Professional Documents
Culture Documents
SPECIFICATION
University of Melbourne
PS‐002428 New Accommodation for
Melbourne Centre for Behaviour
This document is a strictly confidential communication to and solely for the use of the recipient and may not be
reproduced or circulated without Millar Architects’ prior written consent. If you are not the intended recipient, you
may not disclose or use the information in this documentation in any way.
TABLE OF CONTENTS
1. The Project
Refurbishment and fitout of existing offices at the University of Melbourne Parkville Campus.
2. The Contract
Fixed lump sum not subject to rise and fall.
5. Tender Documents
Refer to standard University of Melbourne Tender Documents.
6. Alternative Proposals
Submit tenders in accordance with the tender documents.
7. Exclusions / Assumptions
No exclusions or assumptions will be assumed or accepted unless specifically noted as part of the tender
submission.
9. Definitions
For the purposes of this Specification the following definitions shall apply:
Project Manager shall be the Superintendent (University of Melbourne Project Officer)
Builder shall be the Contractor
Proprietor shall be University of Melbourne
Architect shall be Millar Architects
19. Pre-nominated Contractors / Suppliers (Note: Contractors must submit a copy of pre-nominated
contractors quotations with their Tender submission)
Supply and installation fo AV services – Citadel Technology.
All furniture suppliers – refer to furniture schedule for supplier details.
All FF/E – refer to FF/E schedule for supplier details.
Door hardware – Lockwood.
END OF DOCUMENT
Warranty Requirements
A. The builder or other approved warrantors are to provide written warranties where so specified elsewhere in this
specification.
B. Each warranty is to be in approved form and will specifically include the provisions required in writing.
C. Warranty periods are to commence from the date of the Notice of Practical Completion.
E.
END OF DOCUMENT
Submit each certificate to the principal via the architect before commencement of work.
END OF DOCUMENT
2. Amount of Security
See DOCUMENT 00200 INFORMATION FOR TENDERERS, Annexure or Appendix to General Conditions of
Contract.
3. Interpretation of Drawings
Check dimensions on site before proceeding with the work of the contract. Notify architect of omission or
conflict in drawings and their relation to specifications.
*Hazardous materials in demolition waste, such as lead-based paint, asbestos, and polychlorinated biphenyls
(PCBs), are exempt from percentage calculations.
Note: dockets of deliveries of material to recycling centres will be requested.
7. Contractor’s Responsibility
The Contractor shall be responsible for ensuring that all operations and methods of construction, materials and
workmanship are safe, sufficient, and in accordance with the Contract documents. No inspection by the
Superintendent/Architect, and no instruction given or Certificate issued by the Superintendent/Architect shall be
deemed to imply that the Superintendent/Architect has assumed or taken over any part of the Contractor’s
responsibility as defined above.
The Contractor shall be solely responsible for the execution and completion of the Contract including all sub-
contracted and nominated suppliers/sub-contractors works, which shall be coordinated so that the Works
proceed without delay. The Contractor shall ensure that, in addition to items of the Works specifically
mentioned in the relevant sections, each trade shall assist, leave holes for, cut away for, do chasing and drilling
for, make good after, and arrange each work sequence with every other trade, in such a manner as to promote
the best interests of the Works as a whole.
The Statutory requirements of Work Cover, Occupational Health and Safety regulations, Payroll Tax
(where applicable) and Construction Industry Long Service Leave, PAYG Taxation, GST and
Redundancy Payment Central Fund are being met.
The provision of Workers Superannuation schemes, where agreed between employees / unions and
employers, are being met.
9. Industrial Relations
The Contractor shall work in accordance with the conditions of the appropriate State Building Industry
Agreement. Further the Contractor shall 8ecognize the following Code of Conduct and undertake to maintain a
good industrial record and to ensure that the Contractor and all Sub-Contractors engaged by the Contractor
will:
12. Materials
Unless otherwise specified, materials used throughout these Works shall be new, of good quality and be in
general conformity with the most recent Specifications and Codes of Practice laid down by the Standards
Association of Australia, where such exists or any amendments thereto. Defective materials shall be
immediately removed from the site or otherwise treated as directed by the Superintendent/Architect.
The stacking and disposal of materials and plant shall be orderly and done so as not to impose undue loadings
The contractor will be charged a re-design fee by the architect for alternate product selection and approval of
products that have not been ordered in time.
15. Scaffolding
For the safe and proper execution of the work, the Contractor shall provide and erect all necessary staging and
free-standing scaffolding in compliance with the relevant State Scaffolding Regulations. Obtain all necessary
permits. Protect adjoining works and adjoining property. Any damage shall be made good at the Contractor’s
expense.
The Contractor is to assume full responsibility for the general water tightness of the Building. The Contractor
must also promptly and without cost to the Proprietor, amend, correct, repair and/or restore any portion of the
Building which permits or has permitted the entry of water or damp or in the opinion of the
Superintendent/Architect is likely to do so.
The contractor is to take a photograph and record the meter reading at site handover and provide this proof to
the Project Manager/Architect within 14 days.
The Contractor is to reimburse the owner for all power usage during the contract period.
27. Water
Provide potable drinking water and adequate signage if relevant to identify same, and maintain a temporary
water supply sufficient for executing the work under the contract. Disconnect and clear away same on
completion and pay costs and charges in connection therewith. Provide tapping of main supply if required.
The contractor is to take a photograph and record the meter reading at site handover and provide this proof to
the Project Manager/Architect within 14 days.
The Contractor is to reimburse the owner for all water usage during the contract period.
Fix architect’s sign (supplied by Architect) to site entrance. Remove same from site and return to architect on
completion of works.
Confined excavation:
Definition: Excavation of trenches and to broader areas less than 1000 m2 in extent.
Classification:
Classify material as non-rippable if any of the nominated classes of crawler excavator fitted with a heavy duty
bucket, cannot rip at a production rate (in situ volume) exceeding the nominated values. Fit bucket teeth with
high penetration boots, approved by the machine manufacturer for use on the particular machine in rock.
Class 55 crawler excavator fitted with a maximum 450 mm wide bucket:
Maximum production rate 1.5 m3 per hour.
Class 85 crawler excavator fitted with a maximum 600 mm wide bucket:
Maximum production rate 3 m3 per hour.
Class 115 crawler excavator fitted with a maximum 750 mm wide bucket:
Maximum production rate 4.5 m3 per hour.
Class 155 crawler excavator fitted with a maximum 900 mm wide bucket:
Maximum production rate 7 m3 per hour.
Class 200 crawler excavator fitted with a maximum 1050 mm wide bucket:
Maximum production rate 10 m3 per hour.
Other excavation:
Classification:
Classify material as non-rippable if the nominated classes of crawler tractor, equipped with a heavy duty, single
tine parallelogram ripper (approved by the machine manufacturer for use on the particular machine in rock),
cannot rip at a production rate (in situ volume) exceeding the nominated values.
Class 150C crawler tractor: Maximum production rate of 50 m3 per hour.
Class 200C crawler tractor: Maximum production rate of 75 m3 per hour.
Class 300C crawler tractor: Maximum production rate of 90 m3 per hour.
Class 400C crawler tractor: Maximum production rate of 105 m3 per hour.
Class 500C crawler tractor: Maximum production rate of 120 m3 per hour.
Class 600C crawler tractor: Maximum production rate of 135 m3 per hour.
40. Dimensioning
Do not scale drawings which are clearly diagrammatic and/or marked ‘not to scale’ or NTS.
As-built documentation
Where required in the Specification, the Contractor must submit to the Superintendent comprehensive, detailed
as-built documentation before the Date of Practical Completion. As-built documentation must include positions
of concealed work, penetrations, services, ducting and associated equipment, access and inspection points,
valves, controls and the like which may require later access. The exact position and route of underground
piping as actually laid must be located, by dimensions from boundaries, buildings and other fixed points.
As-built documentation must include accurate measurements and directions from permanent visible items to
locate concealed items. As-built documentation must be suitable for use by the Principal for long term
operations and maintenance. As-built documentation must include:
Relevant documents from the Contract or shop drawings certified as as-built documentation where no
differences occur.
Relevant modified documents from the Contract or shop drawings where work which differs from the
Contract and approved shop drawings.
Additional drawings as required.
The position of valves, branches, inspection openings and the like, dimensioned and checked by the
builder before the work is covered up.
Record on the drawings the invert levels of drains and other relevant piped services.
Variations in position of size of the pipes, valves and the like within the building.
Photographs of concealed work that may require maintenance.
Final survey
The Contractor must submit to the Superintendent the Contractor’s licensed surveyor’s certification of the final
set-out and position of the Works.
55. Warranties
Provide written warranties as set out in DOCUMENT 00630 WARRANTIES.
58. Asbestos
No asbestos products or asbestos based materials are to be used in any part or parts of this building or its
services and the builder is to ensure that sub-contractors, nominated sub-contractors, suppliers and others are
advised of this restriction.
END OF DOCUMENT
1. Compliance
The contractor is to prepare an Occupational Health, Safety and Environmental Management Plan for the
works that complies, as a minimum, with statutory and other legal requirements of the locality the works are to
be undertaken in, including all licensing, permits, fees, charges, etc. relevant to the works they will undertake
and
The contractor is to develop a “Hazard and Risk Register” for the construction phase of the project and:
Include all hazards/risks they have identified as possible, during the conduct of the construction
phase, and
Rate each hazard/risk level. Where the risk is greater than a first aid injury or minor illness…
Identify and include specific controls to reduce the risk so the consequence is minor injury or illness
and …
Re-assess the risk after the introduction of the control so as to ensure the selected control will be
effective in preventing identified injury or illness in the relevant hazard/risk identified and…
Identify and document how the hazards and risks, as identified, will be monitored and reviewed, and
the frequency of such monitoring and review, during the conduct of the works on the project
The contractor is to include, where applicable the following hazard categories and associated risks as a
minimum in the “Hazard and Risk Register”:
Working at height and at same level.
Working in excavations and trenches.
Working on or near essential services, including electricity, gas, telecommunications, water, sewer
etc.
Delivery, storage, decanting, use and disposal of a hazardous chemical/substance.
Delivery, unloading/loading, servicing, maintenance use and repair of plant.
Using a confined space.
Activities generating excessive noise, manual and materials handling risks.
Asbestos and demolition works.
Other categories of hazards, as included in the relevant Occupational Health, Safety and
Environmental Act, Regulation, Policy, Code of Practice, Australian Standard etc.
The contractor is to prepare “Safe Work Method Statements (SWMS)”, or equivalent, so as to control identified
hazards and risks documented in the “Hazard and Risk Register”, in consultation with workers, or providing
training to workers, in the way they will undertake the work, so as to prevent injury or illness during the conduct
of the works. Controls will include the requirements of any Regulation, or where no regulation exists, controls to
be equal to or better than a Code of Practice, Australian Standard, Ministerial Notice, statutory or industry alert,
relevant to the identified hazard and risk,
The contractor shall provide supervision, training and instruction, as relevant, to all affected workers on the
project, so as to ensure that during the conduct of the works the potential for injury or illness, as identified in the
“Hazard and Risk Register”, and documented in “Safe Work Method Statement” is minimised to an acceptable
level.
The contractor is to, at the completion of the project, provide a copy of all identified and unresolved hazards
and risks that remain to be controlled by the end user or end user servicing, maintenance or repair personnel,
so that they are not put at risk by the completed project.
2. Formal Occupational Health, Safety and Environmental Management Systems and Procedures
The contractor is to provide evidence of certification of occupational health, safety and environmental to a
minimum of AS/NZS 4801 Occupational Health and Safety Management Systems and AS/NZS ISO 14000
Environmental Management Systems.
3. Evidence
Provide evidence with tender of means by which the above item 1, is to be implemented and evidence of the
business accreditation to AS/NZS 4801 Occupational Health and Safety Management Systems and AS/NZS
ISO 14000 Environmental management systems as per item 2.
4. Submissions
Develop and submit, prior to commencing work on the project, a copy of the contractors:
Occupational Health Safety and Environmental Management plan, and
Hazard and Risk Register, and
Safe Work Method Statement, and
5. Hazardous Materials
The Contractor must not use any building materials that contain any of the following:
Asbestos
Cadmium
Chlorinated Polyethylene and Chlorosulfonated Polyethlene
Chlorofluorocarbons (CFCs)
Chloroprene (Neoprene)
Formaldehyde (added)
Halogenated Flame Retardants
Hydrochlorofluorocarbons (HCFCs)
Lead (added)
Mercury
Petrochemical Fertilizers and Pesticides
Phthalates
Polyvinyl Chloride (PVC)
Wood treatments containing Creosote, Arsenic or Pentachlorophenol
END OF DOCUMENT
END OF SECTION
PART I GENERAL100
101 General
Comply with Statutory requirements for demolishing work, supervisors, workers and to the approval of the
Principal Certifying Authority.
Provide all temporary works on site such as structural, sediment controls and dewatering. Protect adjacent
properties.
Demolish all sections of the built environment including services as shown in the specification and described
within the architectural and services engineers documentation.
Provide work as follows:
A. Scope
The work of this section includes but is not limited to the following items:
Provide and manage all demolition works including:
Identification of existing services including type of service, depth of service and location of service, co-
ordinate required termination, alteration or protection of services as per service provider requirements,
detail same on a site plan and provide a copy to the architect and other trades or activities undertaking
work at the project. Note that all work is to be in “as found” condition.
Ensure all underground and overhead services that could be affected by the demolition works are made
safe and or terminated in compliance with service owner. Include all relevant service provider
requirements in documentation and control processes and procedures.
Investigate site conditions and provide all temporary site works prior to commencing demolition
Examine documents: examine parts of the drawings and this specification for requirements which affect
the work of this section. In particular, take note of related work. Where Hazardous Materials Report and
the Geotechnical Report are enclosed, these are provided for general information only and the builder is
to evaluate site conditions and remove all material in as found condition.
B. Examine documents: examine parts of the drawings and this specification for requirements which affect
the work of this section. In particular, take note of related work.
C. Ensure only competent and approved persons, working under compliant business licence for the class
of demolition, are employed and perform in accordance with statutory requirements.
D. Provide copies of all relevant documents,eg. Asbestos clearance certificate, Dilapidation report, burial of
waste and other certifications, in accordance with requirements by statutory bodies having jurisdiction.
E. Cleaning the site thoroughly on completion.
104 References
Comply with applicable portions of the following Australian Standards:
AS 2187 Explosives - Storage, transport and use.
2187.2 2006 Use of explosives. There are 4 other parts, 1998 – 2006.
AS 2436 2010 Guide to noise and vibration control on construction, demolition and maintenance
sites.
AS 2550.1 2011 Cranes, hoists and winches – Safe use - General requirements
AS 2601 2001 Demolition of structures.
AS 4687 2007 Temporary fencing and hoardings.
AS 4970 2009 Protection of trees on development sites.
Comply also with the requirements of applicable building regulations, environmental requirements, statutory
and local authority having jurisdiction, including local council.
107 Services
Before demolishing and removing parts of building having essential services installed, ie.electrical or other
wiring, gas and water pipes, tanks, conduits or similar items embedded in them, notify the architect, owners of
services, authorities having jurisdiction, and make sure that these items are out of service so that they can be
removed without danger. Dial before you dig where required. Divert services and provide temporary services to
the work to the approval of the supply authority.
PART II MATERIALS200
202 Equipment
A. Supply equipment required to perform the work of sufficient capacity to meet the time schedule.
B. Provide suitable, approved, if relevant, disposal containers that prevent a spill to the environment for
disposal required.
C. No containers may be located on public streets or pavements without obtaining required municipal
permits for same. Co-operate with sub-contractors doing work in or near container locations to prevent
disruption of their work.
303 Shoring
Provide necessary shoring in accordance with structural engineering instructions.
Alter, adapt, and maintain temporary works as necessary, and strike or withdraw them progressively as the
work proceeds. Obtain the written consent of the architect/structural engineer if such works are to be left in
position at the completion of the work.
306 Reinstatement
Restore to original condition, without expense to the proprietor, any damaged parts of the remaining
construction resulting from failure to provide adequate protection. Refer also clause 105.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Leave the site in an entirely clean condition, ready for the work of other trades.
Location/Description Details
General The Contractor is to visit the site and ascertain/confirm exact conditions and include all
allowances as required for demolition in order to achieve new conditions (including all
associated rectification works). This includes redirecting/ sealing existing services etc.
The Contractor is to include protection of adjoining works and existing buildings areas to
remain during demolition including hoarding, dust sealing (polyurethane with taped joints) so
that minimal disruption occurs. Include all Scaffolding as required to complete the works.
Refer Services Consultants Drawings for cutting and sealing of services where applicable.
Builder is to include to protect adjoining works and existing buildings to remain during
demolition including hoarding, dust sealing (polyurethane with taped joints) so that minimal
disruption occurs. Include for all Scaffolding as required to complete the works.
Remove all rubbish and debris from site.
The Builder is to provide a photographic dilapidation report capturing all existing foot paths,
road surfaces, fences, etc within the vacility of the works prior to start of demolition works.
One copy to be given to the Project Manager.
Delapidation Report The Contractor is to provide a photographic dilapidation report prior to start of demolition
works. One copy is to be provided to the Project Manager.
The dilapidation report is to include all areas of delivery, loading, movement of materials,
shared spaces, etc.
Existing Building All demolition works are to be carried out in such a manner so to cause minimum disruption
to occupants in adjacent occupied areas within the building. Provide hoardings, dust stop
etc. to the Project Managers approval to all affected corridors and entry points.
Provide temporary site signage to all entry areas, including the Site Manager’s contact
details.
All items not required by the proprietor shall become the property of the builder and shall be
removed from site. All other items shall remain unless otherwise noted.
Existing Floor All existing floor finishes (Carpet, Vinyl, Etc) are to be removed and surface to be prepared
Finishes to a standard acceptable to the new covering manufacturer’s specifications
All existing glue is to be fully ground off.
All blemishes and inconsistancies to be filled and smoothed.
Construction The Contractor is to submit a construction management plan to the Project Manager for
Management Plan approval prior to the commencement of works confirming the location of the Contractor’s site
office, method for material delivery, any hoardings/fencing and access arrangements.
Hoarding The Contractor is to include protection of adjoining internal occupied areas and existing
buildings to remain during demolition including provision hoarding, dust sealing/protection to
ceilings (polyurethane with taped joints) so that minimal disruption occurs. Include for all
Page 23 of 89 SECTION 02050 DEMOLITION
Scaffolding as required to complete the works.
Provide minimum 2 metre high solid hoarding (marine grade ply or similar approved) to the
full length of the building site. The hoarding must be maintained throughout the duration of
the works and removed by the Contractor on completion.
Redundant Services Refer Services Consultants Drawings for cutting and sealing of services where applicable.
Ensure that the redundant sewer and water service connection points in the existing
facilities/ amenities to be demolished and capped and sealed nom. 300mm below ground
level.
Hazardous Material All hazardous materials including asbestos are to be removed from areas affected by
Removal demolition works by a certified contractor. Refer to the Division 6 report appended to the
architectural specification for all building elements identified or presumed to contain
hazardous materials. The contractor is to make allowance for all relevant removal works in
their tender, including the provision of a work method statement and plan to be approved by
Client and Project Manager prior to undertaking any works. It is the tenderer's responsibility
to inspect the space during the tender and review the report to make necessary allowance
for all works.
END OF SECTION
Page 24 of 89
SECTION 03530 CONCRETE SCREEDS (GRANOLITHIC)
PART I GENERAL
101 Scope
Supply and install a complete installation of granolithic surface screeds to the extent and thickness as indicated
on drawings or scheduled including but not limited to:
Applied granolithic screeds.
Matching coves, risers, kerbs, margins, pit covers, etc.
Float screeding, curing and protection.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1379 2007 Specification and supply of concrete. Plus Supplement 1-2008.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip hazards.
AS 3700 2011 Masonry structures. There is 1 Supplement 2012
AS 3740 2010 Waterproofing of domestic wet areas. 1 Amdt, 2012.
AS 3799 1998 Liquid membrane-forming curing compounds for concrete.
AS 3972 2010 General purpose and blended cements.
HB 197 1999 An introductory guide to the slip resistance of pedestrian surface materials.
Where relevant, comply with construction standards and notes published by the Cement Concrete and
Aggregates Association of Australia , www.concrete.net.au
105 Submissions
Where applicable, provide evidence of payment of relevant fees.
PART II MATERIALS
204 Mixes
A. Mix screeds with minimum water to produce screed material that is workable and will consolidate
uniformly. The proportion will depend on the sand in use and is found by practical trial. Minimise random
variations once the proportions are established. Carefully control water quantity.
B. Granolithic finish mix: 1:2:1 cement: stone: sand.
C. Protective screed mix: 20 MPa concrete with maximum aggregate size of 6mm.
D. Batching by shovelful is not allowed. Batch by weight only.
Add pigment as instructed by manufacturer to a sample colour approved by the architect.
E. Waterproofing: add mixture. Refer section 07130 WATERPROOFING AND TANKING, System Type D.
301 Examination
Visit site and inspect conditions to drawings before delivery of materials to site. Notify contractor of any
discrepancy or unsuitability or substrate.
Start of work means total acceptance of conditions.
302 Records
Obtain essential services information (Dial Before You Dig).
303 Preparation
Before commencing work, ensure that the concrete is clear and free of mortar, honeycombing, surface cavities,
oil, tying wires or other surface deficiencies and is suitable to receive the membrane.
Sweep up all debris.
Roughen surface of existing surface to ensure adequate key for granolithic.
305 Screeds
A. Dense screeds: thickness of not less than 25mm, except 20mm at outlets. Reinforce with light
galvanised steel mesh. Refer clause 201 G.
B. Protective screeds: 50mm thick parallel to substrate.
Reinforce with light galvanised steel mesh. Provide control joints as specified in clause 305D. Dust on
and trowel in bluestone fines.
C. Setdowns: for screeds to receive other finishes, consult with other sub-contractors for those finishes to
determine the setdown required.
D. Walls and upstands: finish at junction with walls and upstands with galvanised wire mesh and 50mm
radius cove.
307 Tolerances
A. Tolerances to grades established on drawings: + 5mm, -5mm
B. Local variation from a flat surface: not to exceed +3mm -3mm under a 3 metre straightedge, with 6mm
"feet" on each end so variations can be measured from the surface to the straightedge.
308 Curing
General: protect from premature drying and excessively hot or cold temperatures. Where required, provide
damp curing.
Where alternate finish and installation is approved by the architect add in 2 successive applications, worked
into the surface by trowelling to smooth dense finish.
312 Protection
Lay hardboard over completed work for minimum of 5 days.
313 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Clean up leaving the surfaces in first class condition to the satisfaction of the architect.
PART IV DETAILS
Location/Description Details
Screeding Provide concrete bulkfill and screeding to concrete slabs to all areas in scope/affected
by demolition and building works to achieve a smooth and level finished floor.
Tenderersare to allow for a minimuim 10mm thickness of screed/ardit to all areas
receiving new floor finishes in tender pricing. Bulkfill to setdowns to demolished brick
and blockwork walls must be allowed for within tender submissions.
All general screeding to be Ardex or similar approved product.
Provide full infill screeding to the existing slab recessed tracks to the existing
compactus to be demolished.
END OF SECTION
PART I GENERAL100
101 Scope
Supply all labour and material, services and equipment necessary for the preparation, application and finishing
of metal surfaces as indicated on drawings, schedules and as specified herein, to internal and external metal
surfaces as follows:
Refer Schedule of Finishes.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1231 2000 Aluminium and aluminium alloys - Anodic oxidation coatings.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS 2832 Cathodic protection of metals. There are 5 parts, 2003 – 2008.
AS 3715 2002 Metal finishing - Thermoset powder coating for architectural applications of
aluminium and aluminium alloys.
105 Submissions
Submit the following materials:
A. Product literature on all proposed finishing systems.
B. Colour samples for all approved finishing materials. Provide samples identified with:
1. Manufacturer's colour code and colour name.
2. Match to schedule colour code and name.
C. Samples not less than 100 x 100mm and of the same gloss level as the scheduled colour.
107 Warranty
Provide a written warranty stating the preparation of surfaces, materials and material application under this
contract will show no deterioration and remain in good condition for a period of 7 years from date of Practical
Completion.
PART II MATERIALS200
301 Examination
Inspect all surfaces and determine that they are in proper condition to receive the work to be performed under
this section.
The starting of work under this section means acceptance of such surfaces as being satisfactory and any
defects in work resulting from accepting poor surfaces are to be corrected at no cost to the proprietor.
302 Preparation
A. General: prepared to a standard not less than that described in AS 1627.
B. Clean base metal surfaces of all mill scale, rust, grease, oil, dirt or other foreign matter then properly
wash with spirit or other approved cleaning agents.
After cleaning, etch, pickle or prepare as recommended by manufacturer of the finish applied.
303 Protection
Protect finished metal surfaces as necessary during handling, transport and erection to prevent mechanical
imperfections such as scratches, scrapes, dents, spots, stains and streaks.
Do not use adhesive protective coating. Protect by other means with the approval of the architect.
304 Application
Execute all work in this section in strict compliance with the manufacturer's recommendations and with the
provisions of the Australian Standards which are incorporated by reference as part of this specification and
apply to the work in this section to same extent as if written herein. In the event of conflict between
manufacturer's recommendations and the provisions of the Australian Standards, manufacturer's
recommendations govern.
305 Cleaning
At completion of work, keep and maintain finished surfaces clean and free from dust, dirt and other foreign
matter.
306 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued by the
architect.
PART IV DETAILS
Location/Description Details
Colour Refer to Appendix 02 Finishes Schedule for colour and finish.
END OF SECTION
Page 29 of 89
SECTION 05500 METALWORK
PART I GENERAL100
101 Scope
Supply, engineer and install required general and architectural metalwork items including but not limited to:
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1554 Structural steel welding. There are 7 parts, 1994 – 2012.
AS 1627 Metal finishing - Preparation and pre-treatment of surfaces.
1627.6 2003 Chemical conversion treatment of metals.
There are 6 other parts, 1997 – 2005.
AS/NZS 1734 1997 Aluminium and aluminium alloys - Flat sheet, coiled sheet and plate.
AS/NZS 1866 1997 Aluminium and aluminium alloys - Extruded rod, bar, solid and hollow shapes.
AS 4100 1998 Steel structures. Plus 1 Supplement 1999, 1 Amdt 2012.
AS/NZS 4673 2001 Cold-formed stainless steel structures.
AS/NZS 4680 2006 Hot-dip galvanised (zinc) coatings on fabricated ferrous articles.
Comply with requirements of statutory and local authorities.
106 Samples
Sample welds: if requested, provide samples of weld types, including samples of railings joined at right angles
and at typical acute angles, welded and ground smooth, for approval. If not acceptable, provide additional
samples until approved. Approved samples establish quality of similar work of this section.
Check on delivery: request architect to check materials on delivery to site for quality, and materials not meeting
the requirements of this specification or equal to approved samples will be rejected.
Return rejected materials to the fabricator at the fabricator's expense.
Finish: provide samples of specified finishes when requested.
PART II MATERIALS
201 Materials
Refer to Fixtures and Fittings Schedule, as well as Architectural, Structural and other consultant drawings.
202 Finish
Materials exposed to weather may be either:
Mild steel - hot dipped galvanised after fabrication or chromate pre-treated followed by polyester powder
coating.
Finish internal steel after fabrication with zinc-rich organic primer, or with inorganic zinc silicate paint.
Comply with relevant codes of practice or manufacturers' recommendations.
205 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required for a
complete installation.
Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the item is
to be secured. Refer to architect if in doubt.
Fasten galvanised items with galvanised fasteners.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure conditions
are satisfactory for installation. Arrange for rectification required.
Start of work means total acceptance of relevant conditions.
302 Preparation
Field measurements: do not delay job progress. Allow for adjustments and fitting of the work in the field where
taking of measurements might cause delay.
Co-ordination with work of others: furnish to each relevant trade foreman anchorages and setting drawings,
diagrams, templates and instructions for installation of items having integral anchors which are to be embedded
in concrete or masonry construction. Co-ordinate delivery of such items to the project site.
304 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or relevant Australian Standards,
Anchorage: except for anchorages furnished herein but placed by other trades, set and secure necessary
anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as needed.
Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper positioning of
completed work.
Fit: during installation and assembly, form tight joints with exposed connections accurately fitted, and reveals
uniform. Finish work accurately, plumb, level, square and true in reference to adjacent construction. Make
tolerances conform to Australian Standards.
Finish: do not cut or abrade shop finishes which cannot be completely restored in the field.
The use of gas-cutting torch in the field for correcting fabrication errors will not be permitted under conditions.
Fabrications may be cut shorter with power hacksaws on site.
306 Protection
Cover work: immediately following installation, wrap or cover architectural metalwork to avoid wear and tear of
finish during subsequent construction.
307 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
PART IV DETAILS
Location/Description Details
General Refer to Appendices - Fitting and Fixtures Schedule for additional specifications
To be read in conjunction with Door and Door Hardware Schedule.
All wall hung fixtures and fittings including handrails and WC back rests shelves are to be
fixed directly to suitable timber studs located specifically for such support. Studs to be
located with 'stud finder' prior to installation of fixture.
Floor Transition Strip Builder to allow to install transition strips between all dissimilar floor materials, to be located
at the centre of the door in the closed position. Provide DTA Australia ACCP18.33MS in matt
Aluminium or similar approved. Sample to be installed in one location for architect approval
prior to proceeding with general installation.
Skirtings Supply and install 150mm high powdercoated skirting (colour as scheduled) to all new and
existing walls, columns etc…
All moudline skirting is to be 150mm high powdercoated as scheduled.
Vinyl to Carpet At vinyl to carpet transitions, install ‘DTA Australia’ Aluminium vinyl transition.
Transition Locally building up screed for vinyl flooring to to match height of carpet to achieve a flush
finish.
Builder to inspect and measure carpet prior to ordering.
Fire Extinguishers Supply and install fire extinguishers adjacent to switchboards and/or locations as required by
MFB and other relevant authorities. Confirm final location on site with Architect.
Fire Smoke Seals/ All penetrations through fire rated walls and slab are to be fire sealed.
Collars Provide fire rated mechanical dampers as noted on the mechanical engineer’s drawings.
Provide sealants, smoke blankets etc. to achieve this.
Refer Services Engineer’s details for more information.
END OF SECTION
PART I GENERAL
101 Scope
Provide materials and labour, equipment and services and perform operations necessary to complete the
carpentry as indicated and specified. Include nailers, blocking, furring, grounds, hardware, framing, shoring,
bracing, ramps, scaffolding and barriers required by the drawings and construction.
102 Related Work Co-operate and co-ordinate with the following trades:
Include in each prototype elements required by this specification, and finish in every respect. When approved
by the architect, such samples remain part of the work and become the standard for the remaining work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS 1684 Residential timber-framed construction. There are many parts and Supplements,
1999 - 2010.
1684.2 2010 Non-cyclonic areas. Numerous supplements, 2 Amdmts 2012
and 2013
1684.3 2010 Cyclonic areas. Numerous supplements, Amdmt 2012
1684.4 2010 Simplified - Non-cyclonic areas. Special reprint with Amdmt 1
2012 included
AS 1720 Timber structures.
1720.1 2010 Design methods. Plus 2 Amdts, 2010 - 2011.
1720.2 2006 Timber properties. Plus 1 Amdt, 2006.
1720.4 2006 Fire-resistance for structural adequacy of timber members.
AS/NZS 1859 Reconstituted wood-based panels - Specifications
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt, 2009.
There is 1 other part, 2004.
AS 1860.2 2006 Particleboard flooring – Installation. Plus 1 Amdt, 2010.
AS/NZS 2904 1995 Damp-proof courses and flashings. 2 Amdmts, 1998, 2013
AS 3959 2009 Construction of buildings in bushfire-prone areas. Plus 3 Amdts, 2009 - 2011.
AS 4055 2012 Wind loads for housing.
AS 4226 2008 Guidelines for safe housing design.
AS/NZS 4364 2010 Timber – Bond performance of structural adhesives.
AS 4786.2 2005 Timber flooring - Sanding and finishing.
HB 44 1993 Guide to AS 1684 1992, The National Timber Framing Code.
Further advice and changes in specifications of timber are needed frequently. For latest information visit
www.timber.net.au
For timber decks visit the Outdoor Timber section of Resources at www.timber.net.au.
105 Submissions
Submit the following prior to ordering materials:
Product literature on hardware items proposed.
Technical data on melamine laminates proposed for use.
Technical data and samples of substrate materials (particleboard etc.) Thickness of materials at typical
locations and functions.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Start of
work means total acceptance of conditions.
304 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
General All carpentry timbers shall conform with the description, strength groupings and gradings of
the relevant Australian standard specifications. Stress gradings shall conform with the
requirements of the current Australian standard and shall be selected to suit timber size
indicated on the drawings.
Termite Protection All timber used in construction is to be ‘Hyne - T2 Termite Resistant Timber’ (or similar
supplier).
Timber Framed Walls Include to supply and install timber stud with 13mm Plasterboard (standard,
(Internal) acoustic/soundcheck or moisture resistant as nominated) lining to both sides, with skirting as
indicated.
Studs @ 450 ctrs max.
Studs to be 90 x 35 F5 MGP including noggings to AS1684. Max height 3000mm (non load
bearing), unless shown differently on Structural Engineers Details.
Bottom and top plates 90 x 45 F5 MGP, unless shown differently on Structural Engineers
Details.
Provide boxed (double) studs of timber blocking to support loads – shelving, joinery,
cupboards etc.
Provide double studs to sides of all openings.
Load bearing walls to Engineer’s details.
Bulkheads where Include to Supply and install 16mm MDF bulkheads as detailed in architectural
Required documentation.
Cut and Seal all MDF edges prior to plastering and painting.
Engineered timber Engineered timber to have low formaldehyde content.
Adhesives and Adhesives to be Low VOC
Sealants
Steel Stud Framed Supply and install Rondo (or equiavelnt) steel studs (generally 92, 76 or 64mm - refer
Walls (Internal) to architectural drawings) at 450mm or 600mm centres, 1.15 BMT, with 13mm flush
plasterboard (standard, acoustic/soundcheck or moisture resistant as nominated)
linings to both sides, with skirting as indicated on the architectural drawings. Install
Page 34 of 89 SECTION 05500 METALWORK
studs in accordance with manufacturer’s installation instructions– refer to structural
engineer’s details for structural tie or plywood bracing backs for AV elements.
All studs generally at @ 450 ctrs max., unless noted at 600mm centres on the
drawings.
Supply and install 28mm steel furrning channels to existing walls with 13mm flush
plasterboard (standard, acoustic/soundcheck or moisture resistant as nominated)
linings to one side where indicated on the drawings. Furring channels to be @
450mm ctrs max.
Provide boxed (double) studs of timber blocking to support loads – shelving and
joinery etc.
Provide double studs to all sides of all openings, doors, etc…
Bulkheads where Include to Supply and install flush 13mm plasterboard bulkheads as detailed in
Required architectural documentation. Frame bulkheads with 90x45mm timber studs or 64mm
steel studs at 450mm centres.
Cut and Seal all MDF edges prior to plastering and painting.
END OF SECTION
PART I GENERAL
101 Scope
The scope of work includes, but is not limited to, the supply and installation of thermal insulation.
It also includes the supply and installation of acoustic insulation.
104 References
Comply with the applicable portions of these Australian Standards:
AS 1366 Rigid cellular plastic sheets for thermal insulation. There are 4 parts, 1989-1992, and
2 Amdts, 1992 - 1993.
AS/NZS 2107 2000 Acoustics - Recommended design sound levels and reverberation times for building
interiors.
AS 3671 1989 Acoustics - Road traffic noise intrusion - Building siting and construction.
AS 3999 1992 Thermal insulation of dwellings - Bulk insulation - Installation requirements. 1 Amdt,
2012
AS/NZS 4200 Pliable building membranes and underlays.
4200.1 1994 Materials. Plus 1 Amdt, 1994.
4200.2 1994 Installation requirements.
AS/NZS 4859.1 2002 Materials for the thermal insulation of buildings - General criteria and technical
provisions. Plus 1 Amdt, 2006.
Comply with the requirements of the Building Code of Australia.
105 Submission
Provide to the architect before ordering, samples, literature and technical data of each specified material.
PART II MATERIALS
B. Vapour barriers - with and without reflective facings - paper/foil, high density polyethylene breather
membranes, aluminium foil reinforced or folded as batts.
203 Materials–Acoustic
A. Acoustic insulation (attenuation type) with or without facings - flexible polyurethane foam, polyester
blankets, glass and mineral wool batts, plasterboard.
B. Acoustic insulation (absorption type) with or without facings, reinforcement - suspended mineral fibre
ceilings, mineral tiles, perforated fibre cement sheet systems, and panels, metal pans and strips with or
without absorption batts, suspended baffles sound barriers, sprayed texture finishes of plaster, cement
or vermiculite.
301 Examination
Visit the site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Start
of work means total acceptance of conditions.
302 Preparation
Prepare surfaces and/or framing material and ensure that no obstructions will prevent rapid and effective
installation.
305 Cleaning
Remove surplus material on completion and arrange for inspection(s) by manufacturer’s representative.
306 Completion
Complete contracted work in accordance with the contract document and written variation orders issued by the
architect.
Location/Description
Details
General The ‘top edge’ of plasterboard wall lining above the ceiling line is to be sealed to create airtight
thermal air pocket against wall.
All Internal Down Pipes, Sewer Risers, Etc to be fully lagged with acoustic insulation.
All Amenities, Offices, Boardrooms, Lunch Room, Tea Points Meeting Rooms etc…
ACOUSTIC INSULATION
Walls All walls surrounding Amenities, Meeting room & Private offices to have full height insulation to
underside of ceiling tiles above.
All walls surrounding Conference Rooms, Boardrooms and Call Centre to have full height
insulation to underside of floor slab above. Provide mastic for sealing junction between top of
walls and slab.
CSR Bradford (75mm thick, 14kg/m2) Glasswool Partition Batts
Where walls do not extend full height, provide 1200mm wide Autex Greenstuff Baffleblock or
equivalent insulation from the ceiling level to the roof above. Allow to cut and seal around all
in ceiling services penetration.
Ceilings CSR Bradford 115mm thick gold ceiling batts.
Lay a full batt 600mm to either side (1200m overall) of all office perimeter walls
Acoustic Wall Allow to supply and install direct stick 25mm Autex Quietspace fabric acoustic wall panels as
Panels noted on the architectural drawings and schedules. All specified fabrics and panels to be
professionally cut by an Autex recommended contractor and all edge are to be fully fabric
wrapped – no exposed edges. Colours as scheduled. Refer to finishes plan and elevations for
location and extent.
END OF SECTION
PART I GENERAL100
101 Scope
Design, fabricate and install materials with required components, fixings, fabrication techniques, coatings and
finishes including but not limited to:
104 References
Comply with applicable portions of the following Australian Standards:
AS 1530 Methods for fire tests on building materials, compounds and structures.
There are 7 parts, 2 Amdt, 1992 – 2007.
AS 1603 Automatic fire detection and alarm systems. There are 12 parts 1996 – 2011 and 4
Amdts, 1996 – 2001.
AS 1670 Fire detection, warning, control and intercom systems, system design, installation
and commissioning. There are 4 parts, 1997 – 2004, plus 1 Amdt, 2005.
AS 1682 Fire Dampers.
1682.1 1990 Specification.
1682.2 1990 Installation.
AS 2118.4 Automatic fire sprinkler systems
AS 3784.1 1990 Coatings for fire protection of building elements – Guide to selection and installation
of sprayed mineral coatings.
AS 3959 2009 Construction of buildings in bushfire-prone areas. Plus 3 Amdmts 2009-2011
AS 4072.1 2005 Components for the protection of openings in fire-resistant separating elements –
Service penetrations and control joints. Plus 1 Amdt, 2006.
AS 5414 2012 Bushfire water spray systems
Bushfire Set 2009
HB 37.4 1994 Handbook of Australian fire Standards – Building materials, products and
construction.
108 Warranty
Provide to the architect a written warranty stating that components of the complete installation will remain intact
and in a satisfactory condition for 5 years from the date of Practical Completion.
PART II MATERIALS200
204 Fabrication
A. Provide and fabricate frame and support structures.
B. Check site dimensions before fabrication of components. Tolerances are not to exceed +3mm, -3mm.
C. Schedule fabrication in accordance with contractor's construction program.
D. Mark each item for easy identification.
301 Examination
Examine conditions at the site before delivery of materials and prior to the commencement of installation.
Arrange with contractor for correction of non-optimum conditions.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Protect by appropriate means adjoining surfaces of the building which may be damaged during the installation.
303 Installation
Install/apply all fireproofing materials in locations as instructed and as detailed on the documents. Secure in
final position.
Comply with supplier's/manufacturer's installation recommendations.
304 Sealants
At junctions with other materials, insert into opening a backing rod, wedged firmly in place. Apply over the
backing rod an approved fireproofing sealant, to colour selected by the architect.
Comply with supplier's/manufacturer's installation recommendations.
306 Repairs
Repair damaged surfaces which may have been damaged during installation.
Page 39 of 89 SECTION 07810 FIREPROOFING
Make good the surfaces and reinstate material integrity, all in strict accordance with manufacturer’s
instructions.
307 Protection
Protect the installation until completion of the project. Prevent damage to completed work by necessary means.
308 Cleaning
On completion, clean up debris, remove support structures, scaffolding and the like. Leave work and surfaces
in entirely clean and uniform condition.
309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
END OF SECTION
Page 40 of 89
SECTION 08200 DOORS AND DOOR FRAMES
PART I GENERAL100
101 Scope
Supply and install timber doors and timber [or steel] door frames including but not limited to:
A. EXTERNAL DOORS
Timber doors in timber frames (jambs).
Timber doors in metal frames (jambs).
Glazed doors.
Solid core doors.
Waterproof doors.
Timber louvred doors.
Flyscreen doors.
Security doors.
Acoustic doors.
B. INTERNAL DOORS
Flush panel doors – hollow core.
Flush panel doors – solid core.
Timber or metal frames (jambs).
Acoustic doors.
Glazed doors.
Expressed frame doors.
Include in each prototype elements required by this specification, finished in every respect. When approved by
the architect, each prototype remains part of the work and becomes the standard for the remaining work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1288 2006 Glass in buildings – Selection and installation.
Plus 1 Supplement, 2006, and 2 Amdt, 2008 – 2011.
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS/NZS 1859 Reconstituted wood-based panels – Specifications
1859.1 2004 Particleboard. Plus 2 Amdt, 2006 – 2011.
1859.2 2004 Dry processed fibreboard. Plus 2 Amdts, 2006.
1859.3 2005 Decorative overlaid wood panels. Plus 1 Amdt, 2009.
1859.4 2004 Wet-processed fibreboard.
AS/NZS 2272 2006 Plywood – Marine.
AS 2688 1984 (Obsolescent) Timber doors.
AS 2689 1984 (Obsolescent) Timber doorsets.
AS 4145 Locksets and hardware for doors and windows. There are 4 parts, 2001 – 2008 plus
2 Amdts, 2009.
AS 5007 2007 Powered doors for pedestrian access and egress.
AS 5039 2008 Security screen doors and security window grilles.
105 Submissions
Submit the following for inspection by the architect before installation:
Product literature on proposed hardware items.
Samples of items as requested by architect.
PART II MATERIALS200
301 Examination
Inspect site conditions. Ensure conditions are satisfactory for installation.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Prepare openings in walls or other structures before installation. Install fixing grounds and inserts as required to
secure frames.
307 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
END OF SECTION
Page 44 of 89
SECTION 08520 METAL WINDOWS AND GLAZING
PART I GENERAL
101 Scope
Design, engineer, supply and install a complete glazed system of windows, doors and screens, including but
not limited to:
Material type
Finish type
Openings
Glass types
Glazing methods
Insect screens
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.0 2002 General principles. Plus 5 Amdts, 2003 – 2011.
1170.1 2002 Permanent, imposed and other actions. Plus 2 Amdts, 2005 –
2009.
1170.2 2011 Wind actions.
1170.3 2003 Snow and ice actions. Plus 1 Amdt, 2007.
1170.4 2007 Earthquake actions in Australia.
There are several Supplements and Amdts, 2002 – 2011.
AS 1231 2000 Aluminium and aluminium alloys – Anodic oxidation coatings.
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS 2047 1999 Windows in buildings - Selection and installation. Plus 2 Amdts, 2001.
AS 3715 2002 Metal finishing - Thermoset powder coating for architectural applications of
aluminium and aluminium alloys.
AS 4145.2 2008 Locksets and hardware for doors and windows – Mechanical locksets for doors and
windows in buildings. Plus 2 Amdts, 2009.
HB 125 2007 The glass and glazing handbook.
Comply with relevant authority's requirement for fire-rated installation.
107 Warranty
Provide to the proprietor a warranty, counter-signed by the installer, on the whole of the installation, which
states that work will remain intact, waterproof and fully operational for the period of not less than 9 years after
date of Practical Completion.
PART II MATERIALS
202 Materials
Window frames: extruded aluminium components manufactured from aluminium alloy 6063, temper T5 or T6.
Match components detailed on drawings or an alternative approved in writing by the architect.
Glass: refer clause 206.
Insect screens:
205 Finish
Anodising or Polyester Powder Coat.
Anodising:
Metal of windows, doors and shop fronts anodised to selected colour.
Pre-treat and apply anodising by applicators approved by the architect.
Minimum coating thickness of 25 microns subjected to random testing after installation. Remove and replace
non-conforming material.
Comply with requirements of AS 1231.
Polyester powder coat:
Polyester powdercoated, to colour approved by the architect and by the manufacturer of the powder material,
to metal of windows, doors and shop fronts.
Page 46 of 89 SECTION 08520 METAL WINDOWS AND GLAZING
Perform pre-treatment and application of powder coating by applicators approved by the architect and by the
manufacturer of the powder material.
Minimum coating thickness of 50 microns subjected to random testing after installation. non-conforming
material will be removed and made good by the builder.
Comply with requirements of AS 3715.
206 Glass
A. Glass materials for external use:
B. Glass material for internal use:
C. Other glass for:
D. Calculations: calculate glass sizes and thicknesses in accordance with Standards, and fixing devices
and connections to structure in accordance with engineer's computations where applicable.
E. Double glazing:
208 Fabrication
Comply with AS 2047.
Framing system: fabricate from extrusions to profiles shown on approved Shop Drawings.
Form junctions so that no fixings, such as pins, screws, pressure indentations and the like are visible on
exposed faces. Show on Shop Drawings fixings which will be exposed. Cut edges, drill holes, rivet joints and
clean flat sheets, neat, free from burrs and indentations. Remove sharp edges without excessive deformation.
Fit mitred joints accurately to a fine hairline.
Pre-assemble and match mark before delivery.
301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Perform rectification required before delivery of materials.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
305 Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal
expansion of glass, the metal framing and spandrels.
309 Protection
A. Framing system: protect metal surfaces as necessary during erection. Finish surfaces free from
mechanical imperfections such as scratches, scrapes, dents, spots, stains and streaks.
B. Glass: protect glass from breakage immediately upon installation and until Practical Completion.
Remove and replace glass and metal panels which are broken, cracked, abraded, chipped or damaged
in other ways, before, during or after installation, at no additional cost to proprietor.
C. Be responsible for breakage and damage to installation until Practical Completion.
310 Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass, frames,
hardware and other finished surfaces immediately upon installation of glazing for each light.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.
311 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
General All glazing used on the project is to meet the requirements of the BCA, Glazing Code and
‘Viridian’ standards. All toughening required to glazing as a result of the Thermal Assessment
is to be included in the tender price.
Thermal Assessment to be included in Contractor’s price and to be undertaken by Contractor
prior to installation of glazing.
Supply and install all glazing to AS1288 and AS2047.
Page 48 of 89 SECTION 08520 METAL WINDOWS AND GLAZING
All external openings (doors & operable windows) must be fitted with draft seals to all sides
of openings, to be ‘Raven’.
Include all mullions, transoms, slotted sub-sills, sub-head, sub-jamb, head flashing, caulking
etc. as detailed and recommended by Capral.
All silicon and gaskets to be black
Visual Consistancy All façade glazing panes must be matching Colour, Visual Light Transmission (VLT),
Thickness, to achieve strict visual consistency, unless specifically noted otherwise.
It is the tenderer/glaziers responsibility to review, confirm and allow for consistency of glazing
at time of tender.
Internal Glazing Supply and install Viridian Clear Glass – minimum 10.38mm thick to all glazed partitions and
doors.
Provide Laminated or toughened glass as required to comply with AS1288
Silicon Butt joints typical to glazing– refer internal elevations for locations.
Glazing frames to be proprietary system to match steel stud partition framing “Capral” -
System 400 Narrowline Series (depending on situation) similar approved equivalent.
All aluminium Door frames to be Capral – 215 Series Suit (50mm exposed face) so as to
achieve AS1428.1-2009 compliant colour contrast between door and adjacent frame.
All aluminium frames to natural anodised aluminium (to match existing).
Film Supply and install 3M “Haze” film decal as scheduled and noted on the drawings.
Supply and install forsting or feature printed pattern to film as scheduled – refer Internal
Colour and Finishes Schedule (see Appendix.)
Electronic access Where electronic access control (swipe cards) are specified, install double mullion to door
control jamp (latch side) to accommodate swipe card an light switch installation to frame.
Visual Indicators All ground level glazing including all doors, windows and side lights without a chair rail are to
have a solid contrasting line applied to the full extent of the glazing.
Solid contrasting line is to be 75mm high with the lower edge between 900mm and 1000mm
above FFL.
Solid contrasting line to be 30% luminance contrast when viewed against the floor or surface
within 2m of the glazing on the opposite side.
END OF SECTION
Page 49 of 89
SECTION 08710 DOOR HARDWARE
PART I GENERAL100
101 Scope
Supply and install door hardware including but not limited to:
Wall mounted grilles for ventilation and other purposes.
Hinges.
Pivots.
Latches.
Locks.
Door holders.
Push plates.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS 1909 1984 (Obsolescent) Installation of timber doorsets.
AS 2688 1984 (Obsolescent) Timber doors.
AS 2689 1984 (Obsolescent) Timber doorsets.
AS 4145 Locksets.
4145.2 2008 Mechanical locksets for doors in buildings.
There are 3 other parts, 2001 - 2008 plus 2 Amdts 2009.
AS 4178 1994 Electromagnetic door holders.
Comply with requirements of statutory and local authorities.
106 Warranty
Provide to the proprietor a warranty covering faulty materials and installation for 5 years from date of Practical
Completion.
PART II MATERIALS200
201 Manufacturers
Lockwood
203 Miscellaneous
Fasteners: provide required bolts, screws, inserts, fasteners, templates and other accessories required for a
complete installation.
Co-ordinate with other trades as to the proper fastening systems suitable for the substrates to which the item is
to be secured. Refer to architect if in doubt.
301 Examination
Examine the materials to which door hardware is to be fixed.
Ensure conditions are satisfactory for installation.
Start of work means total acceptance of conditions.
302 Preparation
Remove hardware from surfaces to be painted. Replace when paint is dry.
303 Installation
Comply throughout with the written instructions of manufacturer.
304 Keys
Supply duplicate labelled keys (2No of.) for each lock. Provide plastic tags for each key.
Arrange with architect for location of a key cupboard.
Fit cupboard with hooks for each key with room names or numbers.
Install cupboard where instructed.
305 Testing
Check each key in relevant lock for satisfactory operation. Replace defective keys or locks.
Clean the materials installed.
Remove construction locks.
306 Co-ordination
Before finalising hardware order, review with security sub-contractor work related to reed switches, electric
locks/strikes etc. Generally such items will be supplied by the security contractors and fitted to doors and frame
by the builder.
PART IV DETAILS
Location/Description Details
General This section is to be read in conjunction with:
Architectural Door Schedule and
Door Hardware Schedule
All door hardware to be ‘heavy duty’, commercial grade.
'Lockwood' Symphony hardware brass furniture or equivalent
Door hardware to meet Section 13 and 13.5 of as1428.1 -2009
All Offices, Meeting Rooms and other rooms require high acoustic rating, supply and install
Raven acoustic seals aspsecified.
Where doors are scheduled as 2700mm high, provide 4 No. Hinges.
Master Key Builder required to allow to coordinate Masterkey hierarchy system.
Builder to provide a tabulated schedule of all locks and keys to the Architect & Project
Manager for confirmation of keying hierarchy 2 weeks prior to final date required for ordering
of cylinders and locks.
All doors to be master keyed to be ‘Bi-Locked’ master key system unless noted otherwise.
Doors with electronic access control to have similar master key override.
END OF DOCUMENT
PART I GENERAL100
101 Scope
Supply and install a complete system of glass, glazing and sealants including but not limited to:
Glass, clear float
spandrel
translucent patterned
wire reinforced
Glass, laminated
two or more laminations
inter-layer
Glass, toughened and unframed glass assemblies
Glass, tinted, heat reflecting, mirrored
Glass, sloping
Glazing plastics, polycarbonate, etc.
Glazing bars
Glazing systems - structural glass
Glazing beads, strips
Sealants and related materials
Film applied to glass surface
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1170 Structural design actions.
1170.0 2002 General principles. Plus 5 Amdts, 2003 – 2011.
1170.1 2002 Permanent, imposed and other actions. Plus 2 Amdts, 2005 –
2009.
1170.2 2011 Wind actions.
There are 2 other parts, several Supplements and Amdts, 2002 – 2011.
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
AS/NZS 2208 1996 Safety glazing materials in buildings. Plus 1 Amdt, 1999.
AS/NZS 2343 1997 Bullet-resistant panels and elements.
AS 4145.2 2008 Locksets and hardware for doors and windows – Mechanical locksets for doors and
windows in buildings. Plus 1 Amdt, 2009.
AS 4666 2012 Insulating glass units
HB 125 2007 The glass and glazing handbook.
Comply with relevant authority's requirement for fire-rated installation.
107 Warranty
In addition to the warranty requirements of the General Conditions of Contract, provide the following:
A. Warranty: provide glass manufacturer's written warranty, agreeing to, within specified warranty period,
furnish freight paid to project site, replacement units for glass units which have defective hermetic seals
(excluding that due to glass breakage), defined to include intrusion of moisture or dirt, internal
condensation at temperatures above -2°C, deterioration of internal glass coatings, and other visual
evidence of seal failure or performance failure; provided manufacturer's instructions for handling,
installation, protection and maintenance have been adhered to during warranty period.
B. Warranty period is 10 years after date of installation and not less than 9 years after date of Practical
Completion.
PART II MATERIALS200
301 Examination
Inspect site conditions before start of work on site, before delivery of materials. Ensure conditions are
satisfactory for installation.
Arrange for rectification required before delivery of materials.
Start of work means total acceptance of conditions.
302 Preparation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Prepare surfaces affected by the installation in accordance with material manufacturer's instructions.
304 Glazing
Secure glass in accordance with glass manufacturer's recommendations and AS 1288. Allow for thermal
expansion of glass, the metal framing and spandrels.
307 Protection
A. Framing system: protect metal surfaces as necessary during erection.
B. Finish surfaces free from mechanical imperfections such as scratches, scrapes, dents, spots, stains and
streaks.
C. Glass: protect glass from breakage immediately upon installation until Practical Completion. Remove
and replace glass and metal panels which are broken, cracked, abraded, chipped or damaged in other
ways, before, during or after installation, at no additional cost to the Proprietor.
D. Be responsible for breakage and damage to installation until Practical Completion.
308 Cleaning
A. Remove labels, excess glazing compounds, stains, spots and other foreign matter from glass, frames,
hardware and other finished surfaces immediately upon completion of each panel of glazing.
B. Debris: remove rubbish and debris resulting from glazing operations, each day.
309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
General Any glazing pane thicknesses are provided as a guide only. Final thickness, structural,
installation requirements to achieve compliance with the BCA and Australian Standards
are the responsibility of the builder and glazier.
Minimum thickness must be 10.38mm to all spaces.
All glazing used on the project is to meet the requirements of the BCA, Glazing Code
and ‘Viridian’ standards. All toughening required to glazing as a result of the Thermal
Assessment is to be included in the tender price.
Thermal Assessment to be included in Contractor’s price and to be undertaken by
Contractor prior to installation of glazing.
Supply and install all glazing to AS1288 and AS2047.
Include all mullions, transoms, slotted sub-sills, sub-head, sub-jamb, head flashing,
caulking etc. as detailed and recommended by Capral.
All silicon and gaskets to be black
Visual Consistancy All façade glazing panes must be matching Colour, Visual Light Transmission (VLT),
Thickness, to achieve strict visual consistency, unless specifically noted otherwise.
It is the tenderer/glaziers responsibility to review, confirm and allow for consistency of
glazing at time of tender.
Glazing All glass is to be ‘clear‘ glazing and achieve a minimum Visual Light Transmission
(VLT) of 71%
Visual Indicators All ground level glazing including all doors, windows and side lights without a chair rail
are to have a solid contrasting line applied to the full extent of the glazing.
Solid contrasting line is to be 75mm high with the lower edge between 900mm and
1000mm above FFL.
Solid contrasting line to be 30% luminance contrast when viewed against the floor or
surface within 2m of the glazing on the opposite side.
END OF SECTION
PART I GENERAL
101 Scope
Supply and install glass splashbacks including, but not limited to:
Measure area to be covered
Prepare area to be covered
Clean surface
Apply colour to glass
Ensure adequate fixing of glass.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1288 2006 Glass in buildings - Selection and installation.
Plus 1 Supplement, 2006 and 2 Amdts, 2008 - 2011.
Comply with requirements of statutory and local authorities.
106 Warranty
Provide to the proprietor a warranty covering satisfactory performance of the complete installation for 7 years
from the date of Practical Completion.
PART II MATERIALS200
202 Materials
Glass: 6mm toughened. Clear or low iron glass. Form cut outs as required for power outlets.
Background: plasterboard or fibre-cement fixed to bricks.
Colour: solid colour, 2 pack polyurethane or other paint system applied by the manufacturer of the splashback.
Refer to architect for selection of colour.
Sealant: neutral curing silicone rubber around entire perimeter of glass panel.
Fibre cement (if used): 4.5 or 6.0mm secured to masonry as recommended by manufacturer.
301 Examination
Visit the site and inspect conditions.
Compare conditions with the data shown on drawings.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.
Measure the areas to be covered with splashback, including cut-outs for power outlets etc. Advise architect if
walls are found to be out of square with each other or if the wall or substrate is not flat (flat means less than
4mm variation in surface).
305 Cleaning
Clean entire area of glass and adjacent finishes.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
General Refer to Internal Finishes Schedule for details
Glazing to splashback to be Starphire Colour (true clear)
END OF SECTION
Page 58 of 89
SECTION 09250 PLASTERBOARD
PART I GENERAL100
101 Scope
Supply and install a complete installation of plasterboard including but not limited to:
Plasterboard
Plasterglass
Flexible plasterboard, 6.5mm thick in 2 layers
Lining of concrete and masonry walls
Lining of steel stud walls
Lining with water-resistant plasterboard
Ceilings, drop walls, bulkheads
Fire-rated plasterboard walls/ceilings
Cornices.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2589 2007 Gypsum linings - Application and finishing.
HB 161 2005 Guide to plastering
106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 5 years from
the date of Practical Completion. The warranty includes a statement that the whole of the work has been
carried out in accordance with relevant Australian Standards and Codes and manufacturer's instructions in
effect at the time of installation.
PART II MATERIALS
202 Materials
Supply materials in accordance with material supplier's recommendations for each application.
301 Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of materials to
site. Rectify any discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
302 Preparation
A. Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards,
as relevant.
B. Co-ordinate with and ensure preparatory work by other trades is done prior to commencement of work;
failure to do so will involve removal of plasterboard and immediate rectification.
307 Protection
Protect finished work. Make good damage in every respect at no additional cost to the proprietor, and without
delay to job progress.
308 Cleaning
A. Adjust and clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work
which cannot be successfully cleaned and repaired to permanently eliminate damage.
B. Remove spatterings and droppings resulting from work. Remove daily surplus materials and rubbish
from the work area.
C. Leave floors broom clean at completion.
309 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
Internal walls Supply and install Gyprock CSR 13mm paperfaced recessed edge plasterboard typically to all
office walls of both partitions and internal face of all external walls etc., All office areas are to
have plasterboard finish unless noted otherwise.
All consulting / Audio room walls generally to have 2 x layers of 13mm Gyprock flush
‘Soundcheck’ full height wall linings to both sides, as noted on the architectural drawings.
All consulting / Audio room ceilingsgenerally to have 2 x layers of 16mm Gyprock flush
‘Fyrcheck’ lining, as noted on the architectural drawings.
To Wet Areas supply and install 13mm WR (‘aquacheck’) plasterboard lining.
Supply and install all stopping beads, shadow angles etc. as required and noted on
documentation
All plasterboard to be flush jointed to manufacturers details, Ex-angles to all external corners.
Include all bulkheads, drop walls, feature walls.
Provide expansion joints to Gyprock CSR recommendations.
All control joints shall be sealed or filled after the coating system has been applied.
Where indicated on drawings, supply and install Rondo P50 Shadowline trim.
Install all plasterboard in strict accordance with Gyprock installation manual No.547.
Support @ 600 c/c max.
Paint finish to all plasterboard.
External Walls with Plasterboard is not to be fixed directly to concrete panels.
Plasterboard Where nothing noted, use MS top hats. CSR Foilboard insulation. Provide expansion joints to
concrete panel joints in strict accordance with Gyprock specifications.
Expansion Joints Provide Rondo P45 plasterboard expansion joints or Gyprock P35 as required by Gyprock
recommendations.
Page 60 of 89 SECTION 09250 PLASTERBOARD
Maximum expansion joints to be located at 12m centres in both directions to ceilings and to
Gyprock recommendations to walls.
Provide expansion joints where plasterboard abuts different surfaces.
Discuss location of expansion joints in ceiling with architect to get approval for set-out.
Bulkheads Ceilings To areas where indicated provide Rondo screw-up ceiling system as specified. Typically entry
foyer, airlock and amenities areas.
Provide expansion joints to ceiling to manufacturers recommendations.
Provide square set corners where ceiling meets all walls.
Supply and install all suspension clips, joiners, top cross rails, furring channels etc. to complete
the installation.
Supply and install all stopping beads, shadow angles, etc. as required and noted on
documentation
Allow to construct MDF bulkheads and drop walls as documented/specified to Reception Area.
Allow to construct MDF concealed lighting recesses as documented/specified to Reception
Area.
All works to be in strict accordance with Rondo and Gyprock recommendations.
Paint finish to all plasterboard.
FR Plasterboard Supply and install Gyprock CSR 16mm Fyrchek where shown on drawings and inaccordance
with manufacturers specifications.
Refer to CSR ‘Red Book’ for installation requirements.
Access Hatches Supply and install Rondo Panther access hatches to all locations as shown on Architectural
ceiling plan and Services ceiling and details plans and specifications.
Supply and install Atkar Au.dislot or Concept Clip hatches to match surrounding ceiing finish.
END OF SECTION
PART I GENERAL
101 Scope
Supply and install drywall partitions including but not limited to:
Steelwork
Stud wall framing
Plasterboard
Fire-rated plasterboard
Other panelling materials
Pre-surfaced panels of plasterboard etc.
Other:
102 Related Work Co-ordinate and co-operate with the following trade sections:
Floor construction Ceiling construction
Floor treatment Electrical wiring
Skirtings Plumbing
Wall construction Painting
Wall finishing
103 Quality Assurance Prototype: at a location selected by the architect on site, construct a full size
prototype of:
Include in each prototype all elements required by this specification, and finish in every respect.
When approved by the architect, such samples will be the control standard and remain part of the work.
104 References
Comply with applicable portions of the following Australian Standards:
AS 1428 Design for access and mobility.
1428.1 2009 General requirements for access – New building work.
There are 5 other parts. 1992 – 2010.
AS 1684 Residential timber-framed construction. There are many parts and Supplements,
1999 – 2010 and Amdmts 2012, 2013.
AS/NZS 2589 2007 Gypsum linings - Application and finishing.
2589.1 1997 (Available Superseded) Gypsum plasterboard.
2589.2 1997 (Available Superseded) Fibre reinforced gypsum plaster.
AS 3623 1993 Domestic metal framing.
AS/NZS 4600 2005 Cold-formed steel structures. Plus 1 Amdt, 2010.
106 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 5 years from
the date of Practical Completion. Include a statement that the whole of the work has been carried out in
accordance with relevant Australian Standards and codes and manufacturer's instructions in effect at the time
of installation.
PART II MATERIALS
202 Materials
Supply materials in accordance with material supplier's recommendations for each application.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Rectify
discrepancy or unsuitability of substrate.
Start of work means total acceptance of conditions.
Space Enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in space
is completed and nominally dry.
305 Protection
Protect finish work. Damage made good in every respect at no additional cost to the proprietor, and without
delay to job progress.
307 Cleaning
A. Adjust and Clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work
which cannot be successfully cleaned and repaired to permanently eliminate damage.
B. Remove spatterings and droppings from work. Remove daily surplus materials and rubbish from the
work area.
C. Leave floors broom clean at completion.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
Metal Stud Walls Supply and install Rondo steel stud @ 450 c/c with 13mm thick plasterboard each side (2 x
layers of soundcheck plasterboard to select rooms / Meeting Rooms), paint finish. Stud width
to suite application. Refer Wall Type Schedule on drawings for stud size.
Provide boxed studs to manufacturer’s requirements.
Refer to structural engineer’s drawings for loading bearing stud walls.
Provide 15mm structural plywood bracing to all walls with new wall hung AV elements.
Timber framed walls Include to supply and install timber stud walls with 13mm Plasterboard lining to both sides
(load bearing where indicated). Studs @ 450 ctrs max.
Frame timber stud walls in strict accordance with AS1684 and the Victorian Timber Framing
Manual.
Provide double studs to all openings.
Refer to Structural Engineer for locations of double studs etc.
Provide square set cornice to areas indicated.
END OF SECTION
PART I GENERAL100
101 Scope
Supply and install a complete system of suspended ceilings including but not limited to:
Plasterglass ceilings.
Plasterboard ceilings.
Acoustic tile ceilings.
Bulkheads.
Ceiling access panels.
Insulating material.
Mineral fibre fire resistant duct spray.
Fire-rated ceilings.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2785 2000 Suspended ceilings - Design and installation.
AS 2946 1991 Suspended ceilings, recessed luminaires and air diffusers - Interface requirements
for physical compatibility.
AS/NZS 4600 2005 Cold-formed steel structures. Plus 1 Amdt, 2010.
105 Samples
A. Acoustical ceiling tile: provide samples of tile, as selected by architect to be supplied; not less than 2
units of each.
B. Provide one sample of each of the following elements:
1. Rounded cornice
2. Cornice internal angle
3. Cornice external angle
C. Suspension systems: provide sample of each component of suspension and acoustic suspension
system, including both standard shapes and accessories.
107 Warranty
Provide warranty covering the work against defective materials and workmanship for a period of 10 years from
the date of Practical Completion.
Include a statement that the whole of the work has been carried out in accordance with relevant Australian
Standards and manufacturer's instructions in effect at the time of installation.
PART II MATERIALS200
202 Materials
A. Suspension system
(one way exposed)
Page 64 of 89 SECTION 09500 SUSPENDED CEILINGS / FIXED CEILINGS
(two way exposed)
B. Plasterboard 10mm, 13mm
C. Plasterglass
D. Acoustic tile
Tile size: As noted on drawings
E. Ceiling access panels
F. Cornice
G. Beads, straps, etc.
H. Casing beads, stop-ends, etc.
I. Other items:
203 Accessories
Supply and install necessary accessories as indicated by component manufacturer for satisfactory and
complete installation.
204 Equipment
Supply equipment, forms, scaffolding, ladders, frames, etc. necessary for the satisfactory installation of
specified items.
301 Examination
Acceptance: visit site and inspect conditions, comparing conditions to drawings before delivery of materials to
site. Rectify unsuitable situation.
Start of work means total acceptance of conditions. Comply with referenced Standards and manufacturer's
recommendations regarding environmental conditions.
302 Preparation
Space enclosure: do not install interior acoustical ceilings until space is enclosed, is weatherproof until wet-
work in space is completed and nominally dry until work above ceilings completed, and until ambient conditions
of temperature and humidity will be continuously maintained at values near those indicated for final occupancy.
Protect wood, metal, glass, flooring and other finished work during progress. Damage is to be made good in
every respect at no additional cost to the proprietor.
Prepare areas and surfaces against which installation will be constructed. Ensure work by other trades is
completed before erecting suspension system.
Powder driven fasteners are not approved for use.
303 Installation
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Comply throughout with applicable portions of AS/NZS 2785, or AS 2946, and with the data sheets supplied by
material manufacturer.
305 Adjustment
Adjust installation to permit installation of such items as light fittings, mechanical vent registers and the like.
306 Protection
Protect completed installation from possible damage until issue of Practical Completion certificate.
307 Cleaning
Clean surfaces exposed to view. Replace sections or components which cannot be cleaned. Make good
damaged sections or panels affected by later work of other trades.
308 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
Ceiling Grids Supply and install a complete system of ‘balanced Tee’ Rondo rigid rod white finished enamel
exposed suspension T-bar grid 1200 x 600.
Refer to architectyral drawings for height and setout.
Tiles to be Armstrong “Dune max RH99” 600 x 1200 x 20mm Square Lay-in mineral fibre
acoustic tiles – H4981.
Install all suspended ceilings in strict accordance with manufacturers details – Heights as per
documentation – typically office areas 2700mm min and to match existing where ceiling grids
Page 65 of 89 SECTION 09500 SUSPENDED CEILINGS / FIXED CEILINGS
are to be demolished and replaced.
Provide 5% spare ceiling tiles on completion.
Flush Plasterboard Provide flush jointed 13mm thick plasterboard Gyprock (span 600) with paint finish where
(General) noted on the architectural drawings.
Supply and install a complete system of Rondo concealed screw-up ceiling system.
Unless otherwise indicated, all plasterboard ceilings are to have square set cornices.
Refer to architectural drawings for design, rakes, angles etc…
Square set cornice where noted.
Provide expansion joints to ceilings to Gyprock specifications.
Perforated Acoustic Supply and install Gyprock Rigitone Matrix (12.5mm) suspended acoustic plasterboard ceiling
Plasterboard Ceiling in accordance with manufacturer’s specifications.
Sheets to be fully flushed – refer to manufactures details flush jointing details.
Provide continuous black tissue backing lining.
White pre-finish – smooth and flat finish.
Provide continuous acoustic blanket as scheduled over. Cut insulation to suit light fittings, air
registers etc…
Ensure that fixtures are centrally located within the joints of the plasterboard sheet, ensure
that fixtures do not penetrate the perforations. Refer to the RCPfor location/extent and
specifications for details.
END OF SECTION
PART I GENERAL
101 Scope
Supply and install resilient floor surfacing material with necessary accessories and related equipment required
for the work including but not limited to:
Vinyl tile
Linoleum sheet
Vinyl sheet
Cork tile
Vinyl skirting
Rubber sheet or tile
104 References
Comply with applicable portions of the following Australian Standards:
AS 1884 2012 Floor coverings - Resilient sheet and tiles - Laying and maintenance practices.
AS/NZS 3661.2 1994 Slip resistance of pedestrian surfaces – Guide to the reduction of slip hazards.
AS 4586-2013 Slip resistance classification of new pedestrian surface materials.
HB 197 1999 An introductory guide to the slip resistance of pedestrian surface materials.
Comply also with instructions of manufacturers of materials to be installed.
105 Submissions
Provide samples and data sheets of materials.
Obtain architect's approval for each item before ordering.
107 Warranty
Provide a warranty covering aspects of the installation performed by this trade, against defective materials and
workmanship for a period of 5 years from the date of Practical Completion. The warranty includes a statement
that the whole of the work has been carried out in accordance with AS 1884 and the instructions of the
manufacturers of components in effect at the time of installation.
PART II MATERIALS
201 Materials
Refer finishes schedule.
202 Equipment
Supply equipment required for the preparation of floor, and installation of vinyl materials as recommended by
the material manufacturer.
301 Examination
Examine the site conditions applicable to each installation and comply with AS 1884.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.
302 Preparation
Prepare each area to be surfaced in accordance with AS 1884. Test the dryness of concrete sub-floor in
accordance with AS 1884.
304 Cleaning
Remove excess adhesive and blemishes from the completed surfaces of flooring and skirtings.
305 Protection
Apply suitable hardboard or plywood to completed floors and maintain in position until final cleaning prior to
Practical Completion.
Remove and replace work which cannot be successfully repaired or cleaned.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
Vinyl Sheet Supply and install vinyl sheet flooring with coved vinyl skirting as scheduled in Internal
Colour and Finishes Schedule in Appendix.
Vinyl skirtings to be coved 150mm high (to cleaner’s rooms) with coving fillit backing unless
otherwise noted.
Install in strict accordance with manufacturers details.
Provide Ardit under to level floor and raise vinyl to match adjoining carpet.
Provide ‘moisture sealer’ to concrete slab if moisture content exceeds vinyl manufacturer’s
specifications.
Moisture Testing Concrete moisture testing must be conducted prior to installation of any flooring. This
testing must be in accordance with the manufacturer’s specification and the results (of the
testing) must be accepted by the manufacturer prior to installation.
The results of the testing are to be submitted to the architect before installation proceeds.
The test report must be in accordance with AS 2455, Clause B3.
The methodology and equipment used to moisture test concrete subfloors must be in
accordance with AS 2455.1 and the manufacture’s guidelines.
Provide ‘moisture sealer’ to concrete slab if moisture content exceeds floor covering
manufacturer’s specifications.
END OF SECTION
Page 68 of 89
SECTION 09685 MODULAR CARPET (TILE)
PART I GENERAL
101 Scope
Supply labour, materials and equipment required for supply, delivery, storage, installation and testing for the
complete Modular Carpet installation.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 1385 2007 Textile floor coverings - Metric units and commercial tolerances for measurement.
AS/NZS 2270 2006 Plywood and blockboard for interior use. Plus 1 Amdt, 2007.
AS/NZS 2455 Textile floor covering - Installation practice
2455.1 2007 General. Plus 1 Amdt, 2009.
This Standard provides full instructions of pre-installation requirements and
installation methods.
2455.2 2007 Carpet tiles.
Maintain a copy of AS/NZS 2455.1 2007 General, at the project site until completion.
105 Submissions
Submit the following data and obtain approval from the architect before ordering materials:
A. List of recent projects with contact names and telephone numbers.
B. Full size sample module of each carpet type.
C. Confirmation of acceptance and compliance with the requirements of the builder in relation to the time
schedule for supply and laying.
D. Schedule of laying rates per square metre.
These rates include supply and installation of adhesive (if required) and accessories, cutting (where
required) and allowances for profit, overheads and administration costs.
E. Properties: provide test certificates from recognised authorities with the tender to confirm that the
modular carpet complies with the properties set down in clause 204.
F. Certification by the manufacturer that the materials comply with this specification.
202 Accessories
Provide extruded aluminium edge trims
Plain clear anodised aluminium (silver), (gold), (bronze)
Flexible p.v.c. edge trims (gold), (black)
Provide black, flexible p.v.c. stair nosing or equivalent
Provide extruded plain aluminium stair nosing or equivalent filled with a black p.v.c. insert
Provide stair tread nosing or equivalent filled with back slip resistant infill bars
203 Carpet
Refer to Internal Finishes and Fixturers Schedule
Tolerances: AS 1385
204 Properties
Refer to Internal Finishes and Fixturers Schedule
208 Identification
Mark modular carpet tiles on the back to identify the manufacturer and the type of modular carpet.
301 Examination
Visit the site and inspect conditions comparing conditions to drawings before delivery of materials to the site.
Notify the architect of discrepancy or unsuitability of the substrate.
302 Preparation
Comply with referenced standards and manufacturer's recommendations regarding environmental and other
on-site conditions.
Repair by approved means imperfections of the floor surface which might impair the finished carpeted surfaces.
Broom clean or vacuum clean surfaces upon which carpet is to be laid.
On completion of cleaning, obtain architect's approval of surface and follow such standard as he may
determine for preparation throughout the project.
308 Partitions
Partitions will be erected prior to the laying of the modular carpet.
309 Stairs
Lay carpet tiles to treads with pile running into the step. Cut to tight fit between nosing trims and risers.
Lay modular carpet tiles to risers with pile running downwards glued only along the top edge, fitted neatly
between the nosing trim and the tread and laid prior to laying the modular carpet tiles to the tread below.
Provide tread nosing (specified earlier) to the nosings of treads and landings fixed down to the stair treads
before laying the modular carpet tiles to the stair and in accordance with the manufacturer's printed
instructions.
314 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
Carpet Tiles Supply and install Supply and install Carpet Tile as scheduled on Internal Colour and Finishes
Schedule in Appendix to areas indicated on architectural documentation.
Allow to Ardit floor slab to all carpet tile areas.
Allow 6-8weeks lead time for supply.
Lock-dot Installation All carpet tiles must be installed with ‘lock-dot’ adhesive system to manufacturer’s written
specifications.
Moisture Testing Concrete moisture testing must be conducted prior to installation of any flooring. This testing
must be in accordance with the manufacturer’s specification and the results (of the testing)
must be accepted by the manufacturer prior to installation.
The results of the testing are to be submitted to the architect before installation proceeds. The
test report must be in accordance with AS 2455, Clause B3.
The methodology and equipment used to moisture test concrete subfloors must be in
accordance with AS 2455.1 and the manufacture’s written specifications.
Provide ‘moisture sealer’ to concrete slab if moisture content exceeds floor covering
manufacturer’s written specifications.
Carpet Protection All carpets are to be covered and protected with permeable protection sheeting barrier after
installation until just prior to hand over.
Heavy traffic paths are to be protected with additional MDF or similar boarding.
Spare Carpet Tiles Refer 212 Spare Caret Modules.
Transition Strips Metal (aluminium anodised) transition strips at all junction between dis-similar materials.
Refer 05500 Metalwork for details.
END OF SECTION
PART I GENERAL100
101 Scope
Supply labour and materials, services and equipment necessary for the preparation, application and finishing of
wall covering as indicated on drawings, schedules and as specified herein, to internal surfaces of building.
Refer to Schedule of Finishes.
104 References
In the absence of Australian Standards, comply with applicable written recommendations of the manufacturer.
105 Submissions
Submit the following materials:
Product literature on proposed systems.
Samples of approved materials which are to be identified with the manufacturer's colour code batch number
and colour name or match to scheduled colour code and name.
Samples are not to be less than 2 metres long and are to be of the same colour, pattern and type as
scheduled.
107 Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application installed
under this contract will show no deterioration and remain in good condition for a period of 7 years from the date
of completion.
PART II MATERIALS200
201 Materials
Refer to Schedules
301 Examination
Inspect all surfaces and determine that they are in proper condition to receive the work to be performed under
this section.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
The starting of work under this section means acceptance of such surfaces as being satisfactory. Correct
defects in work resulting from accepting poor surfaces at no cost to the Proprietor.
302 Preparation
Prepare all surfaces as required so that they are in a proper condition to receive the work.
Comply with manufacturer's instructions. Remove dust, dirt, grease and other extraneous matter affecting the
finished work.
Remove lighting fixtures, switches, power outlets and similar items in place prior to installation and reposition
upon completion of each space.
303 Protection
Provide suitable protection in all areas where wall covering is being done to protect adjacent surfaces from
damage during work.
Page 73 of 89 SECTION 09720 WALLCOVERING (PAPER, FABRIC ETC)
304 Application
Execute all work of this section in strict compliance with the manufacturer's recommendations.
305 Cleaning
At completion of work in each area, thoroughly clean the area.
Replace wall fittings and fixtures previously removed.
307 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued by the
architect.
END OF SECTION
PART I GENERAL100
101 Scope
Supply labour and materials, services and equipment necessary for the preparation, application and finishing of
painting and staining as indicated on drawings, schedules and as specified herein, to internal and external
surfaces of building, as follows:
Refer Schedule of Finishes.
Consult with the architect with regard to requirements of other trade sections of the specification which require
painting, and include as part of the work of this trade section the appropriate preparation, painting, and finish
required to complete the installation.
104 References
Comply with applicable portions of the following Australian Standards:
AS/NZS 2311 2009 Guide to the painting of buildings.
(NB: maintain this document at the project site by the contractor as a controlling
general reference).
AS/NZS 2312 2002 Guide to the protection of structural steel against atmospheric corrosion by the use
of protective coatings. Plus 1 Amdt, 2004.
105 Submissions
Submit the following materials:
A. Product literature on proposed painting systems.
B. Colour samples for approved painting materials. Identify samples with:
1. Manufacturer's colour code and colour name (if any).
2. Match to Schedule colour code and name.
C. Samples are not to be less than 100 x 100mm, and are to be of the same gloss level as the scheduled
colour.
D. Copies of pre-installation conference minutes.
108 Warranty
Provide a written warranty stating that preparation of surfaces, materials and material application installed
under this contract will show no deterioration and remain in good condition for a period of 7 years from date of
Practical Completion.
201 Materials
All internal paints are to be low VOC or environmental paints.
General: where manufacturer makes more than one grade of any material specified, use the highest grade of
each type, whether or not the material is mentioned by trade name in these specifications.
Paints and finishes used for the project may be manufactured by one or more of the following manufacturers:
Taubmans.
Dulux.
Wattyl.
Pascol.
Other products may be approved by architect. Apply to architect for approval of alternatives.
Provide materials necessary for preparation of surfaces, and for application of paint finishes.
202 Schedules
A Schedule of Finishes is included in this specification.
The architect will prepare a final Schedule of Colours in sufficient time before commencement of work.
301 Examination
Inspect surfaces and determine that they are in proper condition to receive the work to be performed under this
trade section. Refer 302 A, below.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
The starting of work under this trade section will be taken to mean acceptance of such surfaces as being
satisfactory and defects in work resulting from accepting poor surfaces are to be corrected at no cost to the
proprietor.
Refer AS/NZS 2311 Appendix C.
302 Preparation
A. General: prepared to a standard not less than that described under AS/NZS 2311, Section 3:
Preparation of Un-Painted Surfaces inclusive, and other clauses of Australian Standards referenced
therein.
This Standard is incorporated by reference as part of this specification and applies to the work below to
the same extent as if written herein.
B. Broom clean floor surfaces before painting. Remove dust, dirt, plaster, grease and other extraneous
matter affecting the finish work.
C. Putty-stop or plug nail holes and cracks on both exterior and interior work, as required. Natural or
stained wood finishes are to have putty coloured to match. Putty wood after prime coat or sealer coat
has been applied.
D. Clean bare metal surfaces of mill scale, rust, grease, oil, dirt, or other foreign matter, then properly
washed with spirit or other approved cleaning agents. After cleaning, etch, pickle, prime, or otherwise
prepare, as recommended by the paint manufacturer.
E. Remove blisters or other imperfections in previous coats caused by foreign substances or paint skins
from painted surfaces before the subsequent coat is applied.
F. Rub down wood and metal surfaces before finishing and between coats with No. 00 and finer sandpaper
or steel wool, leaving a perfectly clean surface. Sand smooth-finished surfaces before finishing and
between coats as required to smooth out rough areas and to assure a smooth, even finish. Surfaces to
receive paint are to be smooth and free of sandpaper scratches, mill-marks, and other imperfections.
G. Remove hardware, accessories, plates, lighting fixtures and similar items in place prior to painting and
re-position upon completion of each space, or protect as otherwise directed by the architect.
H. Thoroughly stir materials in containers before application, unless otherwise directed by the manufacturer
of the paint used, to ensure uniformity of colour and mass. Strain out paint skins or other materials
which would cause lumps or roughness. Thin only as recommended by the manufacturer.
303 Protection
Furnish and lay suitable drop cloths in areas where painting is being done to protect floors and other surfaces
from damage during the work.
305 Cleaning
At completion of work in each area, remove paint spots, oil and stain from adjacent surfaces, including finish
hardware.
Replace hardware previously removed.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
307 Schedules
PART IV DETAILS
Location/Description Details
General To be read in conjunction with Finishes Schedule.
Paint VOC Limits All paint to be low VOC
Product Type/Sub Category Max TVOC Content (g/L
of ready to use product)
Walls and Ceilings – Interior Gloss 75
Walls and Ceilings – Interior Semi Gloss 16
Walls and Ceilings – Interior Low Sheen 16
Walls and Ceilings – Interior Flat Washable 14
Ceilings – Interior Flat 75
Trim Gloss, Semi Gloss, Satin, Varnish and Wood Stains 30
Timber and binding primers 60
Interior Sealer 140
One and Two Pack Performance Coatings 200
INTERNAL
Walls (General) 1 coat Dulux sealer undercoat.
2 coats Dulux Wash and Wear satin acrylic.
All walls to be painted where not nominated as exposed finished proprietary product as
shown on drawings and schedules.
Walls to Wet Areas 1 coat Dulux sealer undercoat – ‘Aqua primer’
2 coats Dulux Wash and Wear ‘Kitchen and Bathroom’ satin acrylic. Low sheen.
Flush Plaster 1 coat Dulux acrylic sealer undercoat.
Ceilings (General)
2 coats Dulux Wash and Wear ‘flat’ acrylic.
Flush Plaster 1 coat Dulux sealer undercoat – ‘Aqua primer’
Ceilings to Wet
Areas
2 coats Dulux Wash and Wear ‘Kitchen and Bathroom’ satin acrylic. Low sheen.
Timber Doors 1 coat Dulux oil based undercoat.
2 coats Dulux enamel semi-full gloss.
Metalwork 1 coat Dulux ‘all metal primer’
2 coats Dulux gloss enamel.
END OF SECTION
PART I GENERAL
101 Scope
Design, supply and install required items including but not limited to:
Directory panel
Bulletin boards
Panels
Metal frames
Dimensional letters
Exterior/interior signs
Illuminated, non-illuminated
Plaques
Door signs
Signs for the disabled.
104 References
Comply with the applicable portions of the following Australian Standards:
AS 1319 1994 Safety signs for the occupational environment.
106 Submissions
Submit to the architect for approval, the following before ordering materials:
A. Samples of specified materials, conforming to type and finish required.
B. Fully detailed drawings showing overall dimensions and component sizes with proposed methods of
fixing and/or securing position.
C. Check data on sign for data accuracy - spelling , phone number, etc. before manufacture.
D. Copies of minutes of pre-installation conference.
108 Warranty
Provide to the proprietor a warranty co-signed by the manufacturer and installer stating that items in this
specification will remain in full operational condition for a period of 10 years from the date of Practical
Completion.
109 Maintenance
Provide a written undertaking to the proprietor that parts of the installation will be available for additional supply
from time to time to suit the proprietor's needs for a period of 10 years from the date of Practical Completion.
PART II MATERIALS
202 Materials
Refer signage schedule.
203 Finishes
Refer signage schedule.
205 Fabrication
Fabricate components in accordance with manufacturer's instructions and approved drawings.
Form junctions so that fixings are concealed.
Cut edges, drill holes free from burrs and indentations. Fit joints to a fine hairline.
Pre-assemble where possible or practical and mark each item for intended location before delivery.
301 Examination
Visit site and inspect conditions, comparing conditions to drawings before delivery of materials to site. Rectify
discrepancy or unsuitability of substrate.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of conditions.
Space enclosure: do not install materials until space is enclosed and weatherproof, and until wet-work in space
is completed and nominally dry.
302 Preparation
Prepare areas and surfaces before installation, so that best conditions exist.
Where necessary, ensure that lighting cable is in place and concealed ready for connection to light fittings
within the illuminated items.
303 Installation
Comply with manufacturer's written instructions. Provide appropriate anchoring devices, concrete pads for
external signs.
Take care of and protect adjacent surfaces and materials. Provide protective cover to adjacent finishes where
necessary.
304 Protection
Protect finished work.
Replace or make good work found damaged at time of Practical Completion.
305 Cleaning
A. Adjust and clean: clean exposed surfaces including trim, edge moldings, and comply with
manufacturer's instructions for cleaning and touch-up of minor finish damage. Remove and replace work
which cannot be successfully cleaned and repaired to permanently eliminate evidence of damage.
B. Remove spatterings and droppings from work. Remove daily surplus materials and rubbish from the
work area.
C. Leave floors broom clean at completion.
306 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
General Refer Door Schedule and Signage Schedule.
All other statutory signage by Contractor.
All signage to be installed to relevant current Australian Standards and NCC (BCA).
Sample for Approval Builder to provide sample of all signage for approval with at least 10 worksing days within
the program for review and approval.
Room Numbering Supply / install an aluminium natural anodised room numbering plate for each room in the
fitout (all floors) with the University of Melbourne allocated room numbers.
Text to be 50mm high black vinyl lettering.
Fire Service Signage Fire Services Signage to be to the approval of the CFA:
All Fire Service Signage must be installed as per section E1 of the NCC (Formally BCA).
Signage to be installed min 2m above FFL.
Signs to be laminated PVC finish or similar approved.
50mm high text, capital letters
Tactile Signage All Tactile and Braille signs must be installed as per section D3.6 of the NCC (Formally
BCA).
Signs must be located not less than 1200mm and not higher than 1600mm above the floor
or ground surface.
Signs with single lines of characters must have the line of tactile characters not less than
1250mm and not higher than 1350mm above the floor or ground surface.
Sign text to be 20mm high ‘Arial’ font.
END OF SECTION
PART I GENERAL100
101 Scope
Supply and install extinguishers where indicated in accordance with the statutory authority having jurisdiction.
104 References
Comply with applicable portion of the following Australian Standards:
AS 1603 Automatic fire detection and alarm systems.
There are 12 parts 1996 – 2011 and 4 Amdts, 1998 – 2001.
AS 1670 Fire detection, warning, control and intercom systems, system design, installation
and commissioning. There are 5 parts, 1997 – 2004, plus 1 Amdt, 2005.
AS/NZS 1841 2007 Portable fire extinguishers. There are 8 parts, one for each type.
AS/NZS 4353 1995 Portable fire extinguishers - Aerosol type.
Comply with requirements of statutory authority having jurisdiction.
105 Submissions
Copies of minutes of pre-installation conference.
PART II MATERIALS200
201 Manufacturers
Manufacturers of materials approved in writing by the statutory authority may supply equipment.
202 Materials
Supply and install extinguishers authorised by the authority in accordance with the schedule provided by the
authority.
301 Examination
Inspect site conditions before fabrication, where possible, and before delivery of materials. Ensure conditions
are satisfactory for installation. Arrange for rectification if required.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of relevant conditions.
303 Installation
Anchorage: except for anchorages furnished herein but placed by other trades, set and secure necessary
anchorages, including concrete and masonry inserts, bolts, wood screws and other connectors as needed.
Perform cutting, drilling and fitting as needed, locating anchorages and holes to ensure proper positioning of
completed work.
304 Cleaning
Clean materials installed to the satisfaction of the architect.
Remove temporary protective coatings.
305 Completion
Complete contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
General Contractor to assess and supply all fire extinguishers as required to comply with BCA.
All fire extinguishers are to be housed in locked enclosures with ‘break glass’ access.
Supply and insl Type: 2A:20B:E ‘Dry Chemical’ fire extinguisher to all electrical switch boards.
Final location to confirm with Architect prior to installation.
Fire Blanket Supply and install a fire blanket to each kitchen.
Final location to confirm with Architect prior to installation.
END OF SECTION
PART I GENERAL
101 Scope
The work of this trade section covers the supply and installation of manufactured casework items.
It includes but is not limited to:
Cabinets and cupboards
Shelving
Display units
Counters
Lockers
104 References
Comply with applicable portions of the Australian Standards:
AS/NZS 1859 Reconstituted wood-based panels – Specifications.
1859.1 2004 Particleboard. Plus 2 Amdts, 2006 - 2011.
There are 3 other parts, 2004 – 2005, 3 Amdts, 2006 - 2009.
AS 2754.2 1991 Adhesives for timber and timber products - Polymer emulsion adhesives.
AS/NZS 2924 High pressure decorative laminates – Sheets made from thermosetting resins.
There are 2 parts, 1998.
AS/NZS 4386 Domestic kitchen assemblies.
4386.1 1996 Kitchen units.
4386.2 1996 Installation.
AS 4786.2 2005 Timber flooring - Sanding and finishing.
105 Submissions
Submit the following prior to fabrication:
Product literature on proposed hardware items including components.
Technical data on melamine laminates proposed for use.
Technical data and samples of substrate materials.
Thickness of materials at typical locations.
107 Warranty
Provide to the proprietor a warranty co-signed by the manufacturer and installer stating that items in this
specification will remain in full operational condition for a period of 5 years from the date of Practical
Completion.
PART II MATERIALS
201 Materials
Refer to ‘Finishes Schedule’
202 Hardware
Refer ‘Fixtures and Fitting Schedule’.
Refer Hafele catalogue where not nominayed.
- All joinery doors and drawers to have ‘soft close’
301 Examination
Visit the site and inspect conditions. Check dimensions and compare all aspects with the drawings and
specification. Resolve differences before ordering materials or starting work.
Ensure tasks and activities comply with the Act, Regulation, Code of Practice or Australian Standards, as
relevant.
Start of work means total acceptance of all conditions.
303 Installation
Use concealed shims as required to install the work plumb, level, straight and distortion free within the following
tolerances:
- 1mm in 800mm for plumb and level (including bench tops),
- 0.5mm maximum offsets in flush adjoining surfaces,
- 2mm maximum offsets in revealed adjoining surfaces.
Scribe and cut to fit adjoining work; refinish cut surfaces or repair damaged finishes at cuts.
Secure joinery with anchors of blocking built-in or directly attached to substrates. Secure to grounds, stripping
and blocking with countersunk, concealed fasteners and blind nailing as required to complete the installation.
Except where pre-finished matching fastener heads are required, use fine finishing nails, countersunk and filled
flush. Use a matching filler where a transparent finish is required.
Install casework without distortion so that doors will fit openings properly and be accurately aligned.
304 Hardware
Install all door and joinery hardware as scheduled, listed and required in full compliance with the manufacturer's
recommendations.
Adjust as needed to centre doors in openings.
306 Completion
Complete all contracted work in accordance with contract documents and written variation orders issued by the
architect.
Location/Description Details
Kitchen/Tea Point This is to be read in conjunction with Internal Colour and Finishes Schedule and Fixtures,
Fittings and Appliances Schedule in Appendix.
Supply and install laminate 33mm MR-MDF craftwood benchtop and carcass with laminate
finish and post-form edges as scheduled.
Cupboard fronts and drawers to be 18mm thick MDF craftwood with laminate finish. Colour as
selected.
Internals to be 18mm thick white melamine board.
Kickspace to be 100 x 50mm MDF craftwood with natural andoised aluminium finish.
Adjustable shelves to have brass bush and dowel.
Provide chrome tea towel rail behind door to each tea bench.
Hinges to cabinet doors to be Blum 180º spring loaded self closing hinges.
All drawers and cupboard doors to be fitted with ‘soft close’ hinges and drawer runners.
Provide cutlery insert to top drawer of each tea bench.
Drawer runners are to be heavy duty steel ball bearing slides or rollers. Hafele or similar.
Provide minimum 1 bank of 4 drawers to each Tea Area.
Provide chrome flange to cover all penetrations through cabinet.
Wall Mounted Floating shelves (where applicable) to be 25mm thick MDF craftwood with melamine laminate
Shelving finish. Max span. 800mm. Proved concealed steel pin fixings as noted on the drawings.
Storage Joinery Supply and install laminate 18mm MDF craftwood carcass and 25mm MDF craftwood top with
laminate finish and ABS or laminate edges as noted on the architectural drawings, colour as
selected.
All internals to be 16mm white melamine finish.
Kickspace to be 100 x 50mm MDF craftwood with laminate finish.
Adjustable shelves to have brass bush and dowel.
Hinges to be Blum spring loaded 180º self closing type.
Storage Cupboards Supply and install laminate 25mm MDF craftwood carcass with chemical resistant laminate
finish edges as noted on the architectural drawings, colour as selected.
Cupboard fronts to 25mm thick MDF craftwood with laminate finish. Colour as selected.
Shelves to 25mm thick MDF craftwood with chemical resistant laminate finish, sqquare edge
finish. Colour as selected.
Kickspace to be 100 x 50mm MDF craftwood with laminate finish.
Adjustable shelves to have brass bush and dowel.
Hinges to cabinet doors to be Blum 180º spring loaded self closing hinges.
Fixing All shelving and carcasses are to be fixed directly to sud work in walls. Stud finder to be used
to locate prior to installation.
Locks All Locks to joinery shall be from one of the following suppliers:
-Cyberlock
-BMB
-Lock Focus
-Hafele
END OF SECTION
PART I GENERAL100
101 Scope
Seek quotations for all office furniture – workstation,s storage, seating, tables etc… from one of the following:
UCI Australia
Contractor to fully manage and co-ordinate with the workstations / furniture installers.
Coordinate soft wiring installation. Install all starter sockets as noted.
Supply and install a complete installation of workstations where shown on drawings, including but not limited to:
Frames
Panels, solid, glazed, laminated, metal, veneered, acoustic, fabric faced
Cable ducts
Power poles
Work benches
Work bench drop keyboard panel
Shelves
Hampers
Drawer pedestals
Cupboards
Pinboards, whiteboards
Power, telephone and computer data outlets
Light fittings
105 References
Comply with applicable portions of the following Australian Standards:
AS 3590 Screen-based workstations
3590.2 1990 Workstation furniture. There are 2 other parts, 1990.
AS/NZS 4443 1997 Office panel systems – Workstations.
Comply also with the requirements of statutory authorities having jurisdictions.
106 Submissions
Provide before ordering construction of components or ordering from stock:
product data describing components
shop drawings of components
samples of finishes of components
manufacturers written instructions for installation
certificate indicating approval of components by relevant bodies such as electricity supply authority and
telephone service supplier.
108 Scheduling
Deliver materials when the area is practically complete including floor coverings, wall and ceiling finishes,
painting and electrical installation.
Do not allow for covering workstation components to facilitate other trades working near or over them.
Comply with delivery and installation schedules.
Page 86 of 89 SECTION 12720 COMMERCIAL FURNITURE / WORKSTATIONS
109 Warranty
Provide a warranty covering the installation against faulty materials and installation for a period of 5 years.
Advise proprietor or owner of the voiding of the warranty if workstations are moved without the supplier’s
representatives present.
PART II MATERIALS200
202 Materials
A. Design of the system is determined by the location of the cable duct.
203 Equipment
Supply tools necessary for site installation and adjustment of the completed installation. Supply touch-up paint
to match finish colours.
204 Finish
Powder coat or anodised finish to visible metal components before delivery.
205 Fabrication
Cut, fabricate and pre-assemble as much of the installation as possible in the shop before delivery. Reduce on-
site work to a minimum.
301 Examination
Visit the site, inspect the conditions and compare them with the drawings.
302 Preparation
Provide polythene or building paper to surfaces which may be damaged by the installation.
Protect other installation, equipment and finishes.
303 Installation
Install components of the workstations in accordance with agreed layout, design, installation technique and
schedule. Ensure that horizontal surfaces are truly level throughout.
304 Earthing
Earth, in accordance with electric supply authority requirements, the power cable/duct system of each
workstation.
305 Inspection
Arrange for inspection by the architect at times nominated in the schedule.
306 Cleaning
Remove protection membranes. Clean surfaces. Remove and replace damaged materials. Touch-up scratched
or discoloured finishes as directed.
307 Completion
Complete the contracted work in accordance with contract documents and written variation order issued by the
architect.
Location/Description Details
General Mounting height and location on perimeter walls/in ceiling for soft-wired starter sockets is to
be located to suit the selected workstation system and is the responsibility of the builder.
The ‘Building’ contractor is responsible for final connection and certification of all soft wiring.
The ‘Building’ contractor is responsible for final connection and certification of all data.
All data points are to be supplied and installed as part of the ‘Building’ scope of
works.
Workstations will be installed following completion of partitioning.
The drawings are deemed to be diagrammatic in relation to position of fittings, ducting etc. It
is therefore the responsibility of the Furniture manufacturer to coordinate with all other
contractors to ensure that fittings and equipment are accessible and suitably located.
All fittings are required to be symmetrically located in relation to the building appearance and
other services.
Check all dimensions on site and verify details before ordering any materials or equipment
for the work.
No claims will be allowed for errors due to scaling off drawings or not verifying set out
dimensions on site.
Refer to attached Appendices for co-ordination.
Refer to drawing A260 for the position/location of all furniture.
Contractor to ensure all walls are setout in accordance with architectural drawings to suit
furniture.
Contractor to provide all power/data to suit furniture layout.
END OF SECTION
Page 88 of 89
APPENDICES
Page 89 of 89 APPENDICES