volume) exceeding the nominated values. Fit bucket teeth with
high penetration boots, approved by the machine manufacturer for use on the particular machine in rock.
 Class 55 crawler excavator fitted with a maximum 450 mm wide bucket:
Maximum production rate 1.5 m3 per hour.
 Class 85 crawler excavator fitted with a maximum 600 mm wide bucket:
Maximum production rate 3 m3 per hour.
 Class 115 crawler excavator fitted with a maximum 750 mm wide bucket:
Maximum production rate 4.5 m3 per hour.
 Class 155 crawler excavator fitted with a maximum 900 mm wide bucket:
Maximum production rate 7 m3 per hour.
 Class 200 crawler excavator fitted with a maximum 1050 mm wide bucket:
Maximum production rate 10 m3 per hour.

Other excavation:
Classification:
Classify material as non-rippable if the nominated classes of crawler tractor, equipped with a heavy duty, single
tine parallelogram ripper (approved by the machine manufacturer for use on the particular machine in rock),
cannot rip at a production rate (in situ volume) exceeding the nominated values.
 Class 150C crawler tractor: Maximum production rate of 50 m3 per hour.
 Class 200C crawler tractor: Maximum production rate of 75 m3 per hour.
 Class 300C crawler tractor: Maximum production rate of 90 m3 per hour.
 Class 400C crawler tractor: Maximum production rate of 105 m3 per hour.
 Class 500C crawler tractor: Maximum production rate of 120 m3 per hour.
 Class 600C crawler tractor: Maximum production rate of 135 m3 per hour.

Page 11 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


38. Disposal of Refuse
Remove refuse from construction operation (including food scraps and the like) from the site at frequent
intervals. Prior to removal, ensure the refuse is contained so as to prevent it being discharged in the air or onto
adjoining property.

39. Explosive Devices


Do not use free flight explosive power tool(s). Use only piston-driven tools, except as approved by the
architect.

40. Dimensioning
Do not scale drawings which are clearly diagrammatic and/or marked ‘not to scale’ or NTS.

41. Site / Level Survey


The architect has commissioned and provided a feature and level land survey for the site as part of the Tender
documents (refer appendices). All site and building levels have been setout on the based of the survey
provided. It is the Contractor’s reponsibily to confirm all site levels (to AHD) prior to setting out site and
concrete slab levels. The Contractor is required to provide an ‘as-built’ survey of all building concrete slabs
(ground and level 1) confirming that they have been constructed to the AHD levels stipulated on the
architectural drawings and by Melbourne Water. Submit the land survey in PDF / DWG format to the architect
for approval. It is the Contractor’s responsibility to ensure that all correct levels are achieved and any
deveitation (below) the levels stipulated will require the Contractor’s to undertake full rectification.

42. Shop Drawings


Shop Drawings mean complete drawings showing details of fabrication, assembly, installation, fixing and
waterproofing methods of specific items or components, including necessary explanatory notes and
specifications.
When preparing Shop Drawings, do the following:
A. Include provision in construction programme for the production and distribution of Shop Drawings.
B. Refer discrepancies discovered in the contract documents to the architect for direction.
C. Verify relevant dimensions. Dimension drawings so that the items or components fit accurately into the
required positions.
D. Ensure that Shop Drawings conform to the requirements of the contract.
E. Drawings are to be of consistent standard size and presentation.
F. Submit electronic copies of all shop drawings in PDF format. Shop drawings must be drafted in CAD
and a 3D isometric views (as required to adequately represent the full scope of works) of the shop
drawing must accompany the submission. Hand drawn shop drawing will not be accepted.
G. When the Shop Drawings are satisfactory, 1 copy will be stamped by the architect and issued by email.
Provide also as required for the builder’s site office, manufacturers or sub-contractors.
H. Acceptance of Shop Drawings are to imply only that the builder’s interpretations of the relevant
requirements of the contract are generally correct, but are to in no way relieve the builder of his
obligations under the contract to construct and complete the works correctly and accurately.
I. Do not order, manufacture, assemble or supply any item or component needed according to
requirements of Shop Drawings until the architect returns the applicable stamped drawings.
J. The builder is to provide as-built drawings and details of all installed in-ground services, including type,
location and depth, referenced against known data or reference points so as to prevent unintended
contractor damage during future excavation works.

43. Care of the Works


A. Delivery, handling and storage: deliver, handle and store products in accordance with manufacturer’s
recommendations and by methods and means which will prevent damage, deterioration, and loss
including theft. Control delivery schedules to minimise long-term storage of products at site and over-
crowding of construction spaces. In particular, co-ordinate delivery and/or installation to ensure
minimum holding or storage times for products recognised to be flammable, hazardous, easily
damaged, or sensitive to deterioration, theft and other sources of loss.
B. Limiting exposure of work: to the extent possible, through control and protection methods, supervise
performance of work in a manner which will ensure that none of the work, whether completed or in
progress, will be subjected to harmful, dangerous, or damaging exposures during construction period.
C. Cleaning and protection of finished work. General: during handling and installation of work as project
proceeds, clean site and protect work in progress and adjoining work on a basis of perpetual
maintenance. Apply suitable protective covering on newly installed work where required to ensure
freedom from damage or deterioration at a time of Practical Completion; otherwise, clean and perform
maintenance on newly installed work as frequently as necessary throughout remainder of construction
period. Adjust and lubricate operable components to ensure equipment operates as intended.

44. General Product Compliance


A. Provide products which comply with requirements, and which are undamaged and unused at time of
installation, and which are complete with accessories, trim, finish, features required by regulation, and
other devices and details needed for a complete installation and for intended use and effect.
B. Standard products: where available, provide standard products of types which have been produced and
used previously and successfully on other projects and in similar applications.

Page 12 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


C. Continued availability: where additional amounts of a product, by its application, are likely to be needed
by principal at a later date for maintenance and repair or replacement work, provide a standard,
domestically produced product which is likely to be available to principal at such later date.
D. Manufacturer’s recommendations: where installations include manufactured products, comply with
manufacturer’s current and applicable recommendations for installation, to whatever extent these are
more explicit or more stringent than applicable requirements indicated in contract documents.
At completion of project, provide to the architect a copy of each set of manufacturer’s recommendations
which have been used in the work of each trade.
E. Manufacturer’s data sheets: where this specification requires, obtain 2 copies of the current data sheets
issued by the manufacturer of specified component. Retain 1 copy for use on site and submit the other
to the architect as a record of instructions followed on the site.

45. Builder’s Quality Control


Compliance with Australian Quality Standards: in clause 104 of most trade sections, there may be reference to
compliance with Australian Standards for Quality Systems.
A. Inspect each item of materials or equipment immediately prior to installation and reject damaged or
defective items.
B. Provide attachment and connection devices and methods for securing materials properly as they are
installed, true to line and level, and within recognised industry tolerances unless otherwise indicated.
Allow for expansion and building movements. Provide uniform joint widths in exposed work, organised
for best possible visual effect. Refer questionable visual effect choices to the architect.
C. Re-check measurements and dimensions of the work as an integral step before starting each
installation.
D. Install work during conditions of temperature, humidity, exposure and weather which will ensure the best
possible results for each part of the work, or component or treatment as necessary to prevent damage
and deterioration.
E. Co-ordinate enclosure and closing-in of work with required inspections and tests, so as to avoid
necessity of uncovering work for that purpose.

46. Occupational (Workplace) Health and Safety


Be responsible for the maintenance of a satisfactory safety system on site. Ensure Risk Assessments are
made and amended as conditions change and prepare appropriate Risk Management Statements that fully
comply with relevant workplace regulations. Provide evidence to the architect of full compliance with the
provisions of the relevant state health and safety act, and that all relevant documents are approved by
Workcare representatives. It is the responsibility of the contractor and sub-contractors to use the safety
equipment and procedures as required by law.
Refer 00819 OHS & ENVIRONMENTAL REQUIREMENTS.

47. Material/Colour Selections


A. The architect will prepare a master Colour Schedule indicating the required colour, finish, pattern,
material, texture and other pertinent information in connection with interior and exterior finishes.
B. Submit colour chips for items having colour unless otherwise directed or approved by architect.
C. To facilitate the preparation of such a schedule, submit within 15 days following date of award of
contract, unless otherwise extended by the architect, the names and products of those manufacturers
whose products are proposed for use within the framework of the specifications wherever colour, finish,
pattern, texture and other related information is a consideration.

48. Miscellaneous Completion Procedures


A. Removal of protection: except as otherwise indicated or requested by architect, remove temporary
protection devices and facilities installed during course of the work to protect previously-completed work.
Where secured to exposed-to-view new work or existing to remain, remove evidence of protection
devices. Remove protection within 5 days before Practical Completion.
B. Trade cleaning: as each trade completes its work in each area of the building, the sub-contractor is
required to be responsible for “broom clean” standard of cleaning in that area.

49. Making Good


Make good damage done to the Works, or defects which appear during its progress whatever the cause,
including the replacement of items which are not and cannot be made good in accordance with the
Specification.

50. Rectification of Defects


The Defects Liability Period is taken from the time when the Works are deemed by the
Superintendent/Architect to have reached Practical Completion. Defects reported during the Defects Liability
Period shall be rectified progressively and not allowed to accumulate. Defects which affect safety or health or
which seriously interfere with the essential functions of the building shall be rectified immediately once they are
reported, other defects within a reasonable period thereafter.
The Defects Liability Period is not intended to cover any damages caused by users in their occupation other
than those spelt out in the Contract Conditions.

51. Building Handbook

Page 13 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


At the time of Practical Completion the Contractor shall provide or obtain and submit to the
Superintendent/Architect three copies of comprehensive Services and Maintenance Manual for structure and
services, bound in hard covers labeled with the project name, address and titled ‘Building Handbook’ and
incorporating, inter alia, the following sections and information:-

 Section A: Scope and Index.


 Section B: Introduction and General Systems Description.
- Description of the function and composition of each system.
- Name, address and telephone numbers of all Sub-Contractors employed on the works,
identified with each trade or services carried out nominating the name of the responsible
person in each case for normal and emergency service. If carried out by the Contractor state
‘own staff’.
 Section C: Descriptions of Operations.
- Operation of all automatic control systems.
- Correct method of operating all manually controlled items of plant for all specified modes of
operation, including start-up, shutdown and emergency procedures.
 Section D: Training Material
- Training Material must contain training material covering operations, administration and
configuration, set-up training notes and handouts.
- Complete operating instructions with detailed procedures for starting, running and shut down
of all plant and equipment systems, heater panels and HWS etc.

 Section E: Tender specifications.


- Tender Specifications must contain a copy of the tender specifications, schedules and
drawings including complete tender drawings. All drawings are to be A3 size mounted in
plastic envelopes.
 Section F: Maintenance Instructions and Schedules.
- All procedures necessary to undertake the preventive and corrective maintenance of all items
of plant, materials, finishes installed. These procedures must incorporate exploded diagrams
of the components of each plant item where appropriate.
- Details of water treatment (where provided), plant inspection and cleaning of plant items,
including relevant schedules.
- The maintenance procedures must:
 Be based on the manufacturer’s recommendations.
 Provide a minimum frequency of 12 per annum, one of which will be a prescribed for
an annual inspection.
 Section G: Schedule of Installed Equipment and Equipment Suppliers.
- All items of equipment installed.
- The original purchase order and/or invoice number of each component that has a
manufacturer’s warranty.
- The equipment suppliers and/or agents.
- Signed copies of all guarantees required to be provided under the trade sections of the
Specification and all guarantees issued with equipment supplied and installed as part of this
Contract.
 Section H: Manufacturer’s Literature (including software and hardware details, general
descriptions, operating instructions, etc.)
- Original copies only of literature for all equipment supplied as part of the contract.
- Performance charts must be provided for the specific equipment supplied.
- Software and hardware details, general descriptions, operating instructions, etc.
 Section I: Schedule of Spare Parts and/or Special Tools (assets and spare parts register).
- List all spare parts to be supplied.
- Describe the use of all special tools to be provided.
 Section J: Commissioning and Test Results.
- Certificates of compliance.
- Certification of achievement of required performance where required for compliance with
NCC.
- Commissioning and capacity test results (including commissioning for energy efficiency).
- Factory test data results.
- Air and/or water balance results.
- Schedules of control set points and settings for all physical (valves, dampers etc.) and
electronic settings.
- Calculations verifying achievement of the specified performance specifications.
- Copies of test and inspection certificates as issued by statutory authorities, including the
Certificate of Occupancy, Glazing Certificate, Plumbing Certificate, Termite Certificate,
Insulation Certificate, Certificate of Electrical Safety, Fire Seal Statement.
 Section K: As Built Drawings.
- All as built drawings and schedules as described in “As-built Documentation” bound into the
back of each copy of the Building Handbook.
- Complete electronic set of drawings in AutoCAD and PDF format on permanent media (CD
or similar).

Page 14 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


The Contractor shall submit drafts of the text for agreement prior to final printing. Should the Contractor fail to
comply with this Clause the Superintendent/Architect may arrange for the production of the handbook by others
and costs of this work will be deducted from the Contract amounts due to the Contractor.

52. As-built Documentation


Records
The Contractor must keep, and require all subcontractors to keep, accurate as-built records progressively
during construction. The Contractor must keep an on-site copy of as-built records for inspection by the
Superintendent without notice. Records must include sizes, locations and depths of all concealed base-
structure elements, components built-in to base-structure elements, services and penetrations. The Contractor
must keep original as-built records protected from damage or loss, and must not use original as-built records
for construction purposes.

As-built documentation
Where required in the Specification, the Contractor must submit to the Superintendent comprehensive, detailed
as-built documentation before the Date of Practical Completion. As-built documentation must include positions
of concealed work, penetrations, services, ducting and associated equipment, access and inspection points,
valves, controls and the like which may require later access. The exact position and route of underground
piping as actually laid must be located, by dimensions from boundaries, buildings and other fixed points.

As-built documentation must include accurate measurements and directions from permanent visible items to
locate concealed items. As-built documentation must be suitable for use by the Principal for long term
operations and maintenance. As-built documentation must include:
 Relevant documents from the Contract or shop drawings certified as as-built documentation where no
differences occur.
 Relevant modified documents from the Contract or shop drawings where work which differs from the
Contract and approved shop drawings.
 Additional drawings as required.
 The position of valves, branches, inspection openings and the like, dimensioned and checked by the
builder before the work is covered up.
 Record on the drawings the invert levels of drains and other relevant piped services.
 Variations in position of size of the pipes, valves and the like within the building.
 Photographs of concealed work that may require maintenance.

As-built coordination drawings


The Contractor must submit to the Superintendent consolidated as-built coordination drawings including three
hard copies and one electronic copy (pdf files and AutoCAD DWG files of all drawings on compact disc) of all
services, penetrations, equipment, and embedment’s before the Date of Practical Completion. The Contractor
may request from the Superintendent and use copies of the relevant base structure Drawings, for marking up
and overlaying the as-built information.

Final survey
The Contractor must submit to the Superintendent the Contractor’s licensed surveyor’s certification of the final
set-out and position of the Works.

53. Final Cleaning


Final cleaning: provide final cleaning of the work of this specification, at time indicated, consisting of cleaning
each surface of unit of work to normal ‘clean’ condition expected for a first class building cleaning and
maintenance programme.

Examples of required cleaning are:


A. Remove labels which are not required as permanent labels.
B. Clean transparent materials, including mirrors and window/door glass, to a polished condition, removing
substances which are noticeable as vision-obscuring materials. Replace broken glass and damaged
transparent materials.
C. Clean exposed exterior and interior hard surfaces finished, to a dirt free condition, free of dust, stains,
finger marks, films and similar noticeable distracting substances. Except as otherwise indicated, avoid
disturbance of natural weathering of exterior surfaces. Restore reflective surfaces to original reflective
condition.
D. Wipe clean surface of mechanical and electrical equipment, including lift and similar equipment; remove
excess lubrication and other substances.
E. Remove debris and surface dust from limited access spaces.
F. Clean concrete floors broom clean.
G. Vacuum clean carpet and similar soft surfaces.
H. Clean plumbing fixtures to a sanitary and polished condition, free of stains including those resulting from
water exposure.
I. Clean light fixtures and lamps so as to function with full efficiency.
J. If permanent lighting fixtures have been used for construction purposes replace globes with new.

Page 15 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


K. Clean project site, including planted sections and footpaths, of litter and foreign substances. Sweep
paved areas to a broom clean condition; remove stains, petro-chemical spills and other foreign deposits.
L. Label keys for locks accurately and provide in duplicate to the architect at the completion of the project.
M. If existing amenities have been utilised in any way, clean plumbing fixtures to a sanitary and polished
condition, mop and clean floors, wipe walls clean of dirt and finger marks and refill all consumables.

54. Clean Site and Access Roads


Be responsible for ensuring environmental requirements, policies and standards are maintained at all times,
including maintaining clean roads and access. Remove and clean away mud, building debris from footpaths,
gutters, drains, walls etc. when such occurs.

55. Warranties
Provide written warranties as set out in DOCUMENT 00630 WARRANTIES.

56. Authority Approvals and Certificates


A. Prior to the issue of Practical Completion Notice for the whole or section of the work, lodge with the
architect relevant certificates issued by local authorities.
B. Produce to the architect a certificate of clearance of reinstatement of damage to footpaths and road, etc.
from the appropriate road authority or city engineer before issue of Practical Completion Notice.

57. Contract Stamp Duty


If contract is liable to stamp duty, the builder is to provide to the architect at time of signing the contract, duty
stamps to the value required by the state in which the project is being constructed, together with 1 new copy of
the printed Conditions of Contract being used in this project.

58. Asbestos
No asbestos products or asbestos based materials are to be used in any part or parts of this building or its
services and the builder is to ensure that sub-contractors, nominated sub-contractors, suppliers and others are
advised of this restriction.

59. Patent Rights


Ensure that no patent is infringed and that unless otherwise specified, amounts payable and conditions
imposed in respect of the manufacture, use or exercise of patented invention are paid and complied with and
will indemnify the principal against claims, damages, costs, charges and expenses in any way whatsoever
arising out of the manufacture, use or exercise by the builder of patented invention.

60. Payment of Workers and Sub-contractors


Before the principal makes each payment to the contractor, the architect may, not less than 5 days before a
payment certificate is due, in writing request the contractor:
A. To give the architect a statutory declaration by the contractor or, where the contractor is a corporation,
by a representative of the contractor who is in a position to know the facts declared, that all workers who
have at any time been employed by the contractor on work under the contract have at the date of the
request been paid all moneys due and payable to them in respect of their employment on the work
under the contract; and:
B. To provide documentary evidence to the architect that at the date of the request all workers who have
been employed by a sub-contractor of the contractor have been paid all moneys due and payable to
them in respect of their employment on the work under the contract.
C. Not earlier than 14 days after the contractor has made each claim for payment, and before the principal
makes that payment to the contractor, the contractor is to give to the architect a statutory declaration by
the contractor or, where the contractor is a corporation, by a representative of the contractor who is in a
position to know the facts declared, that all sub-contractors have been paid all moneys due and payable
to them in respect of work under the contract.
D. If the contractor fails:
Within 5 days after a request by the architect to provide the statutory declaration, or the documentary
evidence (as the case may be) required, or fails:
To comply with these requirements, payment of moneys to the contractor may be withheld by the
principal until the statutory declaration or the documentary evidence (as the case may be) is received by
the architect.
If the contractor provides to the architect satisfactory proof of the maximum amount due and payable to
workers and sub-contractors by the contractor, the principal is not entitled to withhold any amount in
excess of the maximum amount. At the written request of the contractor, from and out of, moneys
payable to the contractor, the principal may on behalf of the contractor make payments directly to any
worker or sub-contractor. If any worker or sub-contractor obtains a court order in respect of moneys
referred to in clause B or C above and produces to the principal the court order and a statutory
declaration that it remains unpaid, the principal may pay the amount of the order, and costs included in
the order, to the worker or sub-contractor and the amount paid is to be a debt due from the contractor to
the principal. After the making of a sequestration order or a winding up order in respect of the contractor,
the principal is not to make any payment to a worker or sub-contractor without the concurrence of the
official receiver or trustee of the bankrupt or the liquidator as the case may be.

Page 16 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


61. Disability Access
Contractor is to ensure compliance with requirements of AS 1428.1 2009 General requirements for access –
New building work.

62. Tree Preservation


Clearly mark and protect all trees and vegetation identified on the site plan.

END OF DOCUMENT

Page 17 of 89 DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT


DOCUMENT 00819 OHS & ENVIRONMENTAL REQUIREMENTS

1. Compliance
The contractor is to prepare an Occupational Health, Safety and Environmental Management Plan for the
works that complies, as a minimum, with statutory and other legal requirements of the locality the works are to
be undertaken in, including all licensing, permits, fees, charges, etc. relevant to the works they will undertake
and

The contractor is to develop a “Hazard and Risk Register” for the construction phase of the project and:
 Include all hazards/risks they have identified as possible, during the conduct of the construction
phase, and
 Rate each hazard/risk level. Where the risk is greater than a first aid injury or minor illness…
 Identify and include specific controls to reduce the risk so the consequence is minor injury or illness
and …
 Re-assess the risk after the introduction of the control so as to ensure the selected control will be
effective in preventing identified injury or illness in the relevant hazard/risk identified and…
 Identify and document how the hazards and risks, as identified, will be monitored and reviewed, and
the frequency of such monitoring and review, during the conduct of the works on the project

The contractor is to include, where applicable the following hazard categories and associated risks as a
minimum in the “Hazard and Risk Register”:
 Working at height and at same level.
 Working in excavations and trenches.
 Working on or near essential services, including electricity, gas, telecommunications, water, sewer
etc.
 Delivery, storage, decanting, use and disposal of a hazardous chemical/substance.
 Delivery, unloading/loading, servicing, maintenance use and repair of plant.
 Using a confined space.
 Activities generating excessive noise, manual and materials handling risks.
 Asbestos and demolition works.
 Other categories of hazards, as included in the relevant Occupational Health, Safety and
Environmental Act, Regulation, Policy, Code of Practice, Australian Standard etc.

The contractor is to prepare “Safe Work Method Statements (SWMS)”, or equivalent, so as to control identified
hazards and risks documented in the “Hazard and Risk Register”, in consultation with workers, or providing
training to workers, in the way they will undertake the work, so as to prevent injury or illness during the conduct
of the works. Controls will include the requirements of any Regulation, or where no regulation exists, controls to
be equal to or better than a Code of Practice, Australian Standard, Ministerial Notice, statutory or industry alert,
relevant to the identified hazard and risk,

The contractor shall provide supervision, training and instruction, as relevant, to all affected workers on the
project, so as to ensure that during the conduct of the works the potential for injury or illness, as identified in the
“Hazard and Risk Register”, and documented in “Safe Work Method Statement” is minimised to an acceptable
level.

The contractor is to, at the completion of the project, provide a copy of all identified and unresolved hazards
and risks that remain to be controlled by the end user or end user servicing, maintenance or repair personnel,
so that they are not put at risk by the completed project.

2. Formal Occupational Health, Safety and Environmental Management Systems and Procedures
The contractor is to provide evidence of certification of occupational health, safety and environmental to a
minimum of AS/NZS 4801 Occupational Health and Safety Management Systems and AS/NZS ISO 14000
Environmental Management Systems.

3. Evidence
Provide evidence with tender of means by which the above item 1, is to be implemented and evidence of the
business accreditation to AS/NZS 4801 Occupational Health and Safety Management Systems and AS/NZS
ISO 14000 Environmental management systems as per item 2.

4. Submissions
Develop and submit, prior to commencing work on the project, a copy of the contractors:
 Occupational Health Safety and Environmental Management plan, and
 Hazard and Risk Register, and
 Safe Work Method Statement, and

The contractor is to document, and make available as necessary:


 The intended training, supervision, induction and inspection processes and procedures to be undertaken
on the project and …

Page 18 of 89 DOCUMENT 00819 OHS & ENVIRONMENTAL REQUIREMENTS


 The notification of all Incidents occurring at the project, including reporting, investigation, findings and
corrective actions and …
 Any occupational health, safety and environmental visitation, prosecution or consultation, including any
recommendations or finding provided by external parties to the project.

5. Hazardous Materials
The Contractor must not use any building materials that contain any of the following:
 Asbestos
 Cadmium
 Chlorinated Polyethylene and Chlorosulfonated Polyethlene
 Chlorofluorocarbons (CFCs)
 Chloroprene (Neoprene)
 Formaldehyde (added)
 Halogenated Flame Retardants
 Hydrochlorofluorocarbons (HCFCs)
 Lead (added)
 Mercury
 Petrochemical Fertilizers and Pesticides
 Phthalates
 Polyvinyl Chloride (PVC)
 Wood treatments containing Creosote, Arsenic or Pentachlorophenol

END OF DOCUMENT

Page 19 of 89 DOCUMENT 00819 OHS & ENVIRONMENTAL REQUIREMENTS


SECTION 01400 QUALITY ASSURANCE

PART ONE – COMPLIANCE WITH QUALITY STANDARDS


Comply with the following Australian Standards:
AS/NZS ISO 9001 2008 Quality management systems – Requirements.

Provide, implement and maintain a quality assurance system to:


AS/NZS ISO 9001 2008

This system includes at a minimum the following elements:


Submission at time of tender of a copy of the firm’s general quality management system including quality
manual, technical procedures, sample forms used in the quality management system and quality checklists if
used. If the firm has had a third party certification audit prepared by a registered lead assessor within the last 2
years, a copy of such audit will be accepted in lieu of the required submission.
A. Submission within 15 (or 30) days of award of contract, a project-specific quality plan to AS/NZS ISO
9001, which describes specific quality management procedures for all sub-contracts where the sub-
contract amount is 5 percent or more of the contract sum. This project quality plan describes in detail
the quality reporting and quality records procedures to be implemented on the project.
B. Submission within 15 (or 30) days of award of contract, a project-specific plan prepared by each sub-
contractor whose sub-contract work includes a design component and where the trade section
specification requires quality assurance to AS/NZS ISO 9001 2008.

PART TWO - TRADE SECTION REFERENCES

103 Quality Assurance


Provide, implement and maintain a quality assurance system to AS/NZS ISO 9001. This system includes at a
minimum the following elements:
Submission at time of tender of a copy of the firm’s general quality management system including quality
manual, technical procedures, sample forms used in the quality management system and quality checklists if
used. If the firm has had a third party certification audit prepared by a registered lead assessor within the last 2
years, a copy of such audit will be accepted in lieu of the required submission.
Submission within 15 days of award of contract, a project-specific quality plan.

103 Quality Assurance


Submit evidence of the firm’s quality assurance system.

END OF SECTION

Page 20 of 89 SECTION 01400 QUALITY ASSURANCE


SECTION 02050 DEMOLITION

PART I GENERAL100

101 General
Comply with Statutory requirements for demolishing work, supervisors, workers and to the approval of the
Principal Certifying Authority.
Provide all temporary works on site such as structural, sediment controls and dewatering. Protect adjacent
properties.
Demolish all sections of the built environment including services as shown in the specification and described
within the architectural and services engineers documentation.
Provide work as follows:

A. Scope
The work of this section includes but is not limited to the following items:
Provide and manage all demolition works including:
Identification of existing services including type of service, depth of service and location of service, co-
ordinate required termination, alteration or protection of services as per service provider requirements,
detail same on a site plan and provide a copy to the architect and other trades or activities undertaking
work at the project. Note that all work is to be in “as found” condition.
Ensure all underground and overhead services that could be affected by the demolition works are made
safe and or terminated in compliance with service owner. Include all relevant service provider
requirements in documentation and control processes and procedures.
Investigate site conditions and provide all temporary site works prior to commencing demolition
Examine documents: examine parts of the drawings and this specification for requirements which affect
the work of this section. In particular, take note of related work. Where Hazardous Materials Report and
the Geotechnical Report are enclosed, these are provided for general information only and the builder is
to evaluate site conditions and remove all material in as found condition.
B. Examine documents: examine parts of the drawings and this specification for requirements which affect
the work of this section. In particular, take note of related work.
C. Ensure only competent and approved persons, working under compliant business licence for the class
of demolition, are employed and perform in accordance with statutory requirements.
D. Provide copies of all relevant documents,eg. Asbestos clearance certificate, Dilapidation report, burial of
waste and other certifications, in accordance with requirements by statutory bodies having jurisdiction.
E. Cleaning the site thoroughly on completion.

102 Related Work


Co-ordinate with other trades affecting or affected by work of this section, co-operating as necessary to ensure
steady and satisfactory progress of the work.
Disconnection of existing services by appropriate other trades
Site preparation – Excavation Asbestos removal
Water distribution Sanitary sewerage
Storm drainage Structural and civil engineer’s documentation
Services engineer’s documentation

103 Quality Assurance


Relevant business licence for demolition work.
Provide data indicating a minimum of 3 years of experience in such work as required by this specification.
Supply names of contacts, with telephone numbers, who can verify performance quality.

104 References
Comply with applicable portions of the following Australian Standards:
AS 2187 Explosives - Storage, transport and use.
2187.2 2006 Use of explosives. There are 4 other parts, 1998 – 2006.
AS 2436 2010 Guide to noise and vibration control on construction, demolition and maintenance
sites.
AS 2550.1 2011 Cranes, hoists and winches – Safe use - General requirements
AS 2601 2001 Demolition of structures.
AS 4687 2007 Temporary fencing and hoardings.
AS 4970 2009 Protection of trees on development sites.
Comply also with the requirements of applicable building regulations, environmental requirements, statutory
and local authority having jurisdiction, including local council.

105 Public and Property Protection


Obtain heritage, local or environmental approval to demolish where applicable.
Provide measures required by municipal and state ordinances, laws and regulations, Codes of Practice,
Australian and other relevant standards so as to ensure for the protection of surrounding property, footpaths,
streets, kerbs, the public, occupants and workmen during demolition operations. Comply with the above

Page 21 of 89 SECTION 02050 DEMOLITION


ordinances, laws etc. in carrying out measures including hoardings, barricades, fences, warning lights and
signs, rubbish chutes, etc.
No blasting for demolition purposes will be permitted.
Exercise due care in executing this work.
Make good to original condition, damage to structures to be retained and to adjacent property which results
from demolition operations.
Perform restoration work without expense to the proprietor.

106 Fees and Approvals


Pay all fees due to statutory, local or other relevant authority requiring same in connection with the work of this
section. Obtain all approvals as required for the proposed work.

107 Services
Before demolishing and removing parts of building having essential services installed, ie.electrical or other
wiring, gas and water pipes, tanks, conduits or similar items embedded in them, notify the architect, owners of
services, authorities having jurisdiction, and make sure that these items are out of service so that they can be
removed without danger. Dial before you dig where required. Divert services and provide temporary services to
the work to the approval of the supply authority.

108 Photographic Record


Provide a professional quality photographic record of the progress of demolition in accordance with the
proprietor’s requirements, showing "before and after" demolition of typical work involved in demolition.

109 Tree Preservation


Where applicable, clearly mark and protect all trees and vegetation identified on the site plan during demolition.
Comply with conditions of approval as applicable to this item.

110 Pest Management


Where applicable, produce Pest Management Plan, eg fire ants in Queensland.Refer SECTION 10290 PEST
CONTROL.

PART II MATERIALS200

201 Demolished Materials


Material required to be demolished becomes the property of the contractor. Remove it from the site.
Exceptions to this clause are as follows:

202 Equipment
A. Supply equipment required to perform the work of sufficient capacity to meet the time schedule.
B. Provide suitable, approved, if relevant, disposal containers that prevent a spill to the environment for
disposal required.
C. No containers may be located on public streets or pavements without obtaining required municipal
permits for same. Co-operate with sub-contractors doing work in or near container locations to prevent
disruption of their work.

PART III EXECUTION300

301 Examine The Site Conditions


Examine the site conditions and provide all temporary works to suit site requirements.
Note that all associated reports are submitted for information only. Builder is to evaluate all site conditions and
remove all materials and components in as found condition.Refer specifically to the council conditions of
approval. Start of work means total acceptance of conditions. For all structural issues refer queries to structural
engineer.
Provide all dewatering and sediment control measures as required for site conditions.

302 Existing Reinforced Concrete


Neatly cut back or trim to new alignment with a clean true face on material to be retained. Cut with diamond
saw where necessary. Refer to structural engineer’s documentation for reference and seek structural
engineer’s advice if required.

303 Shoring
Provide necessary shoring in accordance with structural engineering instructions.
Alter, adapt, and maintain temporary works as necessary, and strike or withdraw them progressively as the
work proceeds. Obtain the written consent of the architect/structural engineer if such works are to be left in
position at the completion of the work.

304 Exposed Excavations


Leave excavations open and protected as required by the statutory authority after removal of work below
ground level until completion of inspection by architect/structural engineer.

Page 22 of 89 SECTION 02050 DEMOLITION


305 Methods and Operations
A. Ensure, where applicable, a copy of asbestos clearance certificate is received and maintained with the
demolition plan at the site.
B. Demolish and remove completely parts of structure listed and/or drawn for demolition. The methods of
cutting and removal of floors, walls, and other items to be removed are to be approved by authorities
having jurisdiction, or certified practising engineer.
C. Furnish flame-cutting required to dismantle sections of equipment too large to be otherwise removed.
Flame-cutting is to be performed only by experienced and qualified mechanics. Protect combustible
surfaces during flame cutting. Maintain fire extinguishers, required by the fire authority, at hand.
D. Do not drop or throw material, other than as detailed in Safe Work Method Statement.. Lower by means
of hoists, cranes or rubbish chutes etc. Wet down thoroughly during demolition to prevent nuisance of
dirt and dust. Equip trucks used in hauling debris with tarpaulins to cover the loads. Do not load so
excessively as to spill debris on streets.
E. Plaster removal: in general, removal of existing plaster showing cracks, bulges or drumminess is
required. Refer to architect if in doubt.
F. Except as placed in approved disposal containers, do not allow combustible material and rubbish to
accumulate on the site. Remove daily, or as directed. Burn no debris on site.
G. Upon completion of wrecking, demolition and the removal of rubbish and debris, remove equipment.

306 Reinstatement
Restore to original condition, without expense to the proprietor, any damaged parts of the remaining
construction resulting from failure to provide adequate protection. Refer also clause 105.

307 Disposal of Waste


Dispose of asbestos and other hazardous waste as per statutory or local requirements.

308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Leave the site in an entirely clean condition, ready for the work of other trades.

PART IV FITTINGS & FIXTURES

Location/Description Details
General The Contractor is to visit the site and ascertain/confirm exact conditions and include all
allowances as required for demolition in order to achieve new conditions (including all
associated rectification works). This includes redirecting/ sealing existing services etc.
The Contractor is to include protection of adjoining works and existing buildings areas to
remain during demolition including hoarding, dust sealing (polyurethane with taped joints) so
that minimal disruption occurs. Include all Scaffolding as required to complete the works.
Refer Services Consultants Drawings for cutting and sealing of services where applicable.
Builder is to include to protect adjoining works and existing buildings to remain during
demolition including hoarding, dust sealing (polyurethane with taped joints) so that minimal
disruption occurs. Include for all Scaffolding as required to complete the works.
Remove all rubbish and debris from site.
The Builder is to provide a photographic dilapidation report capturing all existing foot paths,
road surfaces, fences, etc within the vacility of the works prior to start of demolition works.
One copy to be given to the Project Manager.
Delapidation Report The Contractor is to provide a photographic dilapidation report prior to start of demolition
works. One copy is to be provided to the Project Manager.
The dilapidation report is to include all areas of delivery, loading, movement of materials,
shared spaces, etc.
Existing Building All demolition works are to be carried out in such a manner so to cause minimum disruption
to occupants in adjacent occupied areas within the building. Provide hoardings, dust stop
etc. to the Project Managers approval to all affected corridors and entry points.
Provide temporary site signage to all entry areas, including the Site Manager’s contact
details.
All items not required by the proprietor shall become the property of the builder and shall be
removed from site. All other items shall remain unless otherwise noted.
Existing Floor All existing floor finishes (Carpet, Vinyl, Etc) are to be removed and surface to be prepared
Finishes to a standard acceptable to the new covering manufacturer’s specifications
All existing glue is to be fully ground off.
All blemishes and inconsistancies to be filled and smoothed.
Construction The Contractor is to submit a construction management plan to the Project Manager for
Management Plan approval prior to the commencement of works confirming the location of the Contractor’s site
office, method for material delivery, any hoardings/fencing and access arrangements.
Hoarding The Contractor is to include protection of adjoining internal occupied areas and existing
buildings to remain during demolition including provision hoarding, dust sealing/protection to
ceilings (polyurethane with taped joints) so that minimal disruption occurs. Include for all
Page 23 of 89 SECTION 02050 DEMOLITION
Scaffolding as required to complete the works.
Provide minimum 2 metre high solid hoarding (marine grade ply or similar approved) to the
full length of the building site. The hoarding must be maintained throughout the duration of
the works and removed by the Contractor on completion.
Redundant Services Refer Services Consultants Drawings for cutting and sealing of services where applicable.
Ensure that the redundant sewer and water service connection points in the existing
facilities/ amenities to be demolished and capped and sealed nom. 300mm below ground
level.
Hazardous Material All hazardous materials including asbestos are to be removed from areas affected by
Removal demolition works by a certified contractor. Refer to the Division 6 report appended to the
architectural specification for all building elements identified or presumed to contain
hazardous materials. The contractor is to make allowance for all relevant removal works in
their tender, including the provision of a work method statement and plan to be approved by
Client and Project Manager prior to undertaking any works. It is the tenderer's responsibility
to inspect the space during the tender and review the report to make necessary allowance
for all works.

END OF SECTION

Page 24 of 89
SECTION 03530 CONCRETE SCREEDS (GRANOLITHIC)

PART I GENERAL

101 Scope
Supply and install a complete installation of granolithic surface screeds to the extent and thickness as indicated
on drawings or scheduled including but not limited to:
Applied granolithic screeds.
Matching coves, risers, kerbs, margins, pit covers, etc.
Float screeding, curing and protection.

102 Related Work


Co-ordinate and co-operate with the following trades:
Concrete Concrete pavements
Sanitary sewerage Floor finishes
Wall finishes Waterproofing and tanking

103 Quality Assurance


A. Provide data indicating that the tradesmen engaged for this project have a minimum of 5 years of
experience in such work as required by this specification.
Supply names of contacts, with telephone numbers, who can verify performance quality.
B. Prepare for the architect’s approval a square meter of granolithic screed, including coves, risers, kerbs
where applicable. When approved proceed with remaining work.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1379 2007 Specification and supply of concrete. Plus Supplement 1-2008.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip hazards.
AS 3700 2011 Masonry structures. There is 1 Supplement 2012
AS 3740 2010 Waterproofing of domestic wet areas. 1 Amdt, 2012.
AS 3799 1998 Liquid membrane-forming curing compounds for concrete.
AS 3972 2010 General purpose and blended cements.
HB 197 1999 An introductory guide to the slip resistance of pedestrian surface materials.
Where relevant, comply with construction standards and notes published by the Cement Concrete and
Aggregates Association of Australia , www.concrete.net.au

105 Submissions
Where applicable, provide evidence of payment of relevant fees.

106 Delivery Handling and Storage


Deliver materials properly packaged to the site in original, unopened containers with grade, type and quality
indicated on the labels.
Store and protect materials raised above floor and kept dry until ready for use.

PART II MATERIALS

201 Granolithic Components


A. Cement: Portland Cement, comply with AS 3972.
B. Stone (granolithic screeds): clean granite screenings of maximum size 6mm.
C. Stone dust (protective screeds): clean bluestone fines of maximum size 4mm.
D. Sand: washed, sieved, sharp sand, passing a No 16 (1.19mm) sieve.
E. Aggregate for screeds: dense aggregate graded as follows:
Passing 4.75 mm sieve 80%
Passing 6.00 mm sieve 90%
F. Water: clean drinking quality
G. Mesh: galvanised welded wire fabric, minimum 2.5mm diameter wires at 100mm each way.
H. Pigments: compatible with other components.

202 Joint Sealing Materials


A. Non-structural external weather-proofing sealants: low modulus neutral curing silicone rubber
compounds.
B. Joint primer/sealer: provide type of joint primer/sealer recommended by sealant manufacturer for joint
surfaces to be primed or sealed.
C. Bond breaker tape: polyethylene tape or other plastic as recommended by sealant manufacturer to be
applied to contact surfaces where bond to substrate or joint filler is to be avoided for proper performance
of sealant. Provide self-adhesive tape where applicable.
D. Sealant backer rod: compressible rod stock of polyethylene foam, polyethylene jacketed polyurethane
foam, butyl foam, neoprene foam or other flexible, permanent durable non-absorptive material as
recommended by sealant manufacturer for compatibility with sealant.
E. Sealant for floor joints: 2-part, self-levelling polyurethane based, chemically cured.
Page 25 of 89 SECTION 03530 CONCRETE SCREEDS (GRANOLITHIC)
203 Miscellaneous Materials
A. Compressed fibre cement sheet: 6mm thick.
B. Non-slip material: set into formed grooves in stair treads, silicone carbide or carborundum mix, mixed
and installed in accordance with manufacturer's instructions.

204 Mixes
A. Mix screeds with minimum water to produce screed material that is workable and will consolidate
uniformly. The proportion will depend on the sand in use and is found by practical trial. Minimise random
variations once the proportions are established. Carefully control water quantity.
B. Granolithic finish mix: 1:2:1 cement: stone: sand.
C. Protective screed mix: 20 MPa concrete with maximum aggregate size of 6mm.
D. Batching by shovelful is not allowed. Batch by weight only.
Add pigment as instructed by manufacturer to a sample colour approved by the architect.
E. Waterproofing: add mixture. Refer section 07130 WATERPROOFING AND TANKING, System Type D.

PART III EXECUTION

301 Examination
Visit site and inspect conditions to drawings before delivery of materials to site. Notify contractor of any
discrepancy or unsuitability or substrate.
Start of work means total acceptance of conditions.

302 Records
Obtain essential services information (Dial Before You Dig).
303 Preparation
Before commencing work, ensure that the concrete is clear and free of mortar, honeycombing, surface cavities,
oil, tying wires or other surface deficiencies and is suitable to receive the membrane.
Sweep up all debris.
Roughen surface of existing surface to ensure adequate key for granolithic.

304 Mix Life


Reject material which, in the architect's opinion, has become excessively stiff so as to make placement difficult.
Re-tempering of mixes will not in any case be permitted. Discard any mortar unused within 2 hours of adding
water.

305 Screeds
A. Dense screeds: thickness of not less than 25mm, except 20mm at outlets. Reinforce with light
galvanised steel mesh. Refer clause 201 G.
B. Protective screeds: 50mm thick parallel to substrate.
Reinforce with light galvanised steel mesh. Provide control joints as specified in clause 305D. Dust on
and trowel in bluestone fines.
C. Setdowns: for screeds to receive other finishes, consult with other sub-contractors for those finishes to
determine the setdown required.
D. Walls and upstands: finish at junction with walls and upstands with galvanised wire mesh and 50mm
radius cove.

306 Installation of Granolithic Toppings


A. Place, compact and screed to the required levels and grades and trowel to a smooth surface, true to
plane and free from trowel marks. Grade evenly to drains, 1:80 minimum.
B. Thickness: 50mm thick parallel to substrate.
C. Scoring: provide scored pattern of 600 x 600 with trowel to regular depth.
D. Control joints: provide control joints 10mm wide to receive floor joint sealant. Joints to be maximum 3
metres apart. Provide joint 600mm inside and parallel to parapets or walls.

307 Tolerances
A. Tolerances to grades established on drawings: + 5mm, -5mm
B. Local variation from a flat surface: not to exceed +3mm -3mm under a 3 metre straightedge, with 6mm
"feet" on each end so variations can be measured from the surface to the straightedge.

308 Curing
General: protect from premature drying and excessively hot or cold temperatures. Where required, provide
damp curing.

309 Added Colour


Where scheduled, add to concrete mix prior to pouring/application.

Where alternate finish and installation is approved by the architect add in 2 successive applications, worked
into the surface by trowelling to smooth dense finish.

Page 26 of 89 SECTION 03530 CONCRETE SCREEDS (GRANOLITHIC)


310 Joint Preparation - Sealants
A. Clean joint surfaces immediately before installation of sealant or caulking compound. Remove dirt,
insecure coatings, moisture and other substances which could interfere with bond of sealant or caulking
compound. Etch concrete and masonry joint surfaces as recommended by sealant manufacturer.
Roughen vitreous and glazed joint surfaces as recommended by sealant manufacturer.
B. Prime or seal joint surfaces where indicated and where recommended by sealant manufacturers. Do not
allow primer/sealant to spill or migrate onto adjoining surfaces.

311 Installation of Sealants


Install sealant backer rod for liquid elastomeric sealants, except where shown to be omitted or recommended to
be omitted by sealant manufacturer for application indicated. Install bond breaker tape where indicated and
where required by manufacturer's recommendations to ensure that elastomeric sealants will perform properly.

312 Protection
Lay hardboard over completed work for minimum of 5 days.

313 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Clean up leaving the surfaces in first class condition to the satisfaction of the architect.

PART IV DETAILS

Location/Description Details
Screeding Provide concrete bulkfill and screeding to concrete slabs to all areas in scope/affected
by demolition and building works to achieve a smooth and level finished floor.
Tenderersare to allow for a minimuim 10mm thickness of screed/ardit to all areas
receiving new floor finishes in tender pricing. Bulkfill to setdowns to demolished brick
and blockwork walls must be allowed for within tender submissions.
All general screeding to be Ardex or similar approved product.
Provide full infill screeding to the existing slab recessed tracks to the existing
compactus to be demolished.

END OF SECTION

Page 27 of 89 SECTION 03530 CONCRETE SCREEDS (GRANOLITHIC)


SECTION 05080 METAL FINISHES - SHOP-APPLIED

PART I GENERAL100

101 Scope
Supply all labour and material, services and equipment necessary for the preparation, application and finishing
of metal surfaces as indicated on drawings, schedules and as specified herein, to internal and external metal
surfaces as follows:
Refer Schedule of Finishes.

102 Related Work


Co-ordinate and co-operate with the following trades:
Metalwork Structural steel
Metal door frames and fire doors Metal windows
Metal decking and roof plumbing

103 Quality Assurance


A contractor with wide experience in this class of work is required for the work of this section.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1231 2000 Aluminium and aluminium alloys - Anodic oxidation coatings.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS 2832 Cathodic protection of metals. There are 5 parts, 2003 – 2008.
AS 3715 2002 Metal finishing - Thermoset powder coating for architectural applications of
aluminium and aluminium alloys.

105 Submissions
Submit the following materials:
A. Product literature on all proposed finishing systems.
B. Colour samples for all approved finishing materials. Provide samples identified with:
1. Manufacturer's colour code and colour name.
2. Match to schedule colour code and name.
C. Samples not less than 100 x 100mm and of the same gloss level as the scheduled colour.

106 Delivery, Handling and Storage


Handle all materials with care.
Do not store on site.
Install directly in place.

107 Warranty
Provide a written warranty stating the preparation of surfaces, materials and material application under this
contract will show no deterioration and remain in good condition for a period of 7 years from date of Practical
Completion.

PART II MATERIALS200

201 Materials – General


Where manufacturer makes more than one grade of any material specified, use the highest grade of each type,
whether or not the material is mentioned by trade name in these specifications.

202 Metal Finishes


A. Anodising
Anodise to colour selected and approved by the architect. Pre-treat and apply anodising by applicators
approved by the architect.
Minimum coating thickness of 25 microns subjected to random testing after installation. Remove and
replace non-conforming material.
B. Polyester powdercoat
Apply polyester powdercoat, to colour approved by the architect to metal surfaces specified.
Perform pre-treatment and application of powder coating by applicators approved by the architect and
by the manufacturer of the powder material.
Minimum coating thickness of 50 microns subjected to random testing after installation. Remove and
replace non-conforming material.
C. Fluoroset FP (Dulux Product).

Page 28 of 89 SECTION 05080 METAL FINISHES - SHOP-APPLIED


203 Schedule
Refer to Fixtures and Finishes Schedule

PART III EXECUTION300

301 Examination
Inspect all surfaces and determine that they are in proper condition to receive the work to be performed under
this section.
The starting of work under this section means acceptance of such surfaces as being satisfactory and any
defects in work resulting from accepting poor surfaces are to be corrected at no cost to the proprietor.

302 Preparation
A. General: prepared to a standard not less than that described in AS 1627.
B. Clean base metal surfaces of all mill scale, rust, grease, oil, dirt or other foreign matter then properly
wash with spirit or other approved cleaning agents.
After cleaning, etch, pickle or prepare as recommended by manufacturer of the finish applied.

303 Protection
Protect finished metal surfaces as necessary during handling, transport and erection to prevent mechanical
imperfections such as scratches, scrapes, dents, spots, stains and streaks.
Do not use adhesive protective coating. Protect by other means with the approval of the architect.

304 Application
Execute all work in this section in strict compliance with the manufacturer's recommendations and with the
provisions of the Australian Standards which are incorporated by reference as part of this specification and
apply to the work in this section to same extent as if written herein. In the event of conflict between
manufacturer's recommendations and the provisions of the Australian Standards, manufacturer's
recommendations govern.

305 Cleaning
At completion of work, keep and maintain finished surfaces clean and free from dust, dirt and other foreign
matter.

306 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV DETAILS

Location/Description Details
Colour Refer to Appendix 02 Finishes Schedule for colour and finish.

END OF SECTION

Page 29 of 89
SECTION 05500 METALWORK

PART I GENERAL100

101 Scope
Supply, engineer and install required general and architectural metalwork items including but not limited to:

102 Related Work


Co-ordinate and co-operate with the following trade sections:

103 Quality Assurance


Work of this section will be performed by experienced craftsmen familiar with the quality required in this class of
work.
Comply throughout with manufacturer's instructions.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1554 Structural steel welding. There are 7 parts, 1994 – 2012.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS/NZS 1734 1997 Aluminium and aluminium alloys - Flat sheet, coiled sheet and plate.
AS/NZS 1866 1997 Aluminium and aluminium alloys - Extruded rod, bar, solid and hollow shapes.
AS 4100 1998 Steel structures. Plus 1 Supplement 1999, 1 Amdt 2012.
AS/NZS 4673 2001 Cold-formed stainless steel structures.
AS/NZS 4680 2006 Hot-dip galvanised (zinc) coatings on fabricated ferrous articles.
Comply with requirements of statutory and local authorities.

105 Shop Drawings


Comply with DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT, clause 27.
Provide Shop Drawings for major items supplied hereunder.
A. Contract drawings and details provided are indicative as to general and minimum requirements, and do
not show conditions.
Develop details not shown and in conformity with the indicative details shown.
B. Take and confirm dimensions on site, before preparing Shop Drawings where possible.
C. Submit detailed Shop Drawings for fabrication and installation of major metalwork. Show plans,
elevations and detailed sections; indicate materials, finishes, types of joinery, fasteners, anchorages and
accessory items. Provide setting diagrams and full-scale templates of blocking, anchorages, sleeves
and bolts installed by others.

106 Samples
Sample welds: if requested, provide samples of weld types, including samples of railings joined at right angles
and at typical acute angles, welded and ground smooth, for approval. If not acceptable, provide additional
samples until approved. Approved samples establish quality of similar work of this section.
Check on delivery: request architect to check materials on delivery to site for quality, and materials not meeting
the requirements of this specification or equal to approved samples will be rejected.
Return rejected materials to the fabricator at the fabricator's expense.
Finish: provide samples of specified finishes when requested.

PART II MATERIALS

201 Materials
Refer to Fixtures and Fittings Schedule, as well as Architectural, Structural and other consultant drawings.

202 Finish
Materials exposed to weather may be either:
Mild steel - hot dipped galvanised after fabrication or chromate pre-treated followed by polyester powder
coating.
Finish internal steel after fabrication with zinc-rich organic primer, or with inorganic zinc silicate paint.
Comply with relevant codes of practice or manufacturers' recommendations.

203 Welding Steel


General: details of joints, the techniques of welding employed, the appearance and quality of welds made and
the methods used to correct defective work; conform to requirements of AS/NZS 1554.
Welds exposed to view: grind smooth to architect's approval.
Concealed welds: grind smooth before galvanising.
Tack or skip welding: at regular intervals, very neat. Not permitted if material is to be hot dip galvanised.
Remove weld spatter.
Certification: only welders who have previously been qualified by tests may weld.
Page 30 of 89 SECTION 05500 METALWORK
Tack welding or skip welding will NOT be permitted where items are to be galvanised. Weld continuously form
joints and connections to exclude water and to permit draining during galvanising.
Stainless steel welding: refer AS/NZS 1554.

204 Connection Design


General: design fabricated items so that possible work is done before delivery. Fully protect for shipment.
Take possible care to prevent damage.
A. Welding external items: conform to the recommendations of AS/NZS 1554, noting particularly the design
criteria.
B. Flanges: concealed where possible. Sleeve connecting railings inside railing sections and secure with
flush or set screws. Except where access is impossible, connection screws and bolts will be on the
underside of joints.
C. Fasteners on the top of railing sections will not be permitted.
D. Weld shop connections for steel fabrications, and bolt field connections.
E. Provide smooth finishes to exposed surfaces with sharp well-defined lines and arrises. Mill to a close fit
machined joints. Design necessary lugs, brackets and similar items so that work can be assembled and
installed in a neat, substantial manner.
F. Provide ample strength and stiffness by using appropriate metal thickness of assembly and supports.
G. Provide holes and connections as required to accommodate the work of other trades and for site
assembly of metalwork. Drill or punch and ream in the shop.

205 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required for a
complete installation.
Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the item is
to be secured. Refer to architect if in doubt.
Fasten galvanised items with galvanised fasteners.

206 Dissimilar Metals


In moist environments, eg swimming pools of either fresh water or sea water etc, prevent totally contact
between dissimilar metals (any metals).
This instruction takes priority over any drawing, detail or instruction and will prevent cathodic reaction between
the metals.
Refer this instruction to the structural engineer.

PART III EXECUTION

301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure conditions
are satisfactory for installation. Arrange for rectification required.
Start of work means total acceptance of relevant conditions.

302 Preparation
Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in the field where
taking of measurements might cause delay.
Co-ordination with work of others: furnish to each relevant trade foreman anchorages and setting drawings,
diagrams, templates and instructions for installation of items having integral anchors which are to be embedded
in concrete or masonry construction. Co-ordinate delivery of such items to the project site.

303 Inspection and Reinstatement


Check fabrications as they are unloaded at the project site for evidence of physical damage.
Treat damaged fabrications as follows:
A. Damage through galvanising: perform immediate inorganic zinc silicate paint or cold-galvanising repair.
Do not install until reinstated.
B. Architectural metalwork: returned to shop for repair or replacement.
Verify anchors, bolts and other required anchorage items for proper size and accurate location prior to erection.

304 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or relevant Australian Standards,
Anchorage: except for anchorages furnished herein but placed by other trades, set and secure necessary
anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as needed.
Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper positioning of
completed work.
Fit: during installation and assembly, form tight joints with exposed connections accurately fitted, and reveals
uniform. Finish work accurately, plumb, level, square and true in reference to adjacent construction. Make
tolerances conform to Australian Standards.
Finish: do not cut or abrade shop finishes which cannot be completely restored in the field.
The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted under conditions.
Fabrications may be cut shorter with power hacksaws on site.

Page 31 of 89 SECTION 05500 METALWORK


Isolate dissimilar metals likely to be subject to moisture with inert materials, not visible on completion of
installation.

305 Field Quality Control


Where considered necessary by the architect, arrange for the manufacturer of products to instruct installers
regarding correct installation.

306 Protection
Cover work: immediately following installation, wrap or cover architectural metalwork to avoid wear and tear of
finish during subsequent construction.

307 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.

308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV DETAILS

Location/Description Details
General Refer to Appendices - Fitting and Fixtures Schedule for additional specifications
To be read in conjunction with Door and Door Hardware Schedule.
All wall hung fixtures and fittings including handrails and WC back rests shelves are to be
fixed directly to suitable timber studs located specifically for such support. Studs to be
located with 'stud finder' prior to installation of fixture.
Floor Transition Strip Builder to allow to install transition strips between all dissimilar floor materials, to be located
at the centre of the door in the closed position. Provide DTA Australia ACCP18.33MS in matt
Aluminium or similar approved. Sample to be installed in one location for architect approval
prior to proceeding with general installation.
Skirtings Supply and install 150mm high powdercoated skirting (colour as scheduled) to all new and
existing walls, columns etc…
All moudline skirting is to be 150mm high powdercoated as scheduled.
Vinyl to Carpet At vinyl to carpet transitions, install ‘DTA Australia’ Aluminium vinyl transition.
Transition Locally building up screed for vinyl flooring to to match height of carpet to achieve a flush
finish.
Builder to inspect and measure carpet prior to ordering.
Fire Extinguishers Supply and install fire extinguishers adjacent to switchboards and/or locations as required by
MFB and other relevant authorities. Confirm final location on site with Architect.
Fire Smoke Seals/ All penetrations through fire rated walls and slab are to be fire sealed.
Collars Provide fire rated mechanical dampers as noted on the mechanical engineer’s drawings.
Provide sealants, smoke blankets etc. to achieve this.
Refer Services Engineer’s details for more information.

END OF SECTION

Page 32 of 89 SECTION 05500 METALWORK


SECTION 06100 CARPENTRY

PART I GENERAL

101 Scope
Provide materials and labour, equipment and services and perform operations necessary to complete the
carpentry as indicated and specified. Include nailers, blocking, furring, grounds, hardware, framing, shoring,
bracing, ramps, scaffolding and barriers required by the drawings and construction.

102 Related Work Co-operate and co-ordinate with the following trades:

103 Quality Assurance


Prototype: at a location selected by the architect on site, construct a full size prototype of:

Include in each prototype elements required by this specification, and finish in every respect. When approved
by the architect, such samples remain part of the work and become the standard for the remaining work.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS 1684 Residential timber-framed construction. There are many parts and Supplements,
1999 - 2010.
1684.2 2010 Non-cyclonic areas. Numerous supplements, 2 Amdmts 2012
and 2013
1684.3 2010 Cyclonic areas. Numerous supplements, Amdmt 2012
1684.4 2010 Simplified - Non-cyclonic areas. Special reprint with Amdmt 1
2012 included
AS 1720 Timber structures.
1720.1 2010 Design methods. Plus 2 Amdts, 2010 - 2011.
1720.2 2006 Timber properties. Plus 1 Amdt, 2006.
1720.4 2006 Fire-resistance for structural adequacy of timber members.
AS/NZS 1859 Reconstituted wood-based panels - Specifications
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt, 2009.
There is 1 other part, 2004.
AS 1860.2 2006 Particleboard flooring – Installation. Plus 1 Amdt, 2010.
AS/NZS 2904 1995 Damp-proof courses and flashings. 2 Amdmts, 1998, 2013
AS 3959 2009 Construction of buildings in bushfire-prone areas. Plus 3 Amdts, 2009 - 2011.
AS 4055 2012 Wind loads for housing.
AS 4226 2008 Guidelines for safe housing design.
AS/NZS 4364 2010 Timber – Bond performance of structural adhesives.
AS 4786.2 2005 Timber flooring - Sanding and finishing.
HB 44 1993 Guide to AS 1684 1992, The National Timber Framing Code.
Further advice and changes in specifications of timber are needed frequently. For latest information visit
www.timber.net.au
For timber decks visit the Outdoor Timber section of Resources at www.timber.net.au.

105 Submissions
Submit the following prior to ordering materials:
Product literature on hardware items proposed.
Technical data on melamine laminates proposed for use.
Technical data and samples of substrate materials (particleboard etc.) Thickness of materials at typical
locations and functions.

106 Delivery, Handling and Storage


Deliver, handle and store products so that damage, deterioration and loss will be prevented. Control delivery
schedules to minimise long-term storage at site.
Store timber on site indoors, or above ground and cover with secure impervious material.

Page 33 of 89 SECTION 05500 METALWORK


PART II MATERIALS

PART III EXECUTION300

301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Start of
work means total acceptance of conditions.

302 Installation General


Comply with: AS 1684 Residential timber-framed construction, and other relevant Standards.
Ensure installation of isolation material between timber and damp substrate, installed in accordance with
AS/NZS 2904 1995.

303 Installation Particulars


Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Perform operations including grooving, rebating, framing, housing, beading, mitring, scribing, nailing, screwing
and gluing as necessary to carry out the works. Use timber in single lengths whenever possible. If joins are
necessary, make them over supports unless otherwise shown or specified.
Arris visible edges in sawn work and in dressed work arris with sandpaper to 1.5mm radius unless otherwise
shown or specified.
Back plough boards liable to warping (for example, if exposed on one face). Make the width, depth number and
distribution of ploughs appropriate to the dimensions of the board and the degree of its exposure.
Provide necessary templates, linings, blocks, stops, ironwork and hardware, screws, bolts, plugs and fixings
generally.
Install waterproof membrane to separate infrastructure from concrete or masonry.
Trim framing where necessary for openings, including those required by other trades.
Unless otherwise noted, construct framing so that floors are horizontal, i.e. no more than 3mm slope in
3000mm.
Construct wall framing vertical, so that no more than 3mm out of vertical in 3000mm of wall height.

304 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
General All carpentry timbers shall conform with the description, strength groupings and gradings of
the relevant Australian standard specifications. Stress gradings shall conform with the
requirements of the current Australian standard and shall be selected to suit timber size
indicated on the drawings.
Termite Protection All timber used in construction is to be ‘Hyne - T2 Termite Resistant Timber’ (or similar
supplier).
Timber Framed Walls Include to supply and install timber stud with 13mm Plasterboard (standard,
(Internal) acoustic/soundcheck or moisture resistant as nominated) lining to both sides, with skirting as
indicated.
Studs @ 450 ctrs max.
Studs to be 90 x 35 F5 MGP including noggings to AS1684. Max height 3000mm (non load
bearing), unless shown differently on Structural Engineers Details.
Bottom and top plates 90 x 45 F5 MGP, unless shown differently on Structural Engineers
Details.
Provide boxed (double) studs of timber blocking to support loads – shelving, joinery,
cupboards etc.
Provide double studs to sides of all openings.
Load bearing walls to Engineer’s details.
Bulkheads where Include to Supply and install 16mm MDF bulkheads as detailed in architectural
Required documentation.
Cut and Seal all MDF edges prior to plastering and painting.
Engineered timber Engineered timber to have low formaldehyde content.
Adhesives and Adhesives to be Low VOC
Sealants
Steel Stud Framed Supply and install Rondo (or equiavelnt) steel studs (generally 92, 76 or 64mm - refer
Walls (Internal) to architectural drawings) at 450mm or 600mm centres, 1.15 BMT, with 13mm flush
plasterboard (standard, acoustic/soundcheck or moisture resistant as nominated)
linings to both sides, with skirting as indicated on the architectural drawings. Install
Page 34 of 89 SECTION 05500 METALWORK
studs in accordance with manufacturer’s installation instructions– refer to structural
engineer’s details for structural tie or plywood bracing backs for AV elements.
All studs generally at @ 450 ctrs max., unless noted at 600mm centres on the
drawings.
Supply and install 28mm steel furrning channels to existing walls with 13mm flush
plasterboard (standard, acoustic/soundcheck or moisture resistant as nominated)
linings to one side where indicated on the drawings. Furring channels to be @
450mm ctrs max.
Provide boxed (double) studs of timber blocking to support loads – shelving and
joinery etc.
Provide double studs to all sides of all openings, doors, etc…
Bulkheads where Include to Supply and install flush 13mm plasterboard bulkheads as detailed in
Required architectural documentation. Frame bulkheads with 90x45mm timber studs or 64mm
steel studs at 450mm centres.
Cut and Seal all MDF edges prior to plastering and painting.

END OF SECTION

Page 35 of 89 SECTION 05500 METALWORK


SECTION 07200 INSULATION (THERMAL AND ACOUSTIC)

PART I GENERAL

101 Scope
The scope of work includes, but is not limited to, the supply and installation of thermal insulation.
It also includes the supply and installation of acoustic insulation.

102 Related Work


Co-ordinate and co-operate with the following trades:
Carpentry Wall and roof framing
Brickwork Blockwork
Metal roofing Roof tiles
Plasterboard Suspended ceiling

103 Quality Assurance


Installers are required to be widely experienced in relevant aspects of the work and with the requirements of
Australian Standards appropriate to the work.

104 References
Comply with the applicable portions of these Australian Standards:
AS 1366 Rigid cellular plastic sheets for thermal insulation. There are 4 parts, 1989-1992, and
2 Amdts, 1992 - 1993.
AS/NZS 2107 2000 Acoustics - Recommended design sound levels and reverberation times for building
interiors.
AS 3671 1989 Acoustics - Road traffic noise intrusion - Building siting and construction.
AS 3999 1992 Thermal insulation of dwellings - Bulk insulation - Installation requirements. 1 Amdt,
2012
AS/NZS 4200 Pliable building membranes and underlays.
4200.1 1994 Materials. Plus 1 Amdt, 1994.
4200.2 1994 Installation requirements.
AS/NZS 4859.1 2002 Materials for the thermal insulation of buildings - General criteria and technical
provisions. Plus 1 Amdt, 2006.
Comply with the requirements of the Building Code of Australia.

105 Submission
Provide to the architect before ordering, samples, literature and technical data of each specified material.

106 Delivery, Handling and Storage


Deliver, handle and store products so that damage, deterioration and loss will be prevented. Control delivery
schedules to minimise long-term storage at the site.
Store above ground with secure impervious material.

PART II MATERIALS

201 Approved Material Suppliers

202 Materials – Thermal


A. Thermal insulation (building paper type) with and without reflective facings, with and without flame
retardants, sarking.

B. Vapour barriers - with and without reflective facings - paper/foil, high density polyethylene breather
membranes, aluminium foil reinforced or folded as batts.

Comply with manufacturer’s recommendations and AS/NZS 4200.1 Materials


C. Bulk thermal insulation - in sealed batts or sealed blankets semi-rigid glasswool, rockwool or cellulosic
fibre, sea-grass, polyester, with or without facing. In-situ urea-formaldehyde foam.
Comply with manufacturer’s recommendations and the applicable Australian Standards.
D. Rigid cellular insulation - polystyrene polyurethane, polyisocyanurate urea-formaldehyde foam boards.
Comply with manufacturer’s recommendations and the relevant Australian Standards.

203 Materials–Acoustic
A. Acoustic insulation (attenuation type) with or without facings - flexible polyurethane foam, polyester
blankets, glass and mineral wool batts, plasterboard.

B. Acoustic insulation (absorption type) with or without facings, reinforcement - suspended mineral fibre
ceilings, mineral tiles, perforated fibre cement sheet systems, and panels, metal pans and strips with or
without absorption batts, suspended baffles sound barriers, sprayed texture finishes of plaster, cement
or vermiculite.

Page 36 of 89 SECTION 05500 METALWORK


C. Acoustic sealants - polyethylene foam, closed cell resilient foams, polyurethane foams, non-shrinking
sealants of silicone or similar type with good adhesion, door and window seals.

PART III EXECUTION

301 Examination
Visit the site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Start
of work means total acceptance of conditions.

302 Preparation
Prepare surfaces and/or framing material and ensure that no obstructions will prevent rapid and effective
installation.

303 Installation General (Thermal)


Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Comply with manufacturer’s current written recommendations and the relevant Australian Standards.
Install membrane to metal roofing, tiled roofing, walls, underside of floor.
Install bulk thermal insulation to:
Walls
Roof
Ceiling space
Install rigid thermal insulation to areas shown on the drawings: roof, walls, etc.

304 Installation General (Acoustic)


Install acoustic attenuation type material in accordance with the manufacturer’s current written
recommendations. Comply with AS/NZS 2107.
Install acoustic absorption material in accordance with the manufacturer’s current written recommendations.
Seal junctions and around penetrations where indicated by the acoustic systems designs.
Spray surface after providing protection and masking to surrounding surfaces, in accordance with
manufacturer’s instructions.

305 Cleaning
Remove surplus material on completion and arrange for inspection(s) by manufacturer’s representative.

306 Completion
Complete contracted work in accordance with the contract document and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description
Details
General The ‘top edge’ of plasterboard wall lining above the ceiling line is to be sealed to create airtight
thermal air pocket against wall.
All Internal Down Pipes, Sewer Risers, Etc to be fully lagged with acoustic insulation.
All Amenities, Offices, Boardrooms, Lunch Room, Tea Points Meeting Rooms etc…
ACOUSTIC INSULATION
Walls All walls surrounding Amenities, Meeting room & Private offices to have full height insulation to
underside of ceiling tiles above.
All walls surrounding Conference Rooms, Boardrooms and Call Centre to have full height
insulation to underside of floor slab above. Provide mastic for sealing junction between top of
walls and slab.
CSR Bradford (75mm thick, 14kg/m2) Glasswool Partition Batts
Where walls do not extend full height, provide 1200mm wide Autex Greenstuff Baffleblock or
equivalent insulation from the ceiling level to the roof above. Allow to cut and seal around all
in ceiling services penetration.
Ceilings CSR Bradford 115mm thick gold ceiling batts.
Lay a full batt 600mm to either side (1200m overall) of all office perimeter walls
Acoustic Wall Allow to supply and install direct stick 25mm Autex Quietspace fabric acoustic wall panels as
Panels noted on the architectural drawings and schedules. All specified fabrics and panels to be
professionally cut by an Autex recommended contractor and all edge are to be fully fabric
wrapped – no exposed edges. Colours as scheduled. Refer to finishes plan and elevations for
location and extent.

END OF SECTION

Page 37 of 89 SECTION 05500 METALWORK


SECTION 07810 FIREPROOFING

PART I GENERAL100

101 Scope
Design, fabricate and install materials with required components, fixings, fabrication techniques, coatings and
finishes including but not limited to:

102 Related Work


Co-ordinate and co-operate with the following trades:
Structural steel Concrete
Wall framing Floor framing
Mechanical Electrical

103 Quality Assurance


A. The products specified herein are proprietary items manufactured and supplied by specialist fabricators.
Manufacturer is required to submit written verification of quality of aspects of materials and performance.
B. Provide certificates prepared by relevant testing authorities stating that the materials comply with fire-
rating and other characteristics claimed by the manufacturer, and qualities required by the relevant
statutory authorities.
C. Pre-installation conference.
Arrange for a conference to establish and settle matters regarding the site installation methods and time
schedule.
D. Installation and application at the site is required to be performed in accordance with the requirements of
relevant statutory authorities.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1530 Methods for fire tests on building materials, compounds and structures.
There are 7 parts, 2 Amdt, 1992 – 2007.
AS 1603 Automatic fire detection and alarm systems. There are 12 parts 1996 – 2011 and 4
Amdts, 1996 – 2001.
AS 1670 Fire detection, warning, control and intercom systems, system design, installation
and commissioning. There are 4 parts, 1997 – 2004, plus 1 Amdt, 2005.
AS 1682 Fire Dampers.
1682.1 1990 Specification.
1682.2 1990 Installation.
AS 2118.4 Automatic fire sprinkler systems
AS 3784.1 1990 Coatings for fire protection of building elements – Guide to selection and installation
of sprayed mineral coatings.
AS 3959 2009 Construction of buildings in bushfire-prone areas. Plus 3 Amdmts 2009-2011
AS 4072.1 2005 Components for the protection of openings in fire-resistant separating elements –
Service penetrations and control joints. Plus 1 Amdt, 2006.
AS 5414 2012 Bushfire water spray systems
Bushfire Set 2009
HB 37.4 1994 Handbook of Australian fire Standards – Building materials, products and
construction.

105 Submission Required Prior to Fabrication


A. Complete system description including the following information:
1. Names of manufacturers of products.
2. Names, addresses and telephone numbers of local representatives for products.
3. Types, names of products, and indication whether products are "off the shelf" or custom
fabricated. Include specific information on finishes - thicknesses, patented process name,
process description and test data.
4. Detailed system description including standard details and manufacturer's literature
B. Statement that the proposed system meets the regulatory requirements, for fire protection and warranty
requirements specified.
C. Shop Drawings: refer Document 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT, clause 27.
Provide Shop Drawings showing the following information where appropriate to the items:
1. Layout (sectional plan and elevation of complete assembly).
2. Full size section of members.
3. Methods of assembly.
4. Methods of installation, including fixings, anchorage, caulking.
5. Provision for expansion (thermal).
6. Junctions and trim to adjoining surfaces.
7. Fittings and accessories.
D. Sealants: submit manufacturer's product specifications, handling, installation/curing instructions, and
performance tested data sheets for each elastomeric product required. Submit certificate of test reports
for elastomeric sealants on aged performance, including hardness, stain resistance, adhesion, cohesion
Page 38 of 89 SECTION 07810 FIREPROOFING
or tensile strength, elongation, low-temperature flexibility, compression set, modulus of elasticity, water
absorption and resistance (ageing, weight loss, deterioration), exposure to heat, ozone and ultraviolet
light.

106 Delivery, Handling and Storage


Deliver the materials to the site in a totally satisfactory condition. Provide security for materials not installed,
from loss of damage by weather or other cause.
Do not install damaged components or panels; remove and replace.

107 Project Site Conditions


Do not install wet processes in wet weather, or when temperature is less than 4oC or more than 35oC.

108 Warranty
Provide to the architect a written warranty stating that components of the complete installation will remain intact
and in a satisfactory condition for 5 years from the date of Practical Completion.

PART II MATERIALS200

201 Acceptable Manufacturers

202 Design Criteria


All materials to be erected/applied are to meet the following criteria.
A. Structural movement (of building).
B. Thermal movement.
C. Wind load on panels.
D. Dead load of panels and support structure.
E. Fire resistance requirements.
F. Anchor bolts to secure panels and support structure to building.

203 System Components


Where proprietary items are specified, comply with manufacturer’s/suppliers recommendations.

204 Fabrication
A. Provide and fabricate frame and support structures.
B. Check site dimensions before fabrication of components. Tolerances are not to exceed +3mm, -3mm.
C. Schedule fabrication in accordance with contractor's construction program.
D. Mark each item for easy identification.

205 Source Quality Control


The engineer and architect will make random inspections at various stages of works during installation.
Make available items needed for inspection and verification of compliance with this specification.

PART III EXECUTION300

301 Examination
Examine conditions at the site before delivery of materials and prior to the commencement of installation.
Arrange with contractor for correction of non-optimum conditions.
Start of work means total acceptance of conditions.

302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Protect by appropriate means adjoining surfaces of the building which may be damaged during the installation.

303 Installation
Install/apply all fireproofing materials in locations as instructed and as detailed on the documents. Secure in
final position.
Comply with supplier's/manufacturer's installation recommendations.

304 Sealants
At junctions with other materials, insert into opening a backing rod, wedged firmly in place. Apply over the
backing rod an approved fireproofing sealant, to colour selected by the architect.
Comply with supplier's/manufacturer's installation recommendations.

305 Field Quality Control


A representative or system supplier is required to be present during the installation of fireproofing materials in
the building.

306 Repairs
Repair damaged surfaces which may have been damaged during installation.
Page 39 of 89 SECTION 07810 FIREPROOFING
Make good the surfaces and reinstate material integrity, all in strict accordance with manufacturer’s
instructions.

307 Protection
Protect the installation until completion of the project. Prevent damage to completed work by necessary means.

308 Cleaning
On completion, clean up debris, remove support structures, scaffolding and the like. Leave work and surfaces
in entirely clean and uniform condition.

309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES


Location/Description Details
General Ground floor fire rating to load bearing internal columns generally to achieve a minimum FRL
of 120/-/-.
Ground floor fire rating to load bearing external walls generally to achieve a minimum FRL
120/30/-.
Underside of level 1 slab tos generally to achieve a minimum of FRL 30/30/30.
Enclosure below foyer stair to generally achieve a minimum FRL of 60/60/60.
Services Risers Provide 2 x 16mm CSR Gyprock Fyrcheck with CH Rondo steel studs and 1 xlayer of 25mm
Gyprock shaft liner to services risers where noted on the drawings to achieve a minimum FRL
of -/120/120. Refer appendices.
Fire Rated Fire rated plasterboard to be installed to manufacturers specification.
Plasterboard Refer to architectural drawings for locations.
Refer to CSR ‘Red Book’ and product installation specifications.

END OF SECTION

Page 40 of 89
SECTION 08200 DOORS AND DOOR FRAMES

PART I GENERAL100

101 Scope
Supply and install timber doors and timber [or steel] door frames including but not limited to:
A. EXTERNAL DOORS
Timber doors in timber frames (jambs).
Timber doors in metal frames (jambs).
Glazed doors.
Solid core doors.
Waterproof doors.
Timber louvred doors.
Flyscreen doors.
Security doors.
Acoustic doors.
B. INTERNAL DOORS
Flush panel doors – hollow core.
Flush panel doors – solid core.
Timber or metal frames (jambs).
Acoustic doors.
Glazed doors.
Expressed frame doors.

102 Related Work


Co-ordinate and co-operate with the following trades:
Carpentry Joinery
Blockwork Brickwork
Plasterboard Fire-rated doors and frames
Metalwork Glass and glazing
Painting Electrical

103 Quality Assurance


Prototype: at a location selected by the architect construct a complete prototype installation of:

Include in each prototype elements required by this specification, finished in every respect. When approved by
the architect, each prototype remains part of the work and becomes the standard for the remaining work.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1288 2006 Glass in buildings – Selection and installation.
Plus 1 Supplement, 2006, and 2 Amdt, 2008 – 2011.
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS/NZS 1859 Reconstituted wood-based panels – Specifications
1859.1 2004 Particleboard. Plus 2 Amdt, 2006 – 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt, 2009.
1859.4 2004 Wet-processed fibreboard.
AS/NZS 2272 2006 Plywood – Marine.
AS 2688 1984 (Obsolescent) Timber doors.
AS 2689 1984 (Obsolescent) Timber doorsets.
AS 4145 Locksets and hardware for doors and windows. There are 4 parts, 2001 – 2008 plus
2 Amdts, 2009.
AS 5007 2007 Powered doors for pedestrian access and egress.
AS 5039 2008 Security screen doors and security window grilles.

105 Submissions
Submit the following for inspection by the architect before installation:
Product literature on proposed hardware items.
Samples of items as requested by architect.

106 Delivery, Handling and Storage


Deliver specified items shortly before installation is due to occur.
Prevent damage and deterioration during transport and handling.
Store carefully at site in a secure area. Prevent twisting and warping of doors. Note the condition requirements
of clause 304.

Page 41 of 89 SECTION 08200 DOORS AND DOOR FRAMES


107 Warranty
Provide to the proprietor a warranty covering faulty materials, and installation, warping of materials and other
faults which may occur within 5 years of Practical Completion.

PART II MATERIALS200

201 Acceptable Manufacturers


All glazed doors to be Capral Pty Ltd and Criterion Pty Ltd.

202 External doors


Comply with AS 2688 Timber doors.
A. Timber doors
Size: refer Door Schedule
Thicknesstotal): 40mm
Material: cedar, kiln dried hardwood.
B. Timber frames (jambs)
Thickness: material: cedar, kiln dried hardwood
Rebates: single, double
C. Fly screen doors: metal frame, timber frame,
Manufacturer: Refer to Door Schedule
Screen material: fibreglass, aluminium, stainless steel
D. Security screen doors: metal frame, timber frame
Manufacturer: Refer to Door Schedule
Screen material: fibreglass, aluminium, stainless steel
Comply with AS 5039.
E. Steel frames: pressed steel 1.6mm thick single [or double] rebated fully welded frames with floor
spreader. Provide 8 or 10, 3mm wireties per frame for building into walls and 2 black stops on closing
side. Grout back of frames with cement mortar.
Supply steel frames with shop applied rust inhibitive paint.
F. Fire-rated doors
Refer trade section 08100 FIRE-RATED DOORS AND FRAMES.
G. Solid-core doors
Thickness total: minimum 40mm
Core: particleboard
Face each side: plywood veneer, hardboard, waterproof plywood, metal faced
Edge strips: 10mm hardwood. Total plywood thickness:
H. Acoustic doors
Thickness total: Refer to Door Schedule
Core: mineral, particle board
Edge strips: 10mm hardwood
Acoustic seals: To all sides – Refer to Door Schedule
I. Glazed Timber doors
Timber frame: cedar, hardwood
Glass: comply with AS 1288. Type:
Provide 10mm hardwood frame around glass panel.

203 Internal Doors


Comply with AS 2688.
A. Hollow core, Flush panel
Core: paper, honeycomb, metal
Frame of door: timber with 3 Rails 125mm deep
Face: 4.5mm hardboard, selected veneer. Plywood thickness:
Edge strips: to 2,3 or 4 sides of door, 10mm thick hardwood
Minimum thickness: 35mm,
B. Solid core, Flush panel
Frame of door: timber with top mid and bottom rails
each 50mm deep
Core: medium density particle board
Face: 4.5mm hardboard. Selected veneer, plywood thickness:
Edge strips: to 2, 3 or 4 sides of door, 10mm thick hardwood
Minimum thickness: 35mm,
C. Timber jambs
Material: Selected kiln dried hardwood, cedar,
Thickness of material: Minimum 20mm
Stops: of same material, 10mm
D. Steel jambs
See 202E above.
E. Glazed timber doors
Material: frame of door, kiln dried hardwood or cedar or
Rails and panels: as for frames.
Page 42 of 89 SECTION 08200 DOORS AND DOOR FRAMES
Frame sizes: stiles and rails 130 x 40 bottom rail 220 x 40, all rebated 12mm for glass.
Glazing beads: 12mm thick, shaped, of same material as door frame.
Glass panel: comply with AS 1288.
Lower panel:
F. Timber louvre doors
Manufacturer: Refer to Door Schedule
Material: Cedar
Sizes: each leaf: 2, 3, 4 leafs.
Total opening width.

PART III EXECUTION300

301 Examination
Inspect site conditions. Ensure conditions are satisfactory for installation.
Start of work means total acceptance of conditions.

302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Prepare openings in walls or other structures before installation. Install fixing grounds and inserts as required to
secure frames.

303 Installation of Door Frames


Erect frames plumb and true. Brace as required until surrounding structure is complete. Comply with AS 2689.

304 Installation of Doors


Comply with manufacturer’s instructions and AS 2689. Reject doors which do not comply with AS 2688
Appendix A. Condition doors to average humidity in area prior to hanging.
Align doors to frame for proper fit and uniform clearance at edge and machine for hardware. Seal cut surfaces
after machining.
Provide clearance of 3mm at jambs and heads; 3mm at meeting stiles at pairs of door; 12mm from bottom of
door to top of floor finishing or covering. At thresholds provide 6mm clearance.

305 Installation of Hardware


Refer Schedule of Door Furniture and Hardware. Check deliveries on arrival. Keep items locked until needed.
Assume responsibility for delivered items. Fit accurately and at correct heights, protect with heavy cloth until
completion of project.
Label keys, and hand over to contractor.
Master key locks as instructed.

306 Adjustment and Cleaning


Adjust each door in its frame and ensure silent operation. Oil locks and hinges. Clean all surfaces marked
during the installation of door frames, doors and hardware.

307 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES


Location/Description Details
General This is to be read in conjunction with the Door Schedule and Door Hardware Schedule – see
Appendix.
All external doors are to have weather seals to manufacturers recommendations.
Supply and install integrated acoustic rubber seals to all aluminium door frames of all offices
and meeting rooms.
Where doors are scheduled as 3000mm high, provide 4 No. Hinges.
Where closers are scheduled on glazed entry doors, drop plate to door clcoser must be
installed.
Where Steel Frames are scheduled they are to have 3 hinges and rubber buffers to all door
openings.
Where rooms require high acoustic rating, supply and install Raven RP 8 and 10 acoustic
sealsa as specified.
All external doors are to have trehsold plates and weather seals.
All door glazing to be 10.38mm thick minimum heat toughened glazing.
Painting Refer Section 09910 Painting
All strike recess’ to timber doors are to be fully painted prior to installation of strike plate.
Strike Box All aluminium door frames to have ‘strike boxes’ installed.
Door Stops Door stops to be provided to all internal doors.
Satin Chrome ½ round door stops where appropriate.
Page 43 of 89 SECTION 08200 DOORS AND DOOR FRAMES
General Doors to Supply and install Satin Chrome lockwood level furniture with key lock – refer to door
Offices/ Meeting hardware schedule for details.
Rooms etc. Provide proprietary ravens seals to all door jambs and morticed drop seals to both swing and
sliding doors – refer to door schedule for details.
Provide glazed viewing panels to doors where noted on the drawings/door schedule.
Dimensions as per drawings.
Door leaf sizes as scheduled, to BCA requirements.
Internal Frames Aluminium Door frames to be Capral 225 series (50mm styles to achieve AS1428.1
contrasting colour compliance). Door frames shall be powdercoated aluminium finish as
scheduled.
Aluminium Door Supply and install proprietary steel stud partition wall system ‘Capral’ or similar approved
Frames (internal) including all partition trims, flat plate skirting, shadowline head track etc.
Powdercoat finish to frame and paint finish to door leaf as scheduled.
All aluminium Door and windows frames to be Capral 225 series so as to achieve AS1428.1-
2009 compliant colour contrast between door and adjacent frame.
Where noted in the door schedule, provide aluminium framed Capral 225 series and 45mm
solidcore flush MDF faced (as indicated in door schedule).
Powdercoat finish to frame and paint finish to door leaf as scheduled.
All glazing to aluminium framed glazed doors (internal and external) to be 10.38mm clear heat
toughened glazing to comply with AS1288.
Sliding door Supply and install top hung surface mounted Criterion Niagra sliding doors in accordance with
Manufacturers specifications. Provide end jamb closing pocket to achieve an acoustic seal.
Master Key Refer Section 08710 – Door Hardware
Builder required to allow to coordinate Masterkey hierarchy system.

END OF SECTION

Page 44 of 89
SECTION 08520 METAL WINDOWS AND GLAZING

PART I GENERAL

101 Scope
Design, engineer, supply and install a complete glazed system of windows, doors and screens, including but
not limited to:
Material type
Finish type
Openings
Glass types
Glazing methods
Insect screens

102 Related Work


Co-ordinate and co-operate with the tradesmen preparing walls and frames to accept windows, including
casting in of anchors.

103 Quality Assurance


Manufacturer qualifications: not less than 10 years continuous experience in the manufacture of the product
types specified.
Installer qualifications: installer is to have not less than 5 years continuous experience in the erection of
specified material.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.0 2002 General principles. Plus 5 Amdts, 2003 – 2011.
1170.1 2002 Permanent, imposed and other actions. Plus 2 Amdts, 2005 –
2009.
1170.2 2011 Wind actions.
1170.3 2003 Snow and ice actions. Plus 1 Amdt, 2007.
1170.4 2007 Earthquake actions in Australia.
There are several Supplements and Amdts, 2002 – 2011.
AS 1231 2000 Aluminium and aluminium alloys – Anodic oxidation coatings.
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS 2047 1999 Windows in buildings - Selection and installation. Plus 2 Amdts, 2001.
AS 3715 2002 Metal finishing - Thermoset powder coating for architectural applications of
aluminium and aluminium alloys.
AS 4145.2 2008 Locksets and hardware for doors and windows – Mechanical locksets for doors and
windows in buildings. Plus 2 Amdts, 2009.
HB 125 2007 The glass and glazing handbook.
Comply with relevant authority's requirement for fire-rated installation.

105 Submissions Required Prior to Fabrication


A. Complete system description including the following information:
Names of manufacturers of products.
Names, addresses and telephone numbers of local representatives for products.
Types, model numbers and names of products, and indication whether products are "off the shelf" or
custom fabricated. Include specific information on finishes - thicknesses, patented process name,
process description and test data.
Detailed information on products manufactured specifically for this project.
Detailed system description including standard details and manufacturer's literature; and large-scale
details of specially fabricated products.
B. Statement that the proposed system meet(s) the regulatory requirements, thermal, aesthetic and
waterproofing criteria and wind loading, construction, glazing and warranty requirements specified;
noting in detail exceptions.
C. Shop Drawings: refer DOCUMENT 00800 SUPPLEMENTARY CONDITIONS OF CONTRACT, clause
27. Provide Shop Drawings showing the following information where appropriate to the items:
Layout (sectional plan and elevation of complete assembly).
Full size section of members.
Methods of assembly, type and location of exposed screws.
Methods of glazing.
Methods of installation, including fixings, anchorage, caulking, flashings.
Provision for expansion (thermal).
Junctions and trim to adjoining surfaces.
Fittings and accessories.
D. Engineer's calculations on wind loading.
E. Sealants: submit manufacturer's product specifications, handling, installation/curing instructions, and
performance tested data sheets for each elastomeric product required. Submit certificate test reports for
Page 45 of 89 SECTION 08520 METAL WINDOWS AND GLAZING
elastomeric sealants on aged performance as specified, including hardness, stain resistance, adhesion,
cohesion or tensile strength, elongation, low-temperature flexibility, compression set, modulus of
elasticity, water absorption, and resistance (ageing, weight loss, deterioration) and exposure to heat,
ozone and ultraviolet light.

106 Delivery, Handling and Storage


Handle materials with care. Do not store on site. Install directly in place. Store sealants as instructed by
manufacturer.

107 Warranty
Provide to the proprietor a warranty, counter-signed by the installer, on the whole of the installation, which
states that work will remain intact, waterproof and fully operational for the period of not less than 9 years after
date of Practical Completion.

PART II MATERIALS

201 Acceptable Manufacturers


The following manufacturers of window frames are acceptable:
Capral

202 Materials
Window frames: extruded aluminium components manufactured from aluminium alloy 6063, temper T5 or T6.
Match components detailed on drawings or an alternative approved in writing by the architect.
Glass: refer clause 206.
Insect screens:

203 Structural Criteria


A. Adopt Terrain Category:
Refer AS/NZS 1170.
B. Wind loading: design:
1. Glazing and frame assemblies to suit the static and dynamic wind forces as indicated on the
tables in the AS/NZS 1170.
2. Structural members of glazed units of such strength that when tested at the specified design
wind values they do not deflect by an amount greater than span/240 and do not cause
permanent deflection.
3. Fix members so that the above loading is generated in the members without stress causing
failure or movement becoming evident at any joint.
C. Movement: permit free and noiseless movement of the components due to thermal effects, structural
effect, wind pressure, effect of dead loads, without strain to glass, without buckling of components and
without excessive stress to members or assemblies.
D. Contact with other materials: coat metal surfaces in contact with mortar, concrete, plaster, masonry,
wet-application of fire-proofing and absorbent materials with an anti-galvanic, moisture barrier material.
Isolate, with inert material, dissimilar metals for the prevention of electrolytic action and corrosion.
E. Distortion: design the glazed assembly to minimise visual distortion of reflected images.

204 Detail Design Provisions


A. General: the architect's drawings are to be considered essentially schematic except for profiles of
exposed surfaces and panel arrangement where indicated. If, in the opinion of the builder a change of
profile is required in order to meet the specification, arrange through the architect for a review of the
condition. Design the assembly, reinforcing and anchorage to suit each specified condition in an
acceptable manner complying with the requirements specified herein.
B. Tolerances: design frames to accommodate building tolerances, and when completed, within the
following tolerances:
1. Deviation from plumb, level or dimensioned angle within 3mm per 3.5m of length of member, or
6mm in total run in line.
2. Deviation from theoretical position on plan or elevation, including deviation from plumb, level or
dimensioned angle not to exceed 9mm total at location.
3. Change in deviation not to exceed 3mm for 3.5m run in direction.

205 Finish
Anodising or Polyester Powder Coat.
Anodising:
Metal of windows, doors and shop fronts anodised to selected colour.
Pre-treat and apply anodising by applicators approved by the architect.
Minimum coating thickness of 25 microns subjected to random testing after installation. Remove and replace
non-conforming material.
Comply with requirements of AS 1231.
Polyester powder coat:
Polyester powdercoated, to colour approved by the architect and by the manufacturer of the powder material,
to metal of windows, doors and shop fronts.
Page 46 of 89 SECTION 08520 METAL WINDOWS AND GLAZING
Perform pre-treatment and application of powder coating by applicators approved by the architect and by the
manufacturer of the powder material.
Minimum coating thickness of 50 microns subjected to random testing after installation. non-conforming
material will be removed and made good by the builder.
Comply with requirements of AS 3715.

206 Glass
A. Glass materials for external use:
B. Glass material for internal use:
C. Other glass for:
D. Calculations: calculate glass sizes and thicknesses in accordance with Standards, and fixing devices
and connections to structure in accordance with engineer's computations where applicable.
E. Double glazing:

207 Sealants and Accessory Materials


A. Provide non-structural external weatherproofing sealants of low modulus neutral curing silicone rubber
compounds by approved manufacturer.
B. Generally comply with AS 1288, Part 2, Section 6 or 8. Supply spacer gaskets, glazing tapes and setting
blocks compatible with sealants, which do not contribute to sealant colour change or affect the sealants
adhesion to substrates when exposed to ultraviolet light.
Prior to application, samples of materials receiving the silicone, including elastomeric sealants are to be
evaluated by the silicone sealant manufacturer for compatibility and primer selection. Clearly identify the
submitted materials as to manufacturer and product number.
Silicone sealants generally will be clear in colour.
C. Interior sealers: acrylic-emulsion or latex-rubber-modified acrylic emulsion sealant compound,
permanently flexible, non-staining and non-bleeding; recommended by manufacturer for protected
exterior exposure and general interior exposure.
D. Joint primer/sealer: provide type of joint primer/sealer as recommended by sealant manufacturer to suit
each surface.
E. Bond breaker tape: polyethylene tape or other plastic as recommended by sealant manufacturer to be
applied to sealant-contact surfaces where bond to substrate or joint filler is to be avoided for proper
performance of sealant. Provide self-adhesive tape where applicable.
F. Sealant backer rod: compressible rod stock of polyethylene foam, polyethylene jacketed polyurethane
foam, butyl rubber foam, neoprene foam or other flexible permanent, durable non-absorbent material as
recommended by sealant manufacturer for compatibility with sealant.
G. Glazing tape: polyisobutylene tape of type, thickness and width as recommended by glass manufacturer
and architect.
H. Exposed screws: countersunk type, anodised aluminium or non-magnetic stainless steel evenly and
neatly located in an approved manner. Exposed fasteners: finished to match aluminium.

208 Fabrication
Comply with AS 2047.
Framing system: fabricate from extrusions to profiles shown on approved Shop Drawings.
Form junctions so that no fixings, such as pins, screws, pressure indentations and the like are visible on
exposed faces. Show on Shop Drawings fixings which will be exposed. Cut edges, drill holes, rivet joints and
clean flat sheets, neat, free from burrs and indentations. Remove sharp edges without excessive deformation.
Fit mitred joints accurately to a fine hairline.
Pre-assemble and match mark before delivery.

209 Dissimilar Metals


In moist environments, prevent totally contact between dissimilar metals (any metals).
This instruction takes priority over any drawing, detail or instruction and will prevent cathodic reaction between
the metals.
Refer this instruction to the structural engineer.

PART III EXECUTION

301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Perform rectification required before delivery of materials.
Start of work means total acceptance of conditions.

302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.

Page 47 of 89 SECTION 08520 METAL WINDOWS AND GLAZING


303 Frame Anchorage
Fabricator is required to supply the anchorage devices to the builder for building in by others and check that
devices are located as required to suit the requirements of window frame fabrication for positive and permanent
fixing.
Insulation: isolate dissimilar metals at interfaces with bitumen based or nylon shim materials to prevent galvanic
action.
Make good concrete or masonry damaged during the installation of masonry anchors at no cost to the
proprietor.

304 Frame Installation


Comply with AS 2047.

305 Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal
expansion of glass, the metal framing and spandrels.

306 Preparation for Sealants


Joint preparation sealants: clean joint surfaces immediately before installation of sealant or caulking compound.
Remove dirt, insecure coatings, moisture and other substances which could interfere with bond of sealant or
caulking compound. Etch concrete and masonry joint surfaces as recommended by sealant manufacturer.
Roughen vitreous and glazed joint surfaces if recommended by sealant manufacturer.
Prime or seal joint surfaces where indicated, and where recommended by sealant manufacturer. Do not allow
primer/sealer to spill or migrate on to adjoining surfaces.

307 Installation of Sealants


A. Install bond breaker tape where required by manufacturer's recommendations to ensure that
elastomeric sealants will perform properly.
B. Employ only proven installation techniques, which will ensure that sealants are deposited in uniform
continuous ribbons without gaps or air pockets, with complete "wetting" of joint bond surfaces equally on
opposite sides. Except as otherwise indicated, fill sealant rabbet to a slightly concave surface slightly
below adjoining surfaces.
C. Install sealant to depths as recommended by sealant manufacturer.
D. Cure sealants and caulking compounds in compliance with manufacturer's instructions and
recommendations, to obtain high early bond strength internal cohesive strength and surface durability.
Advise architect of procedures required for cure and protection of joint sealers during construction
period, so that they will be without deterioration or damage (other than normal wear and weathering) at
time of Practical Completion.
E. Remove excess caulking compound and sealant and leave surfaces neat, smooth and clean, without
smears on surrounding work. Tool joints where recommended by manufacturer or where required.
Remove cartons and debris from site as the work progresses.

308 Insect Screens


N/A.

309 Protection
A. Framing system: protect metal surfaces as necessary during erection. Finish surfaces free from
mechanical imperfections such as scratches, scrapes, dents, spots, stains and streaks.
B. Glass: protect glass from breakage immediately upon installation and until Practical Completion.
Remove and replace glass and metal panels which are broken, cracked, abraded, chipped or damaged
in other ways, before, during or after installation, at no additional cost to proprietor.
C. Be responsible for breakage and damage to installation until Practical Completion.

310 Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass, frames,
hardware and other finished surfaces immediately upon installation of glazing for each light.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.

311 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
General All glazing used on the project is to meet the requirements of the BCA, Glazing Code and
‘Viridian’ standards. All toughening required to glazing as a result of the Thermal Assessment
is to be included in the tender price.
Thermal Assessment to be included in Contractor’s price and to be undertaken by Contractor
prior to installation of glazing.
Supply and install all glazing to AS1288 and AS2047.
Page 48 of 89 SECTION 08520 METAL WINDOWS AND GLAZING
All external openings (doors & operable windows) must be fitted with draft seals to all sides
of openings, to be ‘Raven’.
Include all mullions, transoms, slotted sub-sills, sub-head, sub-jamb, head flashing, caulking
etc. as detailed and recommended by Capral.
All silicon and gaskets to be black
Visual Consistancy All façade glazing panes must be matching Colour, Visual Light Transmission (VLT),
Thickness, to achieve strict visual consistency, unless specifically noted otherwise.
It is the tenderer/glaziers responsibility to review, confirm and allow for consistency of glazing
at time of tender.
Internal Glazing Supply and install Viridian Clear Glass – minimum 10.38mm thick to all glazed partitions and
doors.
Provide Laminated or toughened glass as required to comply with AS1288
Silicon Butt joints typical to glazing– refer internal elevations for locations.
Glazing frames to be proprietary system to match steel stud partition framing “Capral” -
System 400 Narrowline Series (depending on situation) similar approved equivalent.
All aluminium Door frames to be Capral – 215 Series Suit (50mm exposed face) so as to
achieve AS1428.1-2009 compliant colour contrast between door and adjacent frame.
All aluminium frames to natural anodised aluminium (to match existing).
Film Supply and install 3M “Haze” film decal as scheduled and noted on the drawings.
Supply and install forsting or feature printed pattern to film as scheduled – refer Internal
Colour and Finishes Schedule (see Appendix.)
Electronic access Where electronic access control (swipe cards) are specified, install double mullion to door
control jamp (latch side) to accommodate swipe card an light switch installation to frame.
Visual Indicators All ground level glazing including all doors, windows and side lights without a chair rail are to
have a solid contrasting line applied to the full extent of the glazing.
Solid contrasting line is to be 75mm high with the lower edge between 900mm and 1000mm
above FFL.
Solid contrasting line to be 30% luminance contrast when viewed against the floor or surface
within 2m of the glazing on the opposite side.

END OF SECTION

Page 49 of 89
SECTION 08710 DOOR HARDWARE

PART I GENERAL100

101 Scope
Supply and install door hardware including but not limited to:
Wall mounted grilles for ventilation and other purposes.
Hinges.
Pivots.
Latches.
Locks.
Door holders.
Push plates.

102 Related Work


Co-ordinate and co-operate with the following trades:
Floor construction Painting
Wall construction Doors and door frames
Ceiling construction Fire-rated door and frames
Concrete Roller shutter doors
Carpentry Folding doors and grilles
Metal finishing Automatic sliding door assemblies

103 Quality Assurance


Work of this trade section is to be performed by experienced craftsmen familiar with the quality required in this
class of work.
Where 5 or more items of a similar product are required, construct a prototype, full size. Finish the prototype in
every respect. When approved by the architect, this sample remains part of the work and becomes the
standard for the remaining work.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS 1909 1984 (Obsolescent) Installation of timber doorsets.
AS 2688 1984 (Obsolescent) Timber doors.
AS 2689 1984 (Obsolescent) Timber doorsets.
AS 4145 Locksets.
4145.2 2008 Mechanical locksets for doors in buildings.
There are 3 other parts, 2001 - 2008 plus 2 Amdts 2009.
AS 4178 1994 Electromagnetic door holders.
Comply with requirements of statutory and local authorities.

105 Delivery, Handling and Storage


Deliver items to site in original packaging, each clearly labelled for the relevant door by door number.

106 Warranty
Provide to the proprietor a warranty covering faulty materials and installation for 5 years from date of Practical
Completion.

PART II MATERIALS200

201 Manufacturers
Lockwood

202 Hardware Items


Master key systems: refer schedule provided by manufacturer.
Finish:
Door stops:

203 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required for a
complete installation.
Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the item is
to be secured. Refer to architect if in doubt.

Page 50 of 89 SECTION 08710 DOOR HARDWARE


PART III EXECUTION

301 Examination
Examine the materials to which door hardware is to be fixed.
Ensure conditions are satisfactory for installation.
Start of work means total acceptance of conditions.

302 Preparation
Remove hardware from surfaces to be painted. Replace when paint is dry.

303 Installation
Comply throughout with the written instructions of manufacturer.

304 Keys
Supply duplicate labelled keys (2No of.) for each lock. Provide plastic tags for each key.
Arrange with architect for location of a key cupboard.
Fit cupboard with hooks for each key with room names or numbers.
Install cupboard where instructed.

305 Testing
Check each key in relevant lock for satisfactory operation. Replace defective keys or locks.
Clean the materials installed.
Remove construction locks.

306 Co-ordination
Before finalising hardware order, review with security sub-contractor work related to reed switches, electric
locks/strikes etc. Generally such items will be supplied by the security contractors and fitted to doors and frame
by the builder.

PART IV DETAILS

Location/Description Details
General This section is to be read in conjunction with:
 Architectural Door Schedule and
 Door Hardware Schedule
All door hardware to be ‘heavy duty’, commercial grade.
'Lockwood' Symphony hardware brass furniture or equivalent
Door hardware to meet Section 13 and 13.5 of as1428.1 -2009
All Offices, Meeting Rooms and other rooms require high acoustic rating, supply and install
Raven acoustic seals aspsecified.
Where doors are scheduled as 2700mm high, provide 4 No. Hinges.
Master Key Builder required to allow to coordinate Masterkey hierarchy system.
Builder to provide a tabulated schedule of all locks and keys to the Architect & Project
Manager for confirmation of keying hierarchy 2 weeks prior to final date required for ordering
of cylinders and locks.
All doors to be master keyed to be ‘Bi-Locked’ master key system unless noted otherwise.
Doors with electronic access control to have similar master key override.

END OF DOCUMENT

Page 51 of 89 SECTION 08710 DOOR HARDWARE


SECTION 08800 GLASS AND GLAZING

PART I GENERAL100

101 Scope
Supply and install a complete system of glass, glazing and sealants including but not limited to:
Glass, clear float
spandrel
translucent patterned
wire reinforced
Glass, laminated
two or more laminations
inter-layer
Glass, toughened and unframed glass assemblies
Glass, tinted, heat reflecting, mirrored
Glass, sloping
Glazing plastics, polycarbonate, etc.
Glazing bars
Glazing systems - structural glass
Glazing beads, strips
Sealants and related materials
Film applied to glass surface

102 Related Work


Co-ordinate and co-operate with the following trades:
Concrete
Masonry
Structural steel
Roof flashings, etc.
Electrical
Security
Fireproofing and fire services
Timber windows and frames

103 Quality Assurance


A. Manufacturer qualifications: not less than ten (10) years continuous experience in the manufacture of
the product types specified.
B. Installer qualifications: installer is to have not less than five (5) years continuous experience in the
erection of specified material.
C. Testing agency qualifications generally: Perform tests, where required, by a NATA Laboratory or by
CSIRO Division of Building Research. Tests performed by recognised overseas testing laboratories
certified by the American Society of Testing Materials (ASTM) may be submitted and will be considered
in evaluation of the products and systems proposed, but such tests will not relieve the builder from
responsibility for providing tests from an approved testing agency.
D. Take responsibility for providing the trades of such Sections with complete information on the materials
and equipment to be installed, the critical dimensions of such work, and other data affecting the work of
the trades identified.
Ensure subcontractors and vendors co-operate in the proper sequence and fit of the work.
E. Review subcontractor’s shop drawings and obtain architect’s approval in writing. Refer DOCUMENT
00800, clause 27.
F. Take care with tolerances and dimensional verifications.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.0 2002 General principles. Plus 5 Amdts, 2003 – 2011.
1170.1 2002 Permanent, imposed and other actions. Plus 2 Amdts, 2005 –
2009.
1170.2 2011 Wind actions.
There are 2 other parts, several Supplements and Amdts, 2002 – 2011.
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS/NZS 2208 1996 Safety glazing materials in buildings. Plus 1 Amdt, 1999.
AS/NZS 2343 1997 Bullet-resistant panels and elements.
AS 4145.2 2008 Locksets and hardware for doors and windows – Mechanical locksets for doors and
windows in buildings. Plus 1 Amdt, 2009.
AS 4666 2012 Insulating glass units
HB 125 2007 The glass and glazing handbook.
Comply with relevant authority's requirement for fire-rated installation.

Page 52 of 89 SECTION 08800 GLASS AND GLAZING


105 Submissions Required Prior to Purchase and Fabrication
A. Complete system description including the following information:
Names of manufacturers of products.
Names, addresses and telephone numbers of local representatives for products.
Types, model numbers and names of products, and indication whether products are "off the shelf" or
custom fabricated. Include specific information on finishes - thicknesses, patented process
name, process description and test data.
Detailed information on products manufactured specifically for this project. Detailed system description
including standard details and manufacturer's literature; and large-scale details of specially fabricated
products.
B. Statement that the proposed system(s) meet(s) the regulatory requirements, thermal, aesthetic and
waterproofing criteria and wind loading, construction, glazing and warranty requirements specified;
noting in detail exceptions.
C. Shop Drawings: pursuant to DOCUMENT 00800, clause 27 and the provisions of this document, provide
the shop drawings showing the following information where appropriate to the items:
1. Layout (sectional plan and elevation of complete assembly).
2. Full size section of members.
3. Methods of assembly.
4. Methods of glazing.
5. Methods of installation, including fixings, anchorage, caulking, flashings.
6. Provision for expansion (thermal).
7. Junctions and trim to adjoining surfaces.
8. Fittings and accessories.
D. Engineer's calculations on wind loading.
E. Sealants: submit manufacturer's product specifications, handling, installation/curing instructions, and
performance tested data sheets for each elastomeric product required. Submit certificate test reports for
elastomeric sealants on aged performance as specified, including hardness, stain resistance, adhesion,
cohesion or tensile strength, elongation, low-temperature flexibility, compression set, modulus of
elasticity, water absorption, and resistance (ageing, weight loss, deterioration) and heat and exposure to
ozone and ultraviolet light.

106 Delivery, Handling and Storage


Handle materials with care. Do not store on site. Install directly in place. Store sealants as instructed by
manufacturer.

107 Warranty
In addition to the warranty requirements of the General Conditions of Contract, provide the following:
A. Warranty: provide glass manufacturer's written warranty, agreeing to, within specified warranty period,
furnish freight paid to project site, replacement units for glass units which have defective hermetic seals
(excluding that due to glass breakage), defined to include intrusion of moisture or dirt, internal
condensation at temperatures above -2°C, deterioration of internal glass coatings, and other visual
evidence of seal failure or performance failure; provided manufacturer's instructions for handling,
installation, protection and maintenance have been adhered to during warranty period.
B. Warranty period is 10 years after date of installation and not less than 9 years after date of Practical
Completion.

PART II MATERIALS200

201 Acceptable Manufacturers


Viridian

202 Structural Criteria


A. Adopt terrain category:
Refer AS/NZS 1170.
B. Wind loading: design glazing and frame assemblies to suit the static and dynamic wind forces as
indicated on the tables in the AS/NZS 1170. Structural members of glazed units: of such strength that
they will not deflect by an amount greater than span/240 without causing permanent deflection when
tested at the specified design wind values. Fix members so that the above loading is generated in the
members without sufficient stress to cause failure or movement becoming evident at any joint.
C. Distortion: design the glazed assembly and erect to minimise visual distortion of reflected images.

203 Selection of Glass and Glazing Materials


Refer to detailed parts and sections of AS 1288.
Part 1 deals with the selection of type and thickness of glass.
Part 3 with unframed toughened glass assemblies.
Note particularly:
Part 1, Section 4, Human Impact Safety Requirements, AS/NZS 2208.
Part 1, Section 3, Non-Vertical Situations.
Part 2, Glazing techniques. Choose the method directly from the eight sections of this part of the Standard.

Page 53 of 89 SECTION 08800 GLASS AND GLAZING


204 Glass Materials - Aesthetic Criteria
Refer Finishes Schedule

205 Sealants and Accessory Materials


A. Comply with AS 1288. Refer the appropriate Trade Section, and comply with requirements stated.
B. For timber frames, use linseed oil glazing putty.
C. For metal frames:
1. Non-structural external weatherproofing sealants: low modulus neutral curing silicone rubber
compounds of approved manufacture.
2.Generally comply with AS 1288. Spacer gaskets, glazing tapes and setting blocks: compatible with
sealants, which do not contribute to sealant colour change or affect the sealants adhesion to
substrates when exposed to ultraviolet light.
Evaluate prior to application, samples of materials receiving the silicone, including elastomeric
sealants for compatibility and primer selection. Submit materials clearly identified as to
manufacturer and product number.
Silicone sealants generally: clear in colour.
3. Interior Sealers: acrylic-emulsion or latex-rubber-modified acrylic-emulsion sealant compound,
permanently flexible, non-staining and non-bleeding; recommended by manufacturer for
protected exterior exposure and general interior exposure.
4. Joint Primer/Sealer: provide type of joint primer/sealer recommended by sealant manufacturer for
joint surfaces to be primed or sealed.
5. Bond Breaker Tape: polyethylene tape or other plastic as recommended by sealant manufacturer
to be applied to sealant-contact surfaces where bond to substrate or joint filler is to be avoided
for proper performance of sealant. Provide self-adhesive tape where applicable.
6. Sealant Backer Rod: compressible rod stock of polyethylene foam, polyethylene jacketed
polyurethane foam, butyl rubber foam, neoprene foam or other permanently flexible, durable non-
absorptive material as recommended by sealant manufacturer for compatibility with sealant.
7. Glazing Tape: polyisobutylene tape of type, thickness and width as recommended by glass
manufacturer and architect.
8. Exposed fixings: countersunk type, anodised aluminium or non-magnetic stainless steel evenly
and neatly located in an approved manner. Exposed fasteners: finished to match aluminium.
Show on shop drawings or discuss with the architect before fabrication and delivery of any fixings
which will be exposed.

PART III EXECUTION300

301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Arrange for rectification required before delivery of materials.
Start of work means total acceptance of conditions.

302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.

303 Preparation for Sealants


Joint preparation sealants: clean joint surfaces immediately before installation of sealant or caulking compound.
Remove dirt, insecure coatings, moisture and other substances which could interfere with bond of sealant or
caulking compound. Etch concrete and masonry joint surfaces as recommended by sealant manufacturer.
Roughen vitreous and glazed joint surfaces if recommended by sealant manufacturer and comply with his
instructions.
Prime or seal joint surfaces where indicated, and where recommended by sealant manufacturer. Do not allow
primer/sealer to spill or migrate on to adjoining surfaces.

304 Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal
expansion of glass, the metal framing and spandrels.

305 Installation of Sealants


A. Install bond breaker tape where required by manufacturer's recommendations to ensure that
elastomeric sealants will perform properly.
B. Employ proven installation techniques, which will ensure that sealants are deposited in uniform
continuous ribbons without gaps or air pockets, with complete "wetting" of joint bond surfaces equally on
opposite sides. Except as otherwise indicated, fill sealant rabbet to a slightly concave surface slightly
below adjoining surfaces.
C. Install sealant to depths as recommended by sealant manufacturer.
D. Cure sealants and caulking compounds in compliance with manufacturer's instructions and
recommendations, to obtain high early bond strength, internal cohesive strength and surface durability.
Page 54 of 89 SECTION 08800 GLASS AND GLAZING
Advise architect of procedures required for cure and protection of joint sealers during construction
period, so that they will be without deterioration or damage (other than normal wear and weathering) at
time of Practical Completion.
E. Remove excess caulking compound and sealant and leave surfaces neat, smooth and clean, without
smears on surrounding work. Tool joints where recommended by manufacturer or where required.
Remove cartons and debris from site as the work progresses.

306 Field Quality Control


Arrange for visits to the site by the supplier's approved technical representative of each component. Such visits
are to occur at the start of and during the first stages of installations and towards the end of installations.
Follow instructions of the technical representatives. Call in the architect where appropriate for resolution of
problems or difficulties.

307 Protection
A. Framing system: protect metal surfaces as necessary during erection.
B. Finish surfaces free from mechanical imperfections such as scratches, scrapes, dents, spots, stains and
streaks.
C. Glass: protect glass from breakage immediately upon installation until Practical Completion. Remove
and replace glass and metal panels which are broken, cracked, abraded, chipped or damaged in other
ways, before, during or after installation, at no additional cost to the Proprietor.
D. Be responsible for breakage and damage to installation until Practical Completion.

308 Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass, frames,
hardware and other finished surfaces immediately upon completion of each panel of glazing.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.

309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
General Any glazing pane thicknesses are provided as a guide only. Final thickness, structural,
installation requirements to achieve compliance with the BCA and Australian Standards
are the responsibility of the builder and glazier.
Minimum thickness must be 10.38mm to all spaces.
All glazing used on the project is to meet the requirements of the BCA, Glazing Code
and ‘Viridian’ standards. All toughening required to glazing as a result of the Thermal
Assessment is to be included in the tender price.
Thermal Assessment to be included in Contractor’s price and to be undertaken by
Contractor prior to installation of glazing.
Supply and install all glazing to AS1288 and AS2047.
Include all mullions, transoms, slotted sub-sills, sub-head, sub-jamb, head flashing,
caulking etc. as detailed and recommended by Capral.
All silicon and gaskets to be black
Visual Consistancy All façade glazing panes must be matching Colour, Visual Light Transmission (VLT),
Thickness, to achieve strict visual consistency, unless specifically noted otherwise.
It is the tenderer/glaziers responsibility to review, confirm and allow for consistency of
glazing at time of tender.
Glazing All glass is to be ‘clear‘ glazing and achieve a minimum Visual Light Transmission
(VLT) of 71%
Visual Indicators All ground level glazing including all doors, windows and side lights without a chair rail
are to have a solid contrasting line applied to the full extent of the glazing.
Solid contrasting line is to be 75mm high with the lower edge between 900mm and
1000mm above FFL.
Solid contrasting line to be 30% luminance contrast when viewed against the floor or
surface within 2m of the glazing on the opposite side.

END OF SECTION

Page 55 of 89 SECTION 08800 GLASS AND GLAZING


Page 56 of 89 SECTION 08800 GLASS AND GLAZING
SECTION 08815 GLASS SPLASHBACKS

PART I GENERAL

101 Scope
Supply and install glass splashbacks including, but not limited to:
Measure area to be covered
Prepare area to be covered
Clean surface
Apply colour to glass
Ensure adequate fixing of glass.

102 Related Work


Co-ordinate and co-operate with the following trades:
Wall framing
Wall finishing – Plasterboard
Manufactured casework
Glazing
Ceramic tile
Electrical

103 Quality Assurance


A. Suppliers and installers are required to be widely experienced in the class of work required by this
Specification.
B. Evidence of similar work on projects is required, providing names and addresses of work to facilitate
inspection and approval of qualifications.
C. Submissions required before ordering materials:
1. Product data including description of materials proposed and samples of each.
2. Description of laying and/or installation methods.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
Comply with requirements of statutory and local authorities.

105 Delivery and Handling


Handle materials with care. Install directly in place. Do not store on site. Store sealants as instructed by
manufacturer.

106 Warranty
Provide to the proprietor a warranty covering satisfactory performance of the complete installation for 7 years
from the date of Practical Completion.

PART II MATERIALS200

201 Acceptable Manufacturers

202 Materials
Glass: 6mm toughened. Clear or low iron glass. Form cut outs as required for power outlets.
Background: plasterboard or fibre-cement fixed to bricks.
Colour: solid colour, 2 pack polyurethane or other paint system applied by the manufacturer of the splashback.
Refer to architect for selection of colour.
Sealant: neutral curing silicone rubber around entire perimeter of glass panel.
Fibre cement (if used): 4.5 or 6.0mm secured to masonry as recommended by manufacturer.

PART III EXECUTION

301 Examination
Visit the site and inspect conditions.
Compare conditions with the data shown on drawings.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.
Measure the areas to be covered with splashback, including cut-outs for power outlets etc. Advise architect if
walls are found to be out of square with each other or if the wall or substrate is not flat (flat means less than
4mm variation in surface).

Page 57 of 89 SECTION 08815 GLASS SPLASHBACKS


302 Wall Surface To Be Covered
Clean the surface thoroughly.
Ensure a dry surface which will suit silicone rubber and double-sided adhesive tape.

303 Adjacent Surfaces


Remove obstructions from adjacent surfaces which might prevent handling of glass into place.
Clean surfaces.
Ensure that painted surface is thoroughly dry and clean.

304 Secure The Glass


Apply double-sided tape to back of glass, if used.
Apply a bead of silicone rubber to entire perimeter of glass. Leave no gaps. Press into place and maintain
pressure until fully set.

305 Cleaning
Clean entire area of glass and adjacent finishes.

306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
General Refer to Internal Finishes Schedule for details
Glazing to splashback to be Starphire Colour (true clear)

END OF SECTION

Page 58 of 89
SECTION 09250 PLASTERBOARD

PART I GENERAL100

101 Scope
Supply and install a complete installation of plasterboard including but not limited to:
Plasterboard
Plasterglass
Flexible plasterboard, 6.5mm thick in 2 layers
Lining of concrete and masonry walls
Lining of steel stud walls
Lining with water-resistant plasterboard
Ceilings, drop walls, bulkheads
Fire-rated plasterboard walls/ceilings
Cornices.

102 Related Work


Co-ordinate and co-operate with the following trades:
Masonry walls Electrical
Stud walls Other:
Suspended ceilings

103 Quality Assurance


Prototype: at a location selected by the architect, construct a complete prototypical installation of plasterboard
on each different substrate.
Each sample, full height by 3600 wide includes elements required by this specification and finish in every
respect. When approved by the architect, this sample will remain part of the work and becomes the standard
for the remaining work.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2589 2007 Gypsum linings - Application and finishing.
HB 161 2005 Guide to plastering

105 Delivery, Handling and Storage


Deliver manufactured materials in bundles and packages bearing the name of the manufacturer and the brand.
Handle with care. Remove damaged materials from the site. Protect stored materials from damage and damp,
or materials which may cause deterioration.

106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 5 years from
the date of Practical Completion. The warranty includes a statement that the whole of the work has been
carried out in accordance with relevant Australian Standards and Codes and manufacturer's instructions in
effect at the time of installation.

PART II MATERIALS

201 Acceptable Manufacturers


CSR
Boral

202 Materials
Supply materials in accordance with material supplier's recommendations for each application.

PART III EXECUTION

301 Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of materials to
site. Rectify any discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.

302 Preparation
A. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
B. Co-ordinate with and ensure preparatory work by other trades is done prior to commencement of work;
failure to do so will involve removal of plasterboard and immediate rectification.

Page 59 of 89 SECTION 09250 PLASTERBOARD


C. Arrange for provision of additional stud, nogging, trimmed openings, boxed studs, fixing grounds, etc.,
required for satisfactory execution of the work of this trade including penetrations through plasterboard
for services. Co-operate in installation of frames, duct openings, etc.
D. Space enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in
space is completed and nominally dry.

303 Layout and Tolerances


A. Check dimensions of areas and surfaces to which material is applied before installation begins.
B. Measure each area and establish layout pattern.
C. All finished work is to be within + 2mm of the sizes shown on the relevant drawings.

304 Installation - General


A. Comply with manufacturer's installation instructions. Anchor and fasten materials and components to
comply with ratings and performance requirements, and to comply with governing local regulations.
Comply with appropriate Australian Standard.
B. Take care of and protect surrounding work, including other finishes, equipment and components, during
installation. Provide protective covering where necessary.

305 Installation Particulars

306 Finishing Details


General: apply treatment at board joints (both directions), flanges of trim accessories, penetration, fasteners,
heads, surface defects and elsewhere as required to prepare work for decoration. Pre-fill open joints and
rounded or bevelled edges, using type of compound recommended by manufacturer.
Apply fibreglass joint tape at joints between boards, where a trim accessory is indicated, or where extra
strength is required.

307 Protection
Protect finished work. Make good damage in every respect at no additional cost to the proprietor, and without
delay to job progress.

308 Cleaning
A. Adjust and clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work
which cannot be successfully cleaned and repaired to permanently eliminate damage.
B. Remove spatterings and droppings resulting from work. Remove daily surplus materials and rubbish
from the work area.
C. Leave floors broom clean at completion.

309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
Internal walls Supply and install Gyprock CSR 13mm paperfaced recessed edge plasterboard typically to all
office walls of both partitions and internal face of all external walls etc., All office areas are to
have plasterboard finish unless noted otherwise.
All consulting / Audio room walls generally to have 2 x layers of 13mm Gyprock flush
‘Soundcheck’ full height wall linings to both sides, as noted on the architectural drawings.
All consulting / Audio room ceilingsgenerally to have 2 x layers of 16mm Gyprock flush
‘Fyrcheck’ lining, as noted on the architectural drawings.
To Wet Areas supply and install 13mm WR (‘aquacheck’) plasterboard lining.
Supply and install all stopping beads, shadow angles etc. as required and noted on
documentation
All plasterboard to be flush jointed to manufacturers details, Ex-angles to all external corners.
Include all bulkheads, drop walls, feature walls.
Provide expansion joints to Gyprock CSR recommendations.
All control joints shall be sealed or filled after the coating system has been applied.
Where indicated on drawings, supply and install Rondo P50 Shadowline trim.
Install all plasterboard in strict accordance with Gyprock installation manual No.547.
Support @ 600 c/c max.
Paint finish to all plasterboard.
External Walls with Plasterboard is not to be fixed directly to concrete panels.
Plasterboard Where nothing noted, use MS top hats. CSR Foilboard insulation. Provide expansion joints to
concrete panel joints in strict accordance with Gyprock specifications.
Expansion Joints Provide Rondo P45 plasterboard expansion joints or Gyprock P35 as required by Gyprock
recommendations.
Page 60 of 89 SECTION 09250 PLASTERBOARD
Maximum expansion joints to be located at 12m centres in both directions to ceilings and to
Gyprock recommendations to walls.
Provide expansion joints where plasterboard abuts different surfaces.
Discuss location of expansion joints in ceiling with architect to get approval for set-out.
Bulkheads Ceilings To areas where indicated provide Rondo screw-up ceiling system as specified. Typically entry
foyer, airlock and amenities areas.
Provide expansion joints to ceiling to manufacturers recommendations.
Provide square set corners where ceiling meets all walls.
Supply and install all suspension clips, joiners, top cross rails, furring channels etc. to complete
the installation.
Supply and install all stopping beads, shadow angles, etc. as required and noted on
documentation
Allow to construct MDF bulkheads and drop walls as documented/specified to Reception Area.
Allow to construct MDF concealed lighting recesses as documented/specified to Reception
Area.
All works to be in strict accordance with Rondo and Gyprock recommendations.
Paint finish to all plasterboard.
FR Plasterboard Supply and install Gyprock CSR 16mm Fyrchek where shown on drawings and inaccordance
with manufacturers specifications.
Refer to CSR ‘Red Book’ for installation requirements.
Access Hatches Supply and install Rondo Panther access hatches to all locations as shown on Architectural
ceiling plan and Services ceiling and details plans and specifications.
Supply and install Atkar Au.dislot or Concept Clip hatches to match surrounding ceiing finish.

END OF SECTION

Page 61 of 89 SECTION 09250 PLASTERBOARD


SECTION 09260 DRY WALL PARTITIONS

PART I GENERAL

101 Scope
Supply and install drywall partitions including but not limited to:
Steelwork
Stud wall framing
Plasterboard
Fire-rated plasterboard
Other panelling materials
Pre-surfaced panels of plasterboard etc.
Other:

102 Related Work Co-ordinate and co-operate with the following trade sections:
Floor construction Ceiling construction
Floor treatment Electrical wiring
Skirtings Plumbing
Wall construction Painting
Wall finishing

103 Quality Assurance Prototype: at a location selected by the architect on site, construct a full size
prototype of:

Include in each prototype all elements required by this specification, and finish in every respect.
When approved by the architect, such samples will be the control standard and remain part of the work.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS 1684 Residential timber-framed construction. There are many parts and Supplements,
1999 – 2010 and Amdmts 2012, 2013.
AS/NZS 2589 2007 Gypsum linings - Application and finishing.
2589.1 1997 (Available Superseded) Gypsum plasterboard.
2589.2 1997 (Available Superseded) Fibre reinforced gypsum plaster.
AS 3623 1993 Domestic metal framing.
AS/NZS 4600 2005 Cold-formed steel structures. Plus 1 Amdt, 2010.

105 Delivery, Handling and Storage


Deliver manufactured materials in bundles and packages bearing the name and manufacturer, and the brand.
Handle with care. Remove damaged materials from the site. Protect stored materials from damage and damp,
or materials which may cause deterioration.

106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 5 years from
the date of Practical Completion. Include a statement that the whole of the work has been carried out in
accordance with relevant Australian Standards and codes and manufacturer's instructions in effect at the time
of installation.

PART II MATERIALS

201 Acceptable Manufacturers


Rondo Pty Ltd

202 Materials
Supply materials in accordance with material supplier's recommendations for each application.

PART III EXECUTION

301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Rectify
discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
Space Enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in space
is completed and nominally dry.

Page 62 of 89 SECTION 09260 DRY WALL PARTITIONS


302 Preparation
A. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
B. Co-ordinate with and ensure preparatory work by other trades is done prior to commencement of work;
failure to do so will involve removal of dry wall partition and immediate rectification.
C. Arrange for provision of additional stud, nogging, trimmed openings, boxed studs, fixing grounds, etc.,
required for satisfactory execution of the work of this trade including penetrations through plasterboard
for services. Co-operate in installation of frames, duct openings, etc.

303 Installation General


A. Comply with manufacturer's installation instructions. Anchor and fasten materials and components to
comply with ratings and performance requirements, and to comply with governing local regulations.
Comply with appropriate Australian Standard.
B. Take care of and protect surrounding work, including other finishes, equipment and components, during
installation. Provide protective covering where necessary.

304 Installation Particulars

305 Protection
Protect finish work. Damage made good in every respect at no additional cost to the proprietor, and without
delay to job progress.

306 Finishing Details


General: apply treatment at board joints (both directions), flanges of trim accessories, penetrations, fasteners,
heads, surface defects and elsewhere as required to prepare work for decoration. Pre-fill open joints and
rounded or bevelled edges, using type of compound recommended by manufacturer.
Apply fibreglass joint tape at joints between boards, where a trim accessory is indicated, or where extra
strength is required.

307 Cleaning
A. Adjust and Clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work
which cannot be successfully cleaned and repaired to permanently eliminate damage.
B. Remove spatterings and droppings from work. Remove daily surplus materials and rubbish from the
work area.
C. Leave floors broom clean at completion.

308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
Metal Stud Walls Supply and install Rondo steel stud @ 450 c/c with 13mm thick plasterboard each side (2 x
layers of soundcheck plasterboard to select rooms / Meeting Rooms), paint finish. Stud width
to suite application. Refer Wall Type Schedule on drawings for stud size.
Provide boxed studs to manufacturer’s requirements.
Refer to structural engineer’s drawings for loading bearing stud walls.
Provide 15mm structural plywood bracing to all walls with new wall hung AV elements.
Timber framed walls Include to supply and install timber stud walls with 13mm Plasterboard lining to both sides
(load bearing where indicated). Studs @ 450 ctrs max.
Frame timber stud walls in strict accordance with AS1684 and the Victorian Timber Framing
Manual.
Provide double studs to all openings.
Refer to Structural Engineer for locations of double studs etc.
Provide square set cornice to areas indicated.

END OF SECTION

Page 63 of 89 SECTION 09260 DRY WALL PARTITIONS


SECTION 09500 SUSPENDED CEILINGS / FIXED CEILINGS

PART I GENERAL100

101 Scope
Supply and install a complete system of suspended ceilings including but not limited to:
Plasterglass ceilings.
Plasterboard ceilings.
Acoustic tile ceilings.
Bulkheads.
Ceiling access panels.
Insulating material.
Mineral fibre fire resistant duct spray.
Fire-rated ceilings.

102 Related Work


Co-ordinate and co-operate with the following trades:
Roof framing Structural steel
Concrete Mechanical services
Masonry Plasterboard

103 Quality Assurance


A. Prototype
At a location and time to be selected by the architect construct a complete prototypical ceiling
installation in one bay from one column to another of each ceiling type. Include elements provided under
this trade section and finish in every respect. When approved by the architect, the prototype becomes
the standard for the remaining work, and will remain as part of the work.
B. Acoustical ceilings installer
Sub-contractor is to have not less than 3 years of successful experience in installation of ceilings similar
to requirements for this project and who is acceptable to manufacturer of each ceiling type.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2785 2000 Suspended ceilings - Design and installation.
AS 2946 1991 Suspended ceilings, recessed luminaires and air diffusers - Interface requirements
for physical compatibility.
AS/NZS 4600 2005 Cold-formed steel structures. Plus 1 Amdt, 2010.

105 Samples
A. Acoustical ceiling tile: provide samples of tile, as selected by architect to be supplied; not less than 2
units of each.
B. Provide one sample of each of the following elements:
1. Rounded cornice
2. Cornice internal angle
3. Cornice external angle
C. Suspension systems: provide sample of each component of suspension and acoustic suspension
system, including both standard shapes and accessories.

106 Delivery, Handling and Storage


Deliver manufactured materials in the original packages, containers, or bundles bearing the name of the
manufacturer and the brand.
Protect materials from dampness. Store off the ground or slab, under cover and away from wet walls and other
damp conditions, in secure storage.

107 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 10 years from
the date of Practical Completion.
Include a statement that the whole of the work has been carried out in accordance with relevant Australian
Standards and manufacturer's instructions in effect at the time of installation.

PART II MATERIALS200

201 Acceptable Manufacturers


Supsnion System/Screw up System – Rondo
Others as indicated in schedules and appendices

202 Materials
A. Suspension system
(one way exposed)
Page 64 of 89 SECTION 09500 SUSPENDED CEILINGS / FIXED CEILINGS
(two way exposed)
B. Plasterboard 10mm, 13mm
C. Plasterglass
D. Acoustic tile
Tile size: As noted on drawings
E. Ceiling access panels
F. Cornice
G. Beads, straps, etc.
H. Casing beads, stop-ends, etc.
I. Other items:

203 Accessories
Supply and install necessary accessories as indicated by component manufacturer for satisfactory and
complete installation.

204 Equipment
Supply equipment, forms, scaffolding, ladders, frames, etc. necessary for the satisfactory installation of
specified items.

PART III EXECUTION300

301 Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of materials to
site. Rectify unsuitable situation.
Start of work means total acceptance of conditions. Comply with referenced Standards and manufacturer's
recommendations regarding environmental conditions.

302 Preparation
Space enclosure: do not install interior acoustical ceilings until space is enclosed, is weatherproof until wet-
work in space is completed and nominally dry until work above ceilings completed, and until ambient conditions
of temperature and humidity will be continuously maintained at values near those indicated for final occupancy.
Protect wood, metal, glass, flooring and other finished work during progress. Damage is to be made good in
every respect at no additional cost to the proprietor.
Prepare areas and surfaces against which installation will be constructed. Ensure work by other trades is
completed before erecting suspension system.
Powder driven fasteners are not approved for use.

303 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Comply throughout with applicable portions of AS/NZS 2785, or AS 2946, and with the data sheets supplied by
material manufacturer.

304 Field Quality Control


When requested by architect, arrange for manufacturer's representative to visit site and check installation.

305 Adjustment
Adjust installation to permit installation of such items as light fittings, mechanical vent registers and the like.

306 Protection
Protect completed installation from possible damage until issue of Practical Completion certificate.

307 Cleaning
Clean surfaces exposed to view. Replace sections or components which cannot be cleaned. Make good
damaged sections or panels affected by later work of other trades.

308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
Ceiling Grids Supply and install a complete system of ‘balanced Tee’ Rondo rigid rod white finished enamel
exposed suspension T-bar grid 1200 x 600.
Refer to architectyral drawings for height and setout.
Tiles to be Armstrong “Dune max RH99” 600 x 1200 x 20mm Square Lay-in mineral fibre
acoustic tiles – H4981.
Install all suspended ceilings in strict accordance with manufacturers details – Heights as per
documentation – typically office areas 2700mm min and to match existing where ceiling grids
Page 65 of 89 SECTION 09500 SUSPENDED CEILINGS / FIXED CEILINGS
are to be demolished and replaced.
Provide 5% spare ceiling tiles on completion.
Flush Plasterboard Provide flush jointed 13mm thick plasterboard Gyprock (span 600) with paint finish where
(General) noted on the architectural drawings.
Supply and install a complete system of Rondo concealed screw-up ceiling system.
Unless otherwise indicated, all plasterboard ceilings are to have square set cornices.
Refer to architectural drawings for design, rakes, angles etc…
Square set cornice where noted.
Provide expansion joints to ceilings to Gyprock specifications.
Perforated Acoustic Supply and install Gyprock Rigitone Matrix (12.5mm) suspended acoustic plasterboard ceiling
Plasterboard Ceiling in accordance with manufacturer’s specifications.
Sheets to be fully flushed – refer to manufactures details flush jointing details.
Provide continuous black tissue backing lining.
White pre-finish – smooth and flat finish.
Provide continuous acoustic blanket as scheduled over. Cut insulation to suit light fittings, air
registers etc…
Ensure that fixtures are centrally located within the joints of the plasterboard sheet, ensure
that fixtures do not penetrate the perforations. Refer to the RCPfor location/extent and
specifications for details.

END OF SECTION

Page 66 of 89 SECTION 09500 SUSPENDED CEILINGS / FIXED CEILINGS


SECTION 09650 RESILIENT FLOORING (VINYL)

PART I GENERAL

101 Scope
Supply and install resilient floor surfacing material with necessary accessories and related equipment required
for the work including but not limited to:
Vinyl tile
Linoleum sheet
Vinyl sheet
Cork tile
Vinyl skirting
Rubber sheet or tile

102 Related Work


Co-ordinate and co-operate with the following trades:
Concrete Internal wall construction

103 Quality Assurance


Suppliers and installers need to be widely experienced in the class of work required for the work of this section.
At a place selected by the architect, construct a prototype of a completed installation of vinyl floor and skirtings,
3 square metres in area. On completion of the prototype and approval by the architect of aspects of the
installation, the work remains in place and becomes the standard for the remaining work.

104 References
Comply with applicable portions of the following Australian Standards:
AS 1884 2012 Floor coverings - Resilient sheet and tiles - Laying and maintenance practices.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip hazards.
AS 4586-2013 Slip resistance classification of new pedestrian surface materials.
HB 197 1999 An introductory guide to the slip resistance of pedestrian surface materials.
Comply also with instructions of manufacturers of materials to be installed.

105 Submissions
Provide samples and data sheets of materials.
Obtain architect's approval for each item before ordering.

106 Delivery, Handling and Storage


Deliver materials in the packaging of the supplier, bearing the brand name, colour, thickness and other relevant
data.
Store materials in a secure dry area away from other materials which may cause deterioration.

107 Warranty
Provide a warranty covering aspects of the installation performed by this trade, against defective materials and
workmanship for a period of 5 years from the date of Practical Completion. The warranty includes a statement
that the whole of the work has been carried out in accordance with AS 1884 and the instructions of the
manufacturers of components in effect at the time of installation.

PART II MATERIALS

201 Materials
Refer finishes schedule.

202 Equipment
Supply equipment required for the preparation of floor, and installation of vinyl materials as recommended by
the material manufacturer.

PART III EXECUTION

301 Examination
Examine the site conditions applicable to each installation and comply with AS 1884.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.

302 Preparation
Prepare each area to be surfaced in accordance with AS 1884. Test the dryness of concrete sub-floor in
accordance with AS 1884.

Page 67 of 89 SECTION 09650 RESILIENT FLOORING (VINYL)


303 Installation
A. Delay installation of sheet until concrete has dried to the percentage established in Appendix A of AS
1884.
B. Adhesives: comply with AS 1884, and manufacturer's instructions.
C. Install material in accordance with AS 1884, including conditioning of both the materials and the sub-
floor.
1. Weld joints of vinyl sheet.
D. Skirting, to manufacturer's instructions.
E. Form junctions of different materials (eg. tiles to carpet) so that they occur under the centre line of
doors.

304 Cleaning
Remove excess adhesive and blemishes from the completed surfaces of flooring and skirtings.

305 Protection
Apply suitable hardboard or plywood to completed floors and maintain in position until final cleaning prior to
Practical Completion.
Remove and replace work which cannot be successfully repaired or cleaned.

306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
Vinyl Sheet Supply and install vinyl sheet flooring with coved vinyl skirting as scheduled in Internal
Colour and Finishes Schedule in Appendix.
Vinyl skirtings to be coved 150mm high (to cleaner’s rooms) with coving fillit backing unless
otherwise noted.
Install in strict accordance with manufacturers details.
Provide Ardit under to level floor and raise vinyl to match adjoining carpet.
Provide ‘moisture sealer’ to concrete slab if moisture content exceeds vinyl manufacturer’s
specifications.
Moisture Testing Concrete moisture testing must be conducted prior to installation of any flooring. This
testing must be in accordance with the manufacturer’s specification and the results (of the
testing) must be accepted by the manufacturer prior to installation.
The results of the testing are to be submitted to the architect before installation proceeds.
The test report must be in accordance with AS 2455, Clause B3.
The methodology and equipment used to moisture test concrete subfloors must be in
accordance with AS 2455.1 and the manufacture’s guidelines.
Provide ‘moisture sealer’ to concrete slab if moisture content exceeds floor covering
manufacturer’s specifications.

END OF SECTION

Page 68 of 89
SECTION 09685 MODULAR CARPET (TILE)

PART I GENERAL

101 Scope
Supply labour, materials and equipment required for supply, delivery, storage, installation and testing for the
complete Modular Carpet installation.

102 Related Work


Co-ordinate and co-operate with:
Installers of floors
Joinery
Preparation of surfaces under and adjacent to floors to receive carpet.

103 Quality Assurance


A thoroughly experienced and skilled tradesmen familiar with projects of this nature, under the direction of a
similarly experienced foreman, is required.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1385 2007 Textile floor coverings - Metric units and commercial tolerances for measurement.
AS/NZS 2270 2006 Plywood and blockboard for interior use. Plus 1 Amdt, 2007.
AS/NZS 2455 Textile floor covering - Installation practice
2455.1 2007 General. Plus 1 Amdt, 2009.
This Standard provides full instructions of pre-installation requirements and
installation methods.
2455.2 2007 Carpet tiles.
Maintain a copy of AS/NZS 2455.1 2007 General, at the project site until completion.

105 Submissions
Submit the following data and obtain approval from the architect before ordering materials:
A. List of recent projects with contact names and telephone numbers.
B. Full size sample module of each carpet type.
C. Confirmation of acceptance and compliance with the requirements of the builder in relation to the time
schedule for supply and laying.
D. Schedule of laying rates per square metre.
These rates include supply and installation of adhesive (if required) and accessories, cutting (where
required) and allowances for profit, overheads and administration costs.
E. Properties: provide test certificates from recognised authorities with the tender to confirm that the
modular carpet complies with the properties set down in clause 204.
F. Certification by the manufacturer that the materials comply with this specification.

106 Delivery, Handling and Storage


Deliver manufactured materials in the original packages, containers, or bundles bearing the name of the
manufacturer.
Protect materials from dampness. Store off the ground or slab, under cover away from wet walls and other
damp conditions in an approved location in the building.

107 Carpet Module Manufacturer's Guarantees


Provide a written confirmation from the manufacturer or his accredited representative that the carpet modules
have been properly installed and that subject to the carpet modules being properly maintained indoors in a
commercial installation, the carpet modules to the affected area/s will be replaced by the manufacturer at his
expense if any of the following occur:
A. Surface pile in area wears more than ten percent (10%) within 10 years of installation.
On stains the period of this guarantee is 5 years.
B. Horizontal dimensions of the modules vary from the specified dimensions by more than .2 percent
(0.2%) within ten years of installation as measured by the Aachen Test undertaken by an independent
test authority.
C. The modular carpet installation will not disrupt electronic office equipment (which is otherwise operating
properly) to cause malfunction by induced static charges.
D. The modular carpet installation, in a commercial installation, is guaranteed to control static shock below
3.5 kilovolts when the relative humidity is no less than 20% and the room test is 70oF. (AATCC Test
134-1975).

108 Modular Carpet Installation Contractor's Warranty


Provide a written warranty stating that materials supplied and installed under this contract will remain in good
condition, secure against faulty workmanship and/or defective materials for a period of 7 years from the date of
Practical Completion.

Page 69 of 89 SECTION 09685 MODULAR CARPET (TILE)


PART II MATERIALS

201 Acceptable Manufacturers


Interface

202 Accessories
Provide extruded aluminium edge trims
Plain clear anodised aluminium (silver), (gold), (bronze)
Flexible p.v.c. edge trims (gold), (black)
Provide black, flexible p.v.c. stair nosing or equivalent
Provide extruded plain aluminium stair nosing or equivalent filled with a black p.v.c. insert
Provide stair tread nosing or equivalent filled with back slip resistant infill bars

203 Carpet
Refer to Internal Finishes and Fixturers Schedule
Tolerances: AS 1385

204 Properties
Refer to Internal Finishes and Fixturers Schedule

205 Non-slip Materials


Water based substance recommended by its manufacturer as suitable for use as a pressure sensitive non-slip
compound.
100mm wide double sided tape with a releasable pressure sensitive coating recommended by its manufacturer
as suitable for the purpose of preventing the slippage of the modular floor tiles.

206 Testing Carpet


A. Before ordering the carpet, provide four no. tiles of the specified modular carpet for testing by the
Australian Wool Testing Authority.
B. During the production run of the carpet supply an additional four no. modular tiles for testing as
specified in "A" above.
Carry out tests at each of the above stages to confirm specified static properties.
Allow for and pay for the costs of tests.

207 Carpet Colour Sample


Before commencing the production of the carpet, supply three (3) tiles of the selected modular carpet to the
architect for written approval of colour and pattern.

208 Identification
Mark modular carpet tiles on the back to identify the manufacturer and the type of modular carpet.

209 Carpet Pattern Design Drawings


Lay the modular carpet to patterns, colours and designs shown on the architect's drawings.

210 Laying Diagrams


Prepare laying diagrams showing locations and directions of joints, types, patterns and colours of the modular
carpet.

211 Inspection Before Laying


Inspect modular carpet tiles before laying to ensure that:
A. The tiles are of types, patterns and colours specified.
B. Colour variations are within the specified tolerances.
C. The tiles are free from colour streaks, oil or grease spots, etc.
D. The carpet generally conforms to the Specification.
Reject modular carpet tiles not conforming to the required standards.

212 Spare Carpet Modules


Deliver to the site in unopened boxes spare modular carpet tiles equivalent to 5% of the total area of carpet
laid.
Do not deliver to the site until directed by the architect. Place in the final storage location.

PART III EXECUTION

301 Examination
Visit the site and inspect conditions comparing conditions to drawings before delivery of materials to the site.
Notify the architect of discrepancy or unsuitability of the substrate.

Page 70 of 89 SECTION 09685 MODULAR CARPET (TILE)


Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.

302 Preparation
Comply with referenced standards and manufacturer's recommendations regarding environmental and other
on-site conditions.
Repair by approved means imperfections of the floor surface which might impair the finished carpeted surfaces.
Broom clean or vacuum clean surfaces upon which carpet is to be laid.
On completion of cleaning, obtain architect's approval of surface and follow such standard as he may
determine for preparation throughout the project.

303 Space Enclosure


Do not install material until space is enclosed and weather-proof and until wet-work in space is completed and
nominally dry, and until ambient conditions of temperature and humidity will be continuously maintained at
values near those indicated for final occupancy.

304 Nap-lok Bars


Fix Nap-lok bars with each length fixed to the sub-floor using fastenings recommended by the manufacturer of
the Nap-lok bars as suitable for the respective sub-floors.
Comply with the requirements of AS/NZS 2455.1.
Fix Nap-lok bars with each length fixed to the concrete sub-floor using Sebco "Scruins" set in neatly drilled
holes in the concrete and spaced at each end at 225m centres between the end fixings.
Comply with the requirements of AS/NZS 2455.1.

305 Setting Out


Before laying modular carpet tiles, accurately establish two starting chalk lines towards the centre of the room
or area and at precisely 90o to each other.
Commencing only at the cross-over point of the chalk lines, complete one row of modules on each side of the
centre line.
From this point proceed in accordance with the manufacturer's printed instructions.

306 Pressure "Sensitive" Non-slip Compounds


Prevent modular carpet tiles for slippage in service by:
Pressure sensitive water based pressure sensitive non-slip compound, applied by paint roller at the rate of 10-
15 sq. metres per litre depending on the absorption rate of the sub-floor and in strict accordance with the non-
slip compound manufacturer's printed recommendations.
Pressure sensitive compound provided in a 350 gram pressure pack container, applied at the rate of 50-70
modules per container either to the whole of the sub-floor or the whole of the back of the modular carpet tiles in
strict accordance with the non-slip compound manufacturer's printed recommendations.
Properly ventilate the area of use.
100mm wide double-sided tape with a releasable pressure sensitive coating laid along the centre line of
modular carpet tiles in both directions.

307 Laying – General


Lay strictly in accordance with the manufacturer's printed directions.
Cut tiles from the back using a sharp knife and a cutting board.
Open boxes on site 24 hours before laying and mix up tiles of similar pattern and colour from different boxes.
Lay tiles hard up against each other and maintain tension on the tiles during laying by kneeling on the tiles as
they are installed.
Use a knee kicker to ensure that tiles are laid hard up against each other.
Carefully scribe up to walls, columns, partitions and other fixed obstructions using techniques recommended by
the manufacturer.
‘Ardit’ floor finish to be installed to room perimeter prior to modular tile installation to ensure carpet finish flat
and parallel with wall skirting.

308 Partitions
Partitions will be erected prior to the laying of the modular carpet.

309 Stairs
Lay carpet tiles to treads with pile running into the step. Cut to tight fit between nosing trims and risers.
Lay modular carpet tiles to risers with pile running downwards glued only along the top edge, fitted neatly
between the nosing trim and the tread and laid prior to laying the modular carpet tiles to the tread below.
Provide tread nosing (specified earlier) to the nosings of treads and landings fixed down to the stair treads
before laying the modular carpet tiles to the stair and in accordance with the manufacturer's printed
instructions.

310 Access Floors


Lay modular carpet tiles over access floors generally as for other floors.

Page 71 of 89 SECTION 09685 MODULAR CARPET (TILE)


Stagger joints between tiles with respect to the joints between the floor panels to prevent the flow of air from air
conditioning systems causing dust to pass through the joints.
Fix down modular carpet tiles to the floor panels as specified for the other floors.

311 Carpets For Lift Cars


Modular carpet tiles for lift cars are to be fire-proofed in accordance with the requirements of the controlling
authorities.
Provide certificates of fire proofing.
Permanently mark the fire-proofed carpet tiles on the back to denote that they have been fire-proofed.
Supply sufficient additional fire-proofed modular carpet tiles to provide two sets for each lift with each set cut to
size where required to fit the lift floor and each tile clearly marked on the back to denote the lift car to which it
belongs and its position on the car floor.
Provide two copies of floor plans of each lift and indicated on the plans the location of each modular tile utilising
the identification markings on the back of the tile.

312 Cleaning And Protection


On completion of laying each section of carpet, remove dirt, scraps of left-over carpet, etc., and vacuum the
surface clean and free from dust, etc.
After inspection by the architect, cover the carpet in each section with continuous layer of 0.152mm thick clean
polythene film with joints lapped 150mm minimum and continuously sealed with self-adhesive tape.
Batten and nail perimeters to the floor.
Maintain the cover in good order and condition and remove the same and finally clean the carpet at Practical
Completion.

314 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
Carpet Tiles Supply and install Supply and install Carpet Tile as scheduled on Internal Colour and Finishes
Schedule in Appendix to areas indicated on architectural documentation.
Allow to Ardit floor slab to all carpet tile areas.
Allow 6-8weeks lead time for supply.
Lock-dot Installation All carpet tiles must be installed with ‘lock-dot’ adhesive system to manufacturer’s written
specifications.
Moisture Testing Concrete moisture testing must be conducted prior to installation of any flooring. This testing
must be in accordance with the manufacturer’s specification and the results (of the testing)
must be accepted by the manufacturer prior to installation.
The results of the testing are to be submitted to the architect before installation proceeds. The
test report must be in accordance with AS 2455, Clause B3.
The methodology and equipment used to moisture test concrete subfloors must be in
accordance with AS 2455.1 and the manufacture’s written specifications.
Provide ‘moisture sealer’ to concrete slab if moisture content exceeds floor covering
manufacturer’s written specifications.
Carpet Protection All carpets are to be covered and protected with permeable protection sheeting barrier after
installation until just prior to hand over.
Heavy traffic paths are to be protected with additional MDF or similar boarding.
Spare Carpet Tiles Refer 212 Spare Caret Modules.
Transition Strips Metal (aluminium anodised) transition strips at all junction between dis-similar materials.
Refer 05500 Metalwork for details.

END OF SECTION

Page 72 of 89 SECTION 09685 MODULAR CARPET (TILE)


SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)

PART I GENERAL100

101 Scope
Supply labour and materials, services and equipment necessary for the preparation, application and finishing of
wall covering as indicated on drawings, schedules and as specified herein, to internal surfaces of building.
Refer to Schedule of Finishes.

102 Related Work


Co-ordinate and co-operate with the following trades:
Plasterboard
Hard plaster Painting
Other substrates to be wallpapered

103 Quality Assurance


The installer is to be widely experienced in the class of work required for the work of this section.
At a place selected by the architect, prepare a test sample for all types. Test samples include the suitable
preparation of substrates. After approval, the test samples remain in place and become the standard of the
remaining work of the same type.

104 References
In the absence of Australian Standards, comply with applicable written recommendations of the manufacturer.

105 Submissions
Submit the following materials:
Product literature on proposed systems.
Samples of approved materials which are to be identified with the manufacturer's colour code batch number
and colour name or match to scheduled colour code and name.
Samples are not to be less than 2 metres long and are to be of the same colour, pattern and type as
scheduled.

106 Delivery, Handling and Storage


A. Bring all materials to the site and store in manufacturer's original packaging, bearing the manufacturer's
standard label, indicating type, pattern and colour.
B. Store materials in designated spaces in a safe and secure manner. When not in use, keep such spaces
locked and inaccessible to those not employed under this Trade Section.

107 Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application installed
under this contract will show no deterioration and remain in good condition for a period of 7 years from the date
of completion.

PART II MATERIALS200

201 Materials
Refer to Schedules

PART III EXECUTION300

301 Examination
Inspect all surfaces and determine that they are in proper condition to receive the work to be performed under
this section.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
The starting of work under this section means acceptance of such surfaces as being satisfactory. Correct
defects in work resulting from accepting poor surfaces at no cost to the Proprietor.

302 Preparation
Prepare all surfaces as required so that they are in a proper condition to receive the work.
Comply with manufacturer's instructions. Remove dust, dirt, grease and other extraneous matter affecting the
finished work.
Remove lighting fixtures, switches, power outlets and similar items in place prior to installation and reposition
upon completion of each space.

303 Protection
Provide suitable protection in all areas where wall covering is being done to protect adjacent surfaces from
damage during work.
Page 73 of 89 SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)
304 Application
Execute all work of this section in strict compliance with the manufacturer's recommendations.

305 Cleaning
At completion of work in each area, thoroughly clean the area.
Replace wall fittings and fixtures previously removed.

306 Spare Material Rolls


Supply to the proprietor’s representative further material being 3% of the area of surfaces covered.

307 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued by the
architect.

END OF SECTION

Page 74 of 89 SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)


SECTION 09910 PAINTING

PART I GENERAL100

101 Scope
Supply labour and materials, services and equipment necessary for the preparation, application and finishing of
painting and staining as indicated on drawings, schedules and as specified herein, to internal and external
surfaces of building, as follows:
Refer Schedule of Finishes.
Consult with the architect with regard to requirements of other trade sections of the specification which require
painting, and include as part of the work of this trade section the appropriate preparation, painting, and finish
required to complete the installation.

102 Related Work


Co-ordinate and co-operate with the following trades:
Substrates to be painted Cleaning and finishing
Scaffolding

103 Quality Assurance


A. Compatibility of shop and field paints:
Determine that the materials specified in the Schedule of Finishes are compatible with shop coats.
Failure to do so will be construed as accepting the paints specified. Contractor is to correct, at his own
expense, defects in his work resulting from the use of such materials.
B. Test samples:
1. Prepare test samples for painting types and typical locations, where determined by the architect.
Do not commence painting of the substrate type until the sample is approved by the architect.
Apply samples in conditions approximating as closely as possible the lighting conditions of the
finished work.
2. Test samples include the suitable preparation of substrates.
3. After approval, test samples are to be the standard for quality control of the completion of work of
same type.

104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2311 2009 Guide to the painting of buildings.
(NB: maintain this document at the project site by the contractor as a controlling
general reference).
AS/NZS 2312 2002 Guide to the protection of structural steel against atmospheric corrosion by the use
of protective coatings. Plus 1 Amdt, 2004.

105 Submissions
Submit the following materials:
A. Product literature on proposed painting systems.
B. Colour samples for approved painting materials. Identify samples with:
1. Manufacturer's colour code and colour name (if any).
2. Match to Schedule colour code and name.
C. Samples are not to be less than 100 x 100mm, and are to be of the same gloss level as the scheduled
colour.
D. Copies of pre-installation conference minutes.

106 Delivery, Handling and Storage


Store materials in designated spaces in a secure manner which meets the requirements of applicable codes
and fire regulations. When not in use, keep such spaces locked and inaccessible to those not employed under
this section. Provide each space with a fire extinguisher of carbon dioxide or dry chemical type bearing a tag of
recent inspection.
Bring materials to the building and store in manufacturer's original sealed containers, bearing the
manufacturer's standard label, indicating type and colour. Deliver materials in sufficient quantities in advance of
the time needed in order that work will not be delayed in any way.

107 Project Conditions


Temperature: comply with the requirements of clause 6.3 of AS/NZS 2311 The painting of buildings, and of
paint manufacturers with regard to both ambient temperature and relative humidity.

108 Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application installed
under this contract will show no deterioration and remain in good condition for a period of 7 years from date of
Practical Completion.

Page 75 of 89 SECTION 09910 PAINTING


PART II MATERIALS200

201 Materials
All internal paints are to be low VOC or environmental paints.
General: where manufacturer makes more than one grade of any material specified, use the highest grade of
each type, whether or not the material is mentioned by trade name in these specifications.
Paints and finishes used for the project may be manufactured by one or more of the following manufacturers:
Taubmans.
Dulux.
Wattyl.
Pascol.
Other products may be approved by architect. Apply to architect for approval of alternatives.
Provide materials necessary for preparation of surfaces, and for application of paint finishes.

202 Schedules
A Schedule of Finishes is included in this specification.
The architect will prepare a final Schedule of Colours in sufficient time before commencement of work.

203 Paint Types

204 Priming Materials


Colours of priming coats (and body coats where specified) are to be lighter than those of finish coat.

205 Spare Paint


Contractor to provide adequate left over paint for touching up and maintenance. To be supplied in well-sealed
long-life containers of colour matched paints, clearly labelled and mapped to rooms/walls inside and outside the
building (where applicable).

PART III EXECUTION300

301 Examination
Inspect surfaces and determine that they are in proper condition to receive the work to be performed under this
trade section. Refer 302 A, below.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
The starting of work under this trade section will be taken to mean acceptance of such surfaces as being
satisfactory and defects in work resulting from accepting poor surfaces are to be corrected at no cost to the
proprietor.
Refer AS/NZS 2311 Appendix C.

302 Preparation
A. General: prepared to a standard not less than that described under AS/NZS 2311, Section 3:
Preparation of Un-Painted Surfaces inclusive, and other clauses of Australian Standards referenced
therein.
This Standard is incorporated by reference as part of this specification and applies to the work below to
the same extent as if written herein.
B. Broom clean floor surfaces before painting. Remove dust, dirt, plaster, grease and other extraneous
matter affecting the finish work.
C. Putty-stop or plug nail holes and cracks on both exterior and interior work, as required. Natural or
stained wood finishes are to have putty coloured to match. Putty wood after prime coat or sealer coat
has been applied.
D. Clean bare metal surfaces of mill scale, rust, grease, oil, dirt, or other foreign matter, then properly
washed with spirit or other approved cleaning agents. After cleaning, etch, pickle, prime, or otherwise
prepare, as recommended by the paint manufacturer.
E. Remove blisters or other imperfections in previous coats caused by foreign substances or paint skins
from painted surfaces before the subsequent coat is applied.
F. Rub down wood and metal surfaces before finishing and between coats with No. 00 and finer sandpaper
or steel wool, leaving a perfectly clean surface. Sand smooth-finished surfaces before finishing and
between coats as required to smooth out rough areas and to assure a smooth, even finish. Surfaces to
receive paint are to be smooth and free of sandpaper scratches, mill-marks, and other imperfections.
G. Remove hardware, accessories, plates, lighting fixtures and similar items in place prior to painting and
re-position upon completion of each space, or protect as otherwise directed by the architect.
H. Thoroughly stir materials in containers before application, unless otherwise directed by the manufacturer
of the paint used, to ensure uniformity of colour and mass. Strain out paint skins or other materials
which would cause lumps or roughness. Thin only as recommended by the manufacturer.

303 Protection
Furnish and lay suitable drop cloths in areas where painting is being done to protect floors and other surfaces
from damage during the work.

Page 76 of 89 SECTION 09910 PAINTING


304 Application
A. General: execute work of this trade section in strict compliance with paint manufacturer's
recommendations, and with the provisions of AS/NZS 2311, Section 6: Paint Application, inclusive. This
standard is incorporated by reference as part of this specification and applies to the work below to the
same extent as if written herein. In the event of conflict between manufacturer's recommendations and
the provisions of AS/NZS 2311, manufacturer's recommendations govern.
B. Maintenance or repainting
Execute work of this trade section in strict compliance with paint manufacturer's recommendations, and
with the provisions of AS/NZS 2311, Section 7: Maintenance of Painted Surfaces on inclusive and
Section 8: Maintenance Painting Systems. This standard is incorporated by reference as part of this
specification and applies to the work below to the same extent as if written herein. In the event of conflict
between manufacturer's recommendations and the provisions of AS/NZS 2311, manufacturer's
recommendations govern.

305 Cleaning
At completion of work in each area, remove paint spots, oil and stain from adjacent surfaces, including finish
hardware.
Replace hardware previously removed.

306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

307 Schedules

PART IV DETAILS

Location/Description Details
General To be read in conjunction with Finishes Schedule.
Paint VOC Limits All paint to be low VOC
Product Type/Sub Category Max TVOC Content (g/L
of ready to use product)
Walls and Ceilings – Interior Gloss 75
Walls and Ceilings – Interior Semi Gloss 16
Walls and Ceilings – Interior Low Sheen 16
Walls and Ceilings – Interior Flat Washable 14
Ceilings – Interior Flat 75
Trim Gloss, Semi Gloss, Satin, Varnish and Wood Stains 30
Timber and binding primers 60
Interior Sealer 140
One and Two Pack Performance Coatings 200
INTERNAL
Walls (General) 1 coat Dulux sealer undercoat.
2 coats Dulux Wash and Wear satin acrylic.
All walls to be painted where not nominated as exposed finished proprietary product as
shown on drawings and schedules.
Walls to Wet Areas 1 coat Dulux sealer undercoat – ‘Aqua primer’
2 coats Dulux Wash and Wear ‘Kitchen and Bathroom’ satin acrylic. Low sheen.
Flush Plaster 1 coat Dulux acrylic sealer undercoat.
Ceilings (General)
2 coats Dulux Wash and Wear ‘flat’ acrylic.
Flush Plaster 1 coat Dulux sealer undercoat – ‘Aqua primer’
Ceilings to Wet
Areas
2 coats Dulux Wash and Wear ‘Kitchen and Bathroom’ satin acrylic. Low sheen.
Timber Doors 1 coat Dulux oil based undercoat.
2 coats Dulux enamel semi-full gloss.
Metalwork 1 coat Dulux ‘all metal primer’
2 coats Dulux gloss enamel.

END OF SECTION

Page 77 of 89 SECTION 09910 PAINTING


SECTION 10400 IDENTIFICATION SIGNS

PART I GENERAL

101 Scope
Design, supply and install required items including but not limited to:
Directory panel
Bulletin boards
Panels
Metal frames
Dimensional letters
Exterior/interior signs
Illuminated, non-illuminated
Plaques
Door signs
Signs for the disabled.

102 Related Work


Co-ordinate and co-operate with the following trades:
Wall construction Concrete
Floor construction Finishes
Tactile warning surfaces

103 Quality Assurance


Materials, shop fabrication and on-site installation are to be supplied and performed by fully trained and
experienced tradesmen in accordance with instructions of the manufacturer.

104 References
Comply with the applicable portions of the following Australian Standards:
AS 1319 1994 Safety signs for the occupational environment.

105 System Description


The specified materials and systems are intended to provide a uniform image throughout the building. Where
possible, materials are to be provided by the same manufacturer.

106 Submissions
Submit to the architect for approval, the following before ordering materials:
A. Samples of specified materials, conforming to type and finish required.
B. Fully detailed drawings showing overall dimensions and component sizes with proposed methods of
fixing and/or securing position.
C. Check data on sign for data accuracy - spelling , phone number, etc. before manufacture.
D. Copies of minutes of pre-installation conference.

107 Delivery, Handling and Storage


Deliver materials in accordance with the Project Schedules.
Prevent damage to materials by securely boxing or wrapping before delivery. Take care with materials during
delivery and handling.
Store materials on site where directed by builder. Where possible install directly in place.

108 Warranty
Provide to the proprietor a warranty co-signed by the manufacturer and installer stating that items in this
specification will remain in full operational condition for a period of 10 years from the date of Practical
Completion.

109 Maintenance
Provide a written undertaking to the proprietor that parts of the installation will be available for additional supply
from time to time to suit the proprietor's needs for a period of 10 years from the date of Practical Completion.

PART II MATERIALS

201 Acceptable Manufacturers


Braille Tactile Signs Pty Ltd.

202 Materials
Refer signage schedule.

203 Finishes
Refer signage schedule.

Page 78 of 89 SECTION 10400 IDENTIFICATION SIGNS


204 Signs for The Disabled
Refer signage schedule.

205 Fabrication
Fabricate components in accordance with manufacturer's instructions and approved drawings.
Form junctions so that fixings are concealed.
Cut edges, drill holes free from burrs and indentations. Fit joints to a fine hairline.
Pre-assemble where possible or practical and mark each item for intended location before delivery.

PART III EXECUTION

301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Rectify
discrepancy or unsuitability of substrate.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.
Space enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in space
is completed and nominally dry.

302 Preparation
Prepare areas and surfaces before installation, so that best conditions exist.
Where necessary, ensure that lighting cable is in place and concealed ready for connection to light fittings
within the illuminated items.

303 Installation
Comply with manufacturer's written instructions. Provide appropriate anchoring devices, concrete pads for
external signs.
Take care of and protect adjacent surfaces and materials. Provide protective cover to adjacent finishes where
necessary.

304 Protection
Protect finished work.
Replace or make good work found damaged at time of Practical Completion.

305 Cleaning
A. Adjust and clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work
which cannot be successfully cleaned and repaired to permanently eliminate evidence of damage.
B. Remove spatterings and droppings from work. Remove daily surplus materials and rubbish from the
work area.
C. Leave floors broom clean at completion.

306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
General Refer Door Schedule and Signage Schedule.
All other statutory signage by Contractor.
All signage to be installed to relevant current Australian Standards and NCC (BCA).
Sample for Approval Builder to provide sample of all signage for approval with at least 10 worksing days within
the program for review and approval.
Room Numbering Supply / install an aluminium natural anodised room numbering plate for each room in the
fitout (all floors) with the University of Melbourne allocated room numbers.
Text to be 50mm high black vinyl lettering.
Fire Service Signage Fire Services Signage to be to the approval of the CFA:
All Fire Service Signage must be installed as per section E1 of the NCC (Formally BCA).
Signage to be installed min 2m above FFL.
Signs to be laminated PVC finish or similar approved.
50mm high text, capital letters
Tactile Signage All Tactile and Braille signs must be installed as per section D3.6 of the NCC (Formally
BCA).
Signs must be located not less than 1200mm and not higher than 1600mm above the floor
or ground surface.
Signs with single lines of characters must have the line of tactile characters not less than
1250mm and not higher than 1350mm above the floor or ground surface.
Sign text to be 20mm high ‘Arial’ font.

Page 79 of 89 SECTION 10400 IDENTIFICATION SIGNS


Signs identifying rooms containing features or facilities listed must be located;
a. On the wall on the latch side of the door with the leading edge of the sign
located between 50mm and 300mm from the architrave; and
b. In the event of insufficient latch side dimension, a sign may be placed on the
non-latch side of the door; and
c. Where (a) or (b) is not possible, the sign may be placed on the door itself.
Signs identifying paths of travel must be placed so they are located directly ahead in the
direction of travel. Where one wall continues in the direction of travel and the other forms a
corner, the sign must be placed on the continuing wall.

END OF SECTION

Page 80 of 89 SECTION 10400 IDENTIFICATION SIGNS


SECTION 10520 FIRE EXTINGUISHERS

PART I GENERAL100

101 Scope
Supply and install extinguishers where indicated in accordance with the statutory authority having jurisdiction.

102 Related Work


Co-ordinate and co-operate with the following trades:
Wall construction
Wall finishes

103 Quality Assurance


Perform work of this trade section with experienced tradesmen familiar with the quality of work required and
licensed by the manufacturers of the extinguishers. Comply throughout with written instructions.

104 References
Comply with applicable portion of the following Australian Standards:
AS 1603 Automatic fire detection and alarm systems.
There are 12 parts 1996 – 2011 and 4 Amdts, 1998 – 2001.
AS 1670 Fire detection, warning, control and intercom systems, system design, installation
and commissioning. There are 5 parts, 1997 – 2004, plus 1 Amdt, 2005.
AS/NZS 1841 2007 Portable fire extinguishers. There are 8 parts, one for each type.
AS/NZS 4353 1995 Portable fire extinguishers - Aerosol type.
Comply with requirements of statutory authority having jurisdiction.

105 Submissions
Copies of minutes of pre-installation conference.

PART II MATERIALS200

201 Manufacturers
Manufacturers of materials approved in writing by the statutory authority may supply equipment.

202 Materials
Supply and install extinguishers authorised by the authority in accordance with the schedule provided by the
authority.

203 Installation Devices


Supply brackets signs and other required items, and the means of securing them to the building.

PART III EXECUTION300

301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure conditions
are satisfactory for installation. Arrange for rectification if required.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of relevant conditions.

302 Inspection on Arrival at Site


Inspect materials on arrival, comparing each item to the schedule provided. Ensure that no material is
damaged. Return to the manufacturer damaged items and obtain a replacement.

303 Installation
Anchorage: except for anchorages furnished herein but placed by other trades, set and secure necessary
anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as needed.
Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper positioning of
completed work.

304 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.

305 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.

Page 81 of 89 SECTION 10520 FIRE EXTINGUISHERS


PART IV FITTINGS & FIXTURES

Location/Description Details
General Contractor to assess and supply all fire extinguishers as required to comply with BCA.
All fire extinguishers are to be housed in locked enclosures with ‘break glass’ access.
Supply and insl Type: 2A:20B:E ‘Dry Chemical’ fire extinguisher to all electrical switch boards.
Final location to confirm with Architect prior to installation.
Fire Blanket Supply and install a fire blanket to each kitchen.
Final location to confirm with Architect prior to installation.

END OF SECTION

Page 82 of 89 SECTION 10520 FIRE EXTINGUISHERS


SECTION 12300 MANUFACTURED CASEWORK - SHOP BUILT

PART I GENERAL

101 Scope
The work of this trade section covers the supply and installation of manufactured casework items.
It includes but is not limited to:
Cabinets and cupboards
Shelving
Display units
Counters
Lockers

102 Related Work


Co-ordinate and co-operate with the following trades:
Carpentry Wall finishes
Floor finishes Ceiling finishes
Plumbing Electrical installation

103 Quality Assurance


Manufacturers and installers are required to be widely experienced in the relevant aspects and class of work
required for this section.
At a place selected by the architect, construct a prototype of a completed installation. Include in this prototype
all elements required by this specification, finished in every respect. When approved by the architect, each
prototype remains part of the work and becomes the standard for the remaining work.

104 References
Comply with applicable portions of the Australian Standards:
AS/NZS 1859 Reconstituted wood-based panels – Specifications.
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
There are 3 other parts, 2004 – 2005, 3 Amdts, 2006 - 2009.
AS 2754.2 1991 Adhesives for timber and timber products - Polymer emulsion adhesives.
AS/NZS 2924 High pressure decorative laminates – Sheets made from thermosetting resins.
There are 2 parts, 1998.
AS/NZS 4386 Domestic kitchen assemblies.
4386.1 1996 Kitchen units.
4386.2 1996 Installation.
AS 4786.2 2005 Timber flooring - Sanding and finishing.

105 Submissions
Submit the following prior to fabrication:
Product literature on proposed hardware items including components.
Technical data on melamine laminates proposed for use.
Technical data and samples of substrate materials.
Thickness of materials at typical locations.

106 Delivery, Handling and Storage


Do not deliver work to the site until after completion of other trade activities which could soil, damage or cause
deterioration of manufactured joinery items.
Prevent soiling, damage or deterioration during delivery, storage and handling.
Keep site storage to a minimum. Install directly in place, but refer to clause 302.
If circumstances make storage necessary in areas other than the final location, store only in those that meet
the requirements specified for installation areas.

107 Warranty
Provide to the proprietor a warranty co-signed by the manufacturer and installer stating that items in this
specification will remain in full operational condition for a period of 5 years from the date of Practical
Completion.

PART II MATERIALS

201 Materials
Refer to ‘Finishes Schedule’

202 Hardware
Refer ‘Fixtures and Fitting Schedule’.
Refer Hafele catalogue where not nominayed.
- All joinery doors and drawers to have ‘soft close’

Page 83 of 89 SECTION 12300 MANUFACTURED CASEWORK - SHOP BUILT


203 Fabrication
Construct by screwing and gluing or other approved method. A dry stapled assembly will not be approved.
Fabricate bench tops as indicated in a manner recommended by the material's manufacturer. Fabricate units
without joints unless counter length exceeds maximum available length of materials.
Seal joints between counter and splash back with matching colour silicone. Wherever possible, pre-cut
openings to receive hardware, appliances, plumbing fixtures, electrical work and similar items.
Locate openings accurately using templates or roughing-in diagrams for proper size and shape. Smooth edges
of cut-outs and, where located in bench tops and similar exposures, seal edges of cut-outs with a water
resistant coating.
Back prime all concealed solid timber surfaces prior to installation.
Install fasteners, hinges etc in accordance with manufacturer’s instructions. When in doubt about suitability,
consult with manufacturer of the items specified or selected.

204 Inspection Before Delivery


Advise architect when the first of any group of items is ready for inspection not less than 4 days before delivery
is due at the site. Where work is found not to comply with documentation, the architect will order rectification.
The architect will be the sole decision-maker regarding compliance or non-compliance.

PART III EXECUTION

301 Examination
Visit the site and inspect conditions. Check dimensions and compare all aspects with the drawings and
specification. Resolve differences before ordering materials or starting work.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of all conditions.

302 Preparation for Installation


Prior to installing, condition joinery to the average humidity conditions prevailing in the installation areas.
Deliver anchoring devices and similar inserts required to be built into substrates well in advance of the fixing of
fittings and provide full details when they are to be fixed by others.
Prior to installation, examine shop-fabricated work for completeness and remedy and any deficiencies. Include
back priming. Remove packing where not required.
Thoroughly clean all floors and walls that will be permanently concealed by joinery.

303 Installation
Use concealed shims as required to install the work plumb, level, straight and distortion free within the following
tolerances:
- 1mm in 800mm for plumb and level (including bench tops),
- 0.5mm maximum offsets in flush adjoining surfaces,
- 2mm maximum offsets in revealed adjoining surfaces.
Scribe and cut to fit adjoining work; refinish cut surfaces or repair damaged finishes at cuts.
Secure joinery with anchors of blocking built-in or directly attached to substrates. Secure to grounds, stripping
and blocking with countersunk, concealed fasteners and blind nailing as required to complete the installation.
Except where pre-finished matching fastener heads are required, use fine finishing nails, countersunk and filled
flush. Use a matching filler where a transparent finish is required.
Install casework without distortion so that doors will fit openings properly and be accurately aligned.

304 Hardware
Install all door and joinery hardware as scheduled, listed and required in full compliance with the manufacturer's
recommendations.
Adjust as needed to centre doors in openings.

305 Adjustments, Cleaning, Finishing and Protection


A. Finish the work specified in this trade section and remedy anything not finished at the shop or any other
stage prior to completion.
B. Adjust joinery to achieve a uniform appearance.
C. Lubricate and clean hardware making any final adjustments needed for proper operation.
D. Remove all handling marks from visible joinery surfaces.
E. Protection: do everything needed to ensure that all work is without damage or deterioration at
completion.

306 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued by the
architect.

Page 84 of 89 SECTION 12300 MANUFACTURED CASEWORK - SHOP BUILT


PART IV FITTINGS & FIXTURES

Location/Description Details
Kitchen/Tea Point This is to be read in conjunction with Internal Colour and Finishes Schedule and Fixtures,
Fittings and Appliances Schedule in Appendix.
Supply and install laminate 33mm MR-MDF craftwood benchtop and carcass with laminate
finish and post-form edges as scheduled.
Cupboard fronts and drawers to be 18mm thick MDF craftwood with laminate finish. Colour as
selected.
Internals to be 18mm thick white melamine board.
Kickspace to be 100 x 50mm MDF craftwood with natural andoised aluminium finish.
Adjustable shelves to have brass bush and dowel.
Provide chrome tea towel rail behind door to each tea bench.
Hinges to cabinet doors to be Blum 180º spring loaded self closing hinges.
All drawers and cupboard doors to be fitted with ‘soft close’ hinges and drawer runners.
Provide cutlery insert to top drawer of each tea bench.
Drawer runners are to be heavy duty steel ball bearing slides or rollers. Hafele or similar.
Provide minimum 1 bank of 4 drawers to each Tea Area.
Provide chrome flange to cover all penetrations through cabinet.
Wall Mounted Floating shelves (where applicable) to be 25mm thick MDF craftwood with melamine laminate
Shelving finish. Max span. 800mm. Proved concealed steel pin fixings as noted on the drawings.
Storage Joinery Supply and install laminate 18mm MDF craftwood carcass and 25mm MDF craftwood top with
laminate finish and ABS or laminate edges as noted on the architectural drawings, colour as
selected.
All internals to be 16mm white melamine finish.
Kickspace to be 100 x 50mm MDF craftwood with laminate finish.
Adjustable shelves to have brass bush and dowel.
Hinges to be Blum spring loaded 180º self closing type.
Storage Cupboards Supply and install laminate 25mm MDF craftwood carcass with chemical resistant laminate
finish edges as noted on the architectural drawings, colour as selected.
Cupboard fronts to 25mm thick MDF craftwood with laminate finish. Colour as selected.
Shelves to 25mm thick MDF craftwood with chemical resistant laminate finish, sqquare edge
finish. Colour as selected.
Kickspace to be 100 x 50mm MDF craftwood with laminate finish.
Adjustable shelves to have brass bush and dowel.
Hinges to cabinet doors to be Blum 180º spring loaded self closing hinges.
Fixing All shelving and carcasses are to be fixed directly to sud work in walls. Stud finder to be used
to locate prior to installation.
Locks All Locks to joinery shall be from one of the following suppliers:
-Cyberlock
-BMB
-Lock Focus
-Hafele

END OF SECTION

Page 85 of 89 SECTION 12300 MANUFACTURED CASEWORK - SHOP BUILT


SECTION 12720 COMMERCIAL FURNITURE / WORKSTATIONS

PART I GENERAL100

101 Scope

Seek quotations for all office furniture – workstation,s storage, seating, tables etc… from one of the following:
UCI Australia

Contractor to fully manage and co-ordinate with the workstations / furniture installers.
Coordinate soft wiring installation. Install all starter sockets as noted.

Supply and install a complete installation of workstations where shown on drawings, including but not limited to:
Frames
Panels, solid, glazed, laminated, metal, veneered, acoustic, fabric faced
Cable ducts
Power poles
Work benches
Work bench drop keyboard panel
Shelves
Hampers
Drawer pedestals
Cupboards
Pinboards, whiteboards
Power, telephone and computer data outlets
Light fittings

102 Related Work


Co-ordinate and co-operate with the following other trades:
Carpet
Electrical installation
Telephone and data cable installation

103 Quality Assurance


Submit evidence of experience with manufacture and installation of similar workstations. Install under the direct
supervision of a capable foreman employed by the manufacturer.

104 System Description


The components of the whole installation are required to be provided and installed by one manufacturer with
the following exceptions:
The workstation system provides for power, telephone and data cable channel at
Allow for fabrication of components off site and for assembly on site with minimum tools. No cutting, soldering,
welding or painting, except touch-up paint, will be permitted on the site.

105 References
Comply with applicable portions of the following Australian Standards:
AS 3590 Screen-based workstations
3590.2 1990 Workstation furniture. There are 2 other parts, 1990.
AS/NZS 4443 1997 Office panel systems – Workstations.
Comply also with the requirements of statutory authorities having jurisdictions.

106 Submissions
Provide before ordering construction of components or ordering from stock:
product data describing components
shop drawings of components
samples of finishes of components
manufacturers written instructions for installation
certificate indicating approval of components by relevant bodies such as electricity supply authority and
telephone service supplier.

107 Delivery, Storage and Handling


Contain components in material suitable for transport to place of installation. Handle with care. Deliver directly
to place of installation. Do not store on site. Replace items found to be faulty or damaged immediately. Do not
delay job progress.

108 Scheduling
Deliver materials when the area is practically complete including floor coverings, wall and ceiling finishes,
painting and electrical installation.
Do not allow for covering workstation components to facilitate other trades working near or over them.
Comply with delivery and installation schedules.
Page 86 of 89 SECTION 12720 COMMERCIAL FURNITURE / WORKSTATIONS
109 Warranty
Provide a warranty covering the installation against faulty materials and installation for a period of 5 years.
Advise proprietor or owner of the voiding of the warranty if workstations are moved without the supplier’s
representatives present.

PART II MATERIALS200

201 Acceptable Manufacturers


Schiavello

202 Materials
A. Design of the system is determined by the location of the cable duct.

B. Refer drawings for panel sizes and configuration of each workstation.


C. Structural components of workstations:
extruded aluminium sections forming vertical and horizontal members and duct channels.
D. Trim: aluminium sections, extrusions and capping.
E. Fixings: concealed extruded clips connecting frames to each other.
F. Feet: adjustable steel.
G. Panels: SELECT FROM Medium density fibreboard (MDF) or metal or glass or marviplate.
H. Fabric:
Fabric backing: sheet foam plastic.
I. Hamper (overhead cupboard).
MDF carcase, faced with timber veneer or melamine, with/without lock on hinged or tambour (roller)
door.
J. Storage shelf: particle board, surfaced to match cupboards or hampers, with end brackets.
K. Paper storage unit: metal or MDF unit, screwed to underside or work top.
L. Storage cupboard: particle board, surfaced to match adjacent surfaces (melamine or veneer) with
internal shelves, filing racks, file pockets. Provide locks to doors.
M. Credenza: finish as for storage cupboard.
N. Pedestal: MDF carcase and drawer fronts, plastic drawers, with lock, with/without casters.
O. Worktops: 32mm thick particle board, laminate or timber veneer surfaces and edges.
Support for free ends: chrome plated steel with single foot or five way foot.
P. Task light: tubular metal casing for fluorescent light, colour to match adjacent metal. Fit diffusing screen
or reflecting louvres to underside. Secure to screen.
Provide lead to power source.
Q. Pinboards/Whiteboards:
Top hung, aluminium frame, powder coated.
R. Power, telephone, data duct:
1. Separate compartment or tray for each cable system. Outlets by system supplier for power and
telephone. Outlet for data, by data cable supplier. Duct cover: "snap on/off" metal panel powder
coated to match adjacent metal.
2. The entire power duct system is required to be capable of being earthed.
S. Power pole: compatible metal and finish extending from top of screen junction to ceiling.
T. Glazed panels: float glass, single or double glazed. Refer Trade Section 08800 Glass and Glazing.
U. Venetian blind: within double glazed partition.

V. Door and Frame: by workstation supplier.

203 Equipment
Supply tools necessary for site installation and adjustment of the completed installation. Supply touch-up paint
to match finish colours.

204 Finish
Powder coat or anodised finish to visible metal components before delivery.

205 Fabrication
Cut, fabricate and pre-assemble as much of the installation as possible in the shop before delivery. Reduce on-
site work to a minimum.

206 Source Quality Control


Allow for and provide facilities for inspection of fabrication procedures by architect during preparation.
Purpose of inspection is to ensure compliance of fabricated items with sample approved before ordering.

PART III EXECUTION300

301 Examination
Visit the site, inspect the conditions and compare them with the drawings.

Page 87 of 89 SECTION 12720 COMMERCIAL FURNITURE / WORKSTATIONS


Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.

302 Preparation
Provide polythene or building paper to surfaces which may be damaged by the installation.
Protect other installation, equipment and finishes.

303 Installation
Install components of the workstations in accordance with agreed layout, design, installation technique and
schedule. Ensure that horizontal surfaces are truly level throughout.

304 Earthing
Earth, in accordance with electric supply authority requirements, the power cable/duct system of each
workstation.

305 Inspection
Arrange for inspection by the architect at times nominated in the schedule.

306 Cleaning
Remove protection membranes. Clean surfaces. Remove and replace damaged materials. Touch-up scratched
or discoloured finishes as directed.

307 Completion
Complete the contracted work in accordance with contract documents and written variation order issued by the
architect.

PART IV FITTINGS & FIXTURES

Location/Description Details
General Mounting height and location on perimeter walls/in ceiling for soft-wired starter sockets is to
be located to suit the selected workstation system and is the responsibility of the builder.
The ‘Building’ contractor is responsible for final connection and certification of all soft wiring.
The ‘Building’ contractor is responsible for final connection and certification of all data.
All data points are to be supplied and installed as part of the ‘Building’ scope of
works.
Workstations will be installed following completion of partitioning.
The drawings are deemed to be diagrammatic in relation to position of fittings, ducting etc. It
is therefore the responsibility of the Furniture manufacturer to coordinate with all other
contractors to ensure that fittings and equipment are accessible and suitably located.
All fittings are required to be symmetrically located in relation to the building appearance and
other services.
Check all dimensions on site and verify details before ordering any materials or equipment
for the work.
No claims will be allowed for errors due to scaling off drawings or not verifying set out
dimensions on site.
Refer to attached Appendices for co-ordination.
Refer to drawing A260 for the position/location of all furniture.
Contractor to ensure all walls are setout in accordance with architectural drawings to suit
furniture.
Contractor to provide all power/data to suit furniture layout.

END OF SECTION

Page 88 of 89
APPENDICES

Following are the schedules for this specification:

Appendix 01 - Architectural Drawing List (Transmittal)

Appendix 02 - Colour and Finishes Schedule

Appendix 03 - FF&E Schedule

Appendix 04 - Furniture Schedule

Appendix 05 - Door Schedule

Appendix 06 - Door Hardware Specification

Appendix 07 - Insulation Specification Partition Batts

Appendix 08 - Insulation Specification 2

Appendix 09 - Autex Quietspace Specification

Appendix 10 - Bradford Soundsscreen

Appendix 11 - Niagra Sliding Door Specifications

Appendix 12 - Property Information

Appendix 13 - Client Artwork

Page 89 of 89 APPENDICES

You might also like