Professional Documents
Culture Documents
REGULATIONS
for
CONTROL OF COMMERCIAL DEVELOPMENTS
in
THE JEBEL ALI FREE ZONE
THIRD EDITION
2003
TABLE OF CONTENTS
Page 1
APPENDICES
I RAINFALL DATA
Page 2
1. DEFINITION OF TERMS
• The "Authority" shall mean the Jebel Ali Free Zone Authority.
• The "Developer" shall mean the lessee or his authorized Agent who submits an
application to the "Authority" on behalf of the lessee.
• The "Project" means the construction of a permanent building, any other civil work
on a leased property including any modifications or installations in pre-built
facilities.
• "Habitable room" means a room used for office, shop, workshop or other purpose
involving occupation by human beings for continuous periods of time, but not
including a W.C.
Page 3
2. PROCEDURE FOR DEVELOPMENT OF PROJECTS
A developer who intends to erect a permanent building or carry out any civil works
such as pipelines, roads, tanks, earthworks etc., shall follow the following
procedure:
a) After signing the lease agreement, he shall appoint a consultant who will act
on his behalf in all technical matters related to the design, construction, and
completion of the project (see Appendix A1 - LETTER OF APPOINTMENT OF
THE CONSULTANT).
b) At the same time the consultant shall apply to the service authorities, such as
Etisalat, Dubai Electricity and Water Authority (DEWA) for NO OBJECTION
CERTIFICATES.
c) The consultant shall then apply to the Authority for a BUILDING PERMIT
stating the purpose for which the building is to be erected and with the
submission requirements as stated in section 3 of these regulations.
ii. Dhs.3.00 per sq. m. of total floor area and a negotiated lump-sum
depending on the Authorities involvement for industries involving
Technical or Manufacturing Processes.
f) A BUILDING PERMIT will be valid for one year from the date of issue
thereof, or for such other period as may be specified therein. If the
construction of the building is not commenced within that period, the validity
of the BUILDING PERMIT may be extended subject to acceptable reasons
being provided and a revalidation fee as decided by the Authority will be
levied.
Any deviations from the approved drawings or from the conditions laid
down in the BUILDING PERMIT will be allowed only if written consent of
the Authority is obtained in advance.
b) The Consultant shall visit the site and confirm the locations of existing
services.
c) The Authority, upon written request from the consultant, will permit the
contractor to mobilise prior to obtaining a Building Permit. After mobilisation
Page 4
the contractor shall invite EHS-FZ department for inspection and obtain a
certificate of conformity by submitting the “Contractor’s Environment, Health
& Safety Form” (see Appendix A4)
d) The Contractor shall pay a refundable deposit of Dhs. 5,000.00 for plots up to
10,000 sq. m. area or such an amount as decided by the Authority for bigger
plots. For carrying out modification works in JAFZA pre-built units the
contractor shall pay a refundable deposit of Dhs 2,500.00
e) The Contractor shall demarcate the site as per the setting out plan prepared as
per the lease drawing. After demarcation and checking, the Consultant shall
get the setting out of plot corners approved by the Authority as per Appendix
B and instruct the Contractor to encase them in concrete.
f) The Consultant shall supervise the construction work and shall communicate
with the Authority regarding any problems arising on site. No direct
communication from the contractor will be entertained by the Authority.
g) The Contractor shall execute the project strictly in accordance with the
approved drawings and regulations and ensure no damage to the Authority's
property. Portacabin offices for the use of the contractor and consultant will
be allowed only during the project construction stage, on receipt of a written
undertaking that they would be removed upon completion of construction.
i) All electrical documents for the project shall be submitted to DEWA and
approval obtained. A copy of DEWA approved electrical documents shall be
submitted to the JAFZA prior to requesting a Building Completion Inspection.
j) On completion, the Contractor shall clear all construction debris from the site.
All costs of clearing up operations shall be borne by the Contractor.
k) The Authority will refund the deposit upon satisfactory completion and
clearance of the site.
a) After completion of the building with the basic electrical, mechanical and fire
protection installations and obtaining approval from DEWA and Etisalat, the
consultant shall apply for a BUILDING COMPLETION CERTIFICATE with
submission requirements as set out in section 3 of these regulations.
c) DEWA shall provide power supply to the building only after the issue of the
BUILDING COMPLETION CERTIFICATE.
Page 5
EHS-FZ Dept) the developer shall then apply immediately to the EHS-FZ
Department for an OPERATION FITNESS CERTIFICATE.
The Authority's approval must be obtained prior to carrying out any modifications
to pre-built factory/warehouse units and offices. The Authority shall permit the
lessee to construct office space up to 20% of warehouse area (102 sq.m.) without any
rent increase and up to 40% of warehouse area (204 sq.m.) with rent increase. The
lessee shall arrange to amend the lease with Free Zone Administration Department.
The lessee shall ensure that the construction is of easily demountable type in order
to minimise reinstatement costs. All drawings as per Section 3 shall be submitted to
obtain a NO OBJECTION CERTIFICATE. The Building Permit fee for
modifications will be Dhs.1.50/sq.m, subject to a minimum of Dhs.250.00. The
modified premises shall be occupied only after obtaining a BUILDING
COMPLETION CERTIFICATE. The developer shall provide a written
undertaking that the premises will be reinstated to their original condition at the
end of the lease period. No equipment other than A/C units shall be placed outside
the leased warehouse/factory units without obtaining the permission of the
Authority. Condensate A/c drain shall not be disposed off in loading/unloading
areas. The facility may not be operated commercially unless an Operation Fitness
Certificate is obtained.
Page 6
3. SUBMISSION REQUIREMENTS FOR OBTAINING BUILDING PERMIT
AND COMPLETION CERTIFICATE
The consultant shall submit the following documents and drawings with an
application for a BUILDING PERMIT (see Appendices A2 & A3) at Civil
Engineering reception:
c) Lease drawing, NOC from DEWA (Electricity and Water) and Etisalat.
Note: Incomplete submissions will be returned without review and JAFZA will not
be responsible for delays to the project as a result of an incomplete submission(s).
Page 7
3.1b For Obtaining a Building Permit for minor modifications on a Leased Plot
NOTE: - Only relevant documents shall be submitted and incomplete submissions will
be returned without review and JAFZA will not be responsible for delays due to
incomplete submissions.
General Guidelines
1. Setting out plan shall clearly identify any additional service lines like drainage,
etc.
2. Complete existing floor plans with the proposal identified clearly shall be
submitted.
3. Detailed plan, elevation, and section for the proposed modification with clear
details of windows, air ventilation, etc., shall be submitted.
4. Fire fighting layout drawing shall clearly show smoke detectors, hydrant
location/relocation.
Page 8
6. The project brief shall comprise: -
3.2a For Obtaining a NOC for Modification in JAFZA’s Pre-Built Warehouse Units.
The following drawings & documents shall be submitted at Civil Engineering reception.
General Guidelines
1. Floor plan shall clearly show existing & proposed additional offices with all
dimensions. Proposed partitions shall be clearly identified.
2. Detailed plan, elevation, and section for the proposed partitions with clear
details of windows, air ventilation, etc shall be submitted.
4. Fire fighting layout drawing shall clearly show smoke detectors, hydrant
location/relocation.
Page 9
6. The project brief shall comprise: -
6.1. The usage of the partitioned area. (For storage, processing &
manufacturing).
6.2. For any effluent in the process, the quality of the effluent shall be
submitted in writing.
6.3. Layout of the machinery, if applicable
7. If the total area of office space exceeds 20% of the warehouse area (20% of
510=102m2), an additional rent of 10% will have to be paid by the lessee. The
maximum space that can be converted for office use shall not exceed 40% of the
warehouse area (204 m2).
3.2b For Obtaining a NOC for Modification in JAFZA’s Lease Office Buildings (LOBs)
I. Architectural drawings (Floor Plan, ceiling plan, section and details) - 2 Sets
NOTE:- Only relevant documents shall be submitted and incomplete submissions will
be returned without review and JAFZA will not be responsible for delays due to
incomplete submission.
General Guidelines
Detailed plan, elevation, section for the proposed partitions with clear details of
windows
air ventilation, etc.
Fire fighting layout drawing shall clearly show smoke detectors, hydrant /Hose Reels,
Fire Alarm panel/Bells, break glass units, fire extinguishers, Fire Exit Doors/Fire rated
doors etc location/relocation.
1. Existing lighting and small power layout drawings revised to show the proposed
modifications.
2. Existing Load schedule of affected DB’s revised to show proposed modified /
additional loads (if required only).
a) A covering letter.
Page 10
b) Notice of Intent duly signed and stamped (See Appendix B1/B2).
The following documents are to be submitted prior to inviting JAFZA for final
Inspection to obtain a BUILDING COMPLETION CERTIFICATE:
a. Letter from the consultant reporting the completion of the building as per the
approved drawings.
c. As Built Documents/Drawings/Certificates.
i. Storage tanks and pipe lines wherever deemed necessary by the Authority.
ii. Lifting equipment.
iii. Pressure vessels and any other equipment as deemed necessary by the
Authority.
The premises shall not be occupied for the purpose of conducting business until the
BUILDING COMPLETION CERTIFICATE has been obtained.
Page 11
3.4b For obtaining BUILDING COMPLETION CERTIFICATE for modification in JAFZA’s
Pre-built warehouse units.
The following documents shall be submitted prior to inviting JAFZA for final inspection
to obtain BUILDING COMPLETION CERTIFICATE.
a) Letter from the consultant reporting the substantial completion of works as per
the approved drawings.
b) Application for BUILDING COMPLETION CERTIFICATE . (See Appendix A5)
c) Documents/Drawings.
Only relevant documents shall be submitted and shall be collated as mentioned above.
The modified area shall be occupied only after obtaining the BUILDING COMPLETION
CERTIFICATE
Page 12
nomination of the persons responsible for the site safety, authorized persons
and authorized key holders.
Page 13
4. POWERS OF THE AUTHORITY
4.1 At the discretion of the Authority the BUILDING PERMIT may be cancelled or
suspended if:
4.2 BUILDING PERMITS will not be withheld unreasonably, but the Authority shall
have the discretionary power, when issuing a BUILDING PERMIT, to attach such
special conditions thereto as related to all or any of the following matters:
4.3 The Authority is empowered to change, amend, replace and/or update the
regulations without notice. It is the developer's responsibility to obtain updated
regulations.
4.4 It is the responsibility of the developer to apply the up-to-date regulations, Free
Zone Rules, etc. that may supersede ones mentioned in these regulations.
4.5 The Authority reserves the right to reject the appointment of consultants or
contractors for particular jobs if they are not deemed competent enough to fulfil the
related responsibilities.
4.6 The Authority reserves the right to levy fines for breach of regulations and to
suspend a consultant or a contractor for non-compliance with the regulations.
Page 14
5. RESPONSIBILITIES AND DISPUTES
5.1 Neither the checking of the drawings, nor the checking of the structural
calculations, nor inspection of the work during the progress of construction, shall be
construed in any way to impose responsibility and/or liability on the Authority or
their agents. The developer and his agents shall remain entirely responsible for all
errors in the design and execution of the project and for the stability and safety of
construction during the progress of the works and after completion.
5.2 All complaints and disputes concerning BUILDING PERMITS and the erection of
buildings shall be referred to the Authority. It shall be noted however that the
Authority will not arbitrate disputes between developers their consultants or
contractors. All such disputes shall be settled through the Dubai Civil Courts.
Page 15
6. FITNESS OF MATERIALS
6.1 All materials used in any construction shall be of a suitable nature and quality in
relation to the purposes for which they are used. Buildings shall have a minimum
design life of twenty years.
6.2 All materials shall conform to UAE/Gulf standards, British standards, International
standards or any other standards approved by the Authority.
6.3 The Authority shall be permitted to take without charge such samples of the
materials used in the works as may be necessary to ascertain whether they comply
with these regulations.
6.4 The Authority is empowered to order the opening-up of work to ascertain whether
materials and/or workmanship, which have been covered-in during subsequent
building operations, are of the standard required by these regulations.
Page 16
7. SITE AND SERVICES
7.1 General
ii. Dubai Electricity and Water Authority (Water Division) for water
connection.
i. Unimpeded road access not less than 5.5 m wide to all buildings and
facilities. Roads shall be of sufficient standard for use by fire tenders
(any septic tank, manhole located in this road shall be of heavy duty)
and shall be adequately illuminated.
iii. Where applicable, a fenced-off reserve of appropriate size for siting the
Authority's electrical supply terminal point, with a padlock able access
gate towards the road, recessed into the perimeter fencing of the plot.
viii. Sign board displaying the name of the company, as registered in the
lease agreement, to the approval of the Authority.
a) All tanks for reception or disposal of sewage from any building shall be
adequately vented and impervious to liquid either internally or externally.
Page 17
Inspection chambers shall be provided at every point of change of direction.
Top inspection chambers shall be adequately vented to fresh air. Any soil
ventilation pipe within 5 m (measured horizontally) from any window shall
extend to not less than 1 m above the window head.
g) The linear soakaway shall not be located in the 5.5m vehicular access area.
The soil above the linear soakaway shall not be compacted and protected
from vehicular access by a raised kerbstone, the same to be shown in the
relevant drawing. A raised kerbstone shall be provided around the linear
soakaway. EHS-FZ department shall be invited for inspection during laying
of liners and their approval obtained prior to back filling.
h) Design and installation of small sewage treatment plants shall comply with
BS 6297 or an equivalent standard approved by the Authority.
k) Wherever there is a sewage network within the Free Zone, the developer is
required to connect into it, the charges for which will be according to the tariff
available with EHS-FZ department (see also sec 7.4 of Free Zone Rules).
These charges may be reviewed from time to time and the developer is
advised to contact EHS-FZ department to obtain the latest tariff. In case such
network is not available, the developer is required to construct a septic tank
and soakaway. (Refer to Environmental Control Rules and Requirements,
IIIrd. Edition, 2002). Provision for future connection to JAFZA drainage
networks shall be provided.
l) Developers are required to have an industrial waste system within their plot
separate from their domestic waste system. No drains from industrial
processes will be allowed to discharge into the dock, soakaway, or the
Authority's drainage network without treatment to standards acceptable to
the Authority (refer to Environmental Control Requirements and Standards
for Prevention of Pollution). The developer will have to pay a one-time
connection charge of Dhs. 25,000.00 and according to tariff for the effluent
Page 18
discharged into the line (see also sec 7.5 of Free Zone Rules). These charges
may be reviewed from time to time and the developer is advised to contact
EHS-FZ department to obtain the latest tariff.
a. A proper holding tank with liquid tight liner (preferably 2mm HDPE liner) of
suitable capacity (minimum 3 days capacity). shall be provided for the
collection/storage of any industrial wastewater generated from the operations.
b. Proper spillage collection facility for the spillages, which could occur in the
liquid chemical storage/ production area to be provided.
e. The A/C drains to be discharged into a properly designed soak pit or domestic
drainage network.
Page 19
8. DESIGN OF BUILDINGS: REQUIREMENTS AND STANDARDS
8.1 The building is to be so constructed that the combined dead, imposed and wind
loads are safely transmitted to the ground without deformation and deflection of
any part of the building, and without such ground movement impairing the
stability of any part of another building. The building stability shall not be
impaired by subsoil movement due to swelling or shrinking. Portacabins will not
be allowed as permanent structures.
8.2 Structures shall be designed in accordance with the current British Standard Codes
of Practice, and shall comply with the Authority's durability requirements
mentioned in this section. Listed below are some British standards applicable to
Building design and construction:
BS 3692 : Specification for ISO metric precision hexagon bolts, screws and nuts -
Metric units.
BS 4604 : Specification for the use of high strength friction grip bolts in structural
steelwork - Metric series.
BS 8007 : Code of practice for the structural use of concrete for retaining aqueous
liquids.
Structures that are designed in accordance with the established current codes of
practice of other countries may be accepted; prior approval of the Authority shall be
sought in such cases.
Page 20
8.3 The following are minimum requirements for structural steelwork:
b) Painting shall be epoxy-based paint with a minimum DFT of 240 microns for
internal surfaces and 270 microns for external surfaces or equivalent.
d) Maximum chloride content (as NaCl ) in any mix shall not exceed 0.3% by
weight of cement for reinforced concrete and 0.12% by weight of cement for
mass concrete.
8.5 The following are particular minimum requirements for concrete in contact with
soil ( substructure):
8.6 The design and construction of pipelines, storage tanks, boilers, cranes, lifting
equipment and pressure vessels shall be checked and certified by an independent
third party inspection agency approved by the Authority.
Page 21
9. GENERAL PLANNING REQUIREMENTS
9.1 All parts of buildings shall lie within plot boundaries and shall not occupy more
than 60% of the site unless otherwise permitted in the approval of the application.
9.2 The site layout shall allow for a minimum set back of 5.5 m from all boundaries.
9.3 In all buildings the height of each floor measured from the finished floor level to the
ceiling shall not be less than:
9.4 No direct access to the Port main distributor road and dual carriageway will be
allowed.
9.5 The site layout shall allow for loading and unloading of vehicles to take place
within the boundary. Adequate parking spaces shall be provided within the plot
limits.
9.6 Access to the plot shall clear all existing services in the service corridor and the cost
of any relocations or modifications shall be borne by the developer.
9.7 The finished floor level of any building shall be not less than 300 mm above the
approach road level.
9.8 The finished level of any paved road, parking or footpath within the boundary shall
be not less than 150 mm above the approach road level and shall have a fall towards
the road. Any earthwork (filling or cutting) shall be restricted to the plot limits.
9.9 The developer is encouraged to allocate a small part of land within the plot
boundary (preferably in front and along the perimeter) for greenery and
landscaping, as this is considered highly desirable by the Authority. No greenery
and landscaping will be permitted outside the leased plot.
9.10 Access to the plot across service corridors shall be paved after installation of service
ducts and protection of the existing services to the Authority's approval. All costs
shall be borne by the developer.
9.11 Space for electrical sub-station and other services as required by the concerned
service authorities shall be provided within the plot limits.
Page 22
10. FENCING
The developer is to provide perimeter fencing to define the boundary of the property and
to provide the degree of security that is consistent with the operations proposed.
Generally the fencing utilised on the Port Area complies with the following
specifications:
a) Intermediate posts shall be set into concrete bases 300 mm x 300 mm x 600 mm deep
and straining and end posts set into concrete bases 450 mm x 450 mm x 800 mm
deep.
b) Intermediate posts to be steel tube 60.3 mm x 2.9-mm wall thickness, strainers and
end posts to be 76.1 mm x 4.5-mm wall thickness, galvanized with zinc to a
thickness of 55 microns and coated with polyester resin to a total resin thickness of
300 microns.
d) Crank size shall be 500 mm. Mesh shall be carried 300 mm below ground level and
the first straining wire shall be 60 mm above ground level.
f) Gates to be set into 500 mm x 500 mm x 1000 mm deep concrete bases unless the
size of the gate is such that a larger base is deemed necessary.
The developer may propose an alternative, similar to one detailed above, for approval.
In particular circumstances, the Authority may insist that the fence be covered with nylon
fabric. In such cases, the fence design shall be substantiated with calculations.
Necessary earth retaining structures and proper measures to prevent discharge of surface
drainage to adjoining plots shall be provided along the plot boundary where required
and to suit site conditions.
Page 23
11. FIRE PROTECTION:
11.1 Extent
a) All the fire protection requirements stipulated hereunder are based almost on
functional requirements and do not encompass detailed dimensional and technical
specifications. The same shall be applicable to construction/erection of any
building/structure/plant; alteration/modification or extension of any of the existing
building/structure/plant; and change of activity/use.
d) DPA/JAFZA has adopted National Fire Protection Association (NFPA) USA and its
companion Codes/standards as guides for practices so that appropriate, consistent
and currently effective fire protection coverage is provided to the
buildings/structures/plants in FZ areas. Therefore, all the Fire Protection
arrangements/ systems shall primarily meet the recommendations contained in
relevant NFPA codes/publications/standards.
f) All the requirements and recommendations of DPA/JAFZA Fire Dept (being the
approving authority having jurisdiction) shall be strictly complied with.
DPA/JAFZA approved Risk Assessment consultants shall include the following points
in their Fire Risk Assessment/Analysis Report: -
b) Severity analysis/Fire & Explosion Index (F & EI) and Toxicity Index (TI).
c) Scenario development.
d) Probability analysis.
Page 24
g) Risk reduction analysis (if the risk is not acceptable). systems & methods and
recommendations to prevent and/or reduce them to the acceptable level(s).
Guideline - Notes
i. The scale that measures severity such as death, injuries, property damage, and
areas reached by flames shall be specified.
ii. Calculations specifying the severity measure used for a particular fire shall be
included.
e) Plans for storied buildings/structures/plants shall include plans of each storey and
its sectional elevations. Also, the locations of staircases, landing valves/hydrants
and fire access details shall be indicated.
Guideline - Notes
i. The site layout shall normally allow for a minimum setback of 5.5 Mtrs. from all
boundaries so as to maintain/permit necessary and natural fire break.
ii. The building/structure/plant shall be accessible to fire tenders and other emergency
vehicles.
iii. Unobstructed layout of building/structure/plant for easy fire fighting.
iv. Emergency lights/escape lighting luminaries shall be sited near each exit door and
at the points where it is necessary to emphasis the position of safety equipment and
potential hazards ( i.e. near intersection of corridors, exit doors, staircase flights,
change of direction, change of floor level, fire fighting equipment, fire alarm call
points and outside final exits).
Page 25
11.4. Hazard Classification: -
Fire protection coverage and means of escape/egress shall be provided depending on the
type of occupancy and hazard classification [broad] as below: -
i) Light Hazard
Guideline - Note
a) General Requirement: -
Guideline - Notes
i. Restrict materials used in contents and furnishings to reduce heat release rate and
smoke generation rate & to prevent unusual toxic hazard relative to quantity of
smoke generated.
ii. Add fire retardants to materials to slow growth of heat release rate.
iii. Use of fire-resistive barriers to slow spread of fire to large secondary items.
iv. Restrict total fuel load to limit contents based in total fuel potential.
v. Restrict linings of rooms to prevent rapid flame spread (Restrict wall coverings,
ceiling coverings, and floor coverings).
Page 26
vii. Use construction barriers to block fire spread between zones (wall assemblies,
ceiling/floor assemblies, barriers between occupied and concealed places, fire-
stopping in concealed spaces and exterior barriers to vertical spread between
floors).
viii. Design doors and windows to block fire spread between zones (Fire door
assemblies and window restrictions to block fire spread between
buildings/structures/plants).
x. Regulate design and operation of systems for heating, venting, and air
conditioning to prevent their serving as mechanism to transfer smoke and gases
into uncontaminated occupied areas. (This shall also permit shut off of air
movement in fires).
xi. Plug vertical and horizontal utility openings (pipes, cable ducts, AC ducts and
cables) and peep-through (at doors, columns & beams) by suitable fire resistive
sealant.
iii. Every exit stairway and other vertical openings between floors of a
building/structure/plant shall be suitably enclosed or protected as necessary to
afford reasonable safety to occupants while using the means of escape/egress and
to prevent the spread of fire, smoke or fumes through the vertical openings from
floor to floor before the occupants have reached the nearest exit.
Guideline - Notes
i) Doors of small individual rooms such as offices are not considered as exits
unless they actually lead directly to the open air.
iii) An interior passageway does not become part of an exit until it is enclosed as a
fire compartment with at least half an hour fire resistance.
Page 27
iv) Where an external stairway exists it shall be ensured that the use of it at the time
of fire is not prejudiced by smoke and flame issuing from openings (e.g.
Windows, doors) in the external face of the building.
Page 28
11.6. Fire Detection & Fire Alarm Systems:-
Every building/structure/plant shall be provided with suitable fire detection / alarm systems
capable of enabling early detection of fire and warning occupants of the existence of fire. These
systems shall be electronically interfaced with DPA/JAFZA Emergency Control Centre (ECC)
monitoring system through a digital communicator.
i. Hose Reel.
ii. Sprinkler including Early Suppression Fast Response (ESFR) sprinklers system
iii. Water Spray System
iv. Automatic Smoke/Heat/ Flame/Low Explosive Limit (LEL) Detectors.
v. Smoke and heat ventilation system.
vi. Deluge foam or water sprinkler & foam or water spray systems.
vii. Closed-Head foam water sprinkler system.
viii. Total flooding systems (of appropriate extinguishing agent (s).)
ix. Foam Pourer System.
x. Foam/Water monitors.
xi. Hydrants and Hose Boxes.
xii. Fire Pumps &
xiii. Fire Water Tanks.
11.8. Certification/Approval
a. All the fire extinguishers and fixed fire fighting installations/systems shall be of
the types, make(s) and brands currently certified/approved by UAE/Dubai
Civil Defence authorities.
Page 29
12. VENTILATION AND AIR CONDITIONING
12.1 The design of walls and roof shall take into account Ventilation and Air
conditioning requirements. The purpose is to limit the accumulation of moisture
and pollutants which originate in the building and which would otherwise become
a health hazard. An adequate supply of fresh air is necessary to ensure the health
and comfort of the occupants of buildings and to limit condensation.
a) For rapid ventilation - one or more ventilating openings with total area of at
least 1/20 floor area of room with some part of the opening at least 1.75 m
above floor level, or
b) For background ventilation - opening(s) with a total ventilation area not less
than 4000 mm2 with opening secure and draughts avoided.
a) Mechanical extract - extract rate not less than 20 Air changes per hour.
12.5 Ventilation of common spaces will be acceptable if opening(s) with a total area of at
least 1/50 of common space floor area are provided. If the common space is
internal and for access only, it may be ventilated mechanically (1 ach).
12.7 WC’s may be ventilated by either rapid ventilation (openings at least 1/20 floor
area with part at least 1.75 m above floor) or mechanical extraction (6 ach which
may be operated intermittently and with a 15 minutes overrun).
Page 30
12.8 Ventilating a habitable room through an adjoining space:
Two habitable rooms may be considered a single room for ventilating purposes if
there is a permanent opening between which is equal to at least 1/20 combined
floor area.
b) There is an opening (which may be closable) between the room and the space,
with an area not less than 1/20th of the combined floor areas and
c) There is a ventilation opening(s) in the room and the space together, or in the
space alone, equal to at least 1/20th of the combined floor areas and with a
part of the ventilation opening area at least 1.75 m above the floor level and
for background ventilation there are openings to the space and between the
space and room each having not less than 4000 mm2 area.
The movement of air may be activated by such means as the operation of the door
of the compartment, the operation of the lighting or by independent manual
control. However, there shall be an overrun of at least 15 minutes after the use of
the compartment.
12.10 The ventilation of industrial buildings shall be in accordance with latest editions of
ASHRAE/CIBSE standards.
12.11 Design and installation of all air conditioning and ventilation systems shall be in
accordance with current guidelines of ASHRAE (American Society of Heating,
Refrigeration and Air conditioning Engineers).
Page 31
13. COMMERCIAL AND INDUSTRIAL REFRIGERATING PLANTS
c) All areas containing ammonia refrigerating plant and/or systems shall have a
suitable ammonia gas detection system fitted to the approval of the Authority.
d) The developer shall hold and maintain suitable positive pressure breathing
apparatus for instant rescue to the approval of the Authority.
The design, erection and maintenance of cold stores, chill stores and cool stores
shall be in accordance with the British Institute of Refrigeration Code of Practice for
Cold Store Construction.
Page 32
14. ELECTRICAL INSTALLATIONS
c) Along with the above application, the developer shall also submit the 'P' form
(Consumer's Request for Power Supply), (see Appendix C), duly completed in
all respects.
a) Upon signing a lease for the allotted plot, the developer shall apply to DEWA
for his power and water connections.
b) The terms and conditions for supply of electricity and water to the developer's
premises shall be as stipulated on DEWA's composite application form
attached as Appendix 'E'. (Only format attached. The developer shall obtain
original form from DEWA for submission).
c) Metering and Isolation facilities will form part of the Terminal Point
equipment and access to these facilities will be strictly at the control of
DEWA.
d) The developer will be responsible for terminating all his power offtake cables
at this Terminal Point. He will be further responsible for all the electrical
works within the leased property.
f) Capacities greater than 1500 KVA are generally provided only through
dedicated feeders. Necessary special arrangements for the provision of
dedicated feeders shall be agreed with DEWA.
Page 33
14.4 General Requirements
a. Any temporary power supply for site services during construction shall be the
responsibility of the developer, but will have to be approved by the DEWA.
d. The Vector Group of any power distribution transformers used shall conform to
the requirements of the Authority's power system.
g) Any 11KV switchgear used shall comply with the current edition of BS 5311
(1976) and 5227 (1984) or approved equivalent. Generally switchgear, which is
metal, clad and utilises withdrawable circuit breaker trucks having an integral
earthing facility with essential foolproof interlocks shall conform to the
requirements of the Authority. No concession will be granted against this
requirement and details of developer's proposals in this respect shall be
submitted for approval before ordering the switchgear. The technical
specification of 11KV switchgear and transformers supplied and installed by the
developer shall be submitted to DEWA for approval prior to installation.
a) The developer shall submit the following documents to enable the Authority to
assess and approve the electrical installations.
ii. Drawings showing sufficient details of the electrical systems. e.g., Single
line diagrams, layout, load schedule, power factor correction
arrangements etc.
Page 34
b) In view of the long lead-time for electrical equipment, it is necessary that an
early approach be made to the Authority with above details of the electrical
requirements. The procedure is listed in Appendix H.
a) The developer shall ensure the following prior to inviting the Authority for a
completion inspection:
vi. Site clearance has been effected so that access to the building(s) is
unimpeded.
ix. Any electrical circuits shown on the approved electrical drawings and
provided for the installation of machinery which may not be in position
at the time of the building completion, shall be terminated in suitably
approved local isolating switches/terminal boxes.
b) The Authority shall then inspect the premises and if the results are
satisfactory the Authority will issue a BUILDING COMPLETION
CERTIFICATE with which the developer may approach DEWA for
immediate action to connect the developer's electrical system to the power
supply from the Authority.
d) The developer shall not lay electrical cables, conduits, trunking etc. on the
floor surface for the purpose of supplying power to machines or other
apparatus. Suitable alternative methods must be employed.
Page 35
e) Upon completion of installation of production equipment, machinery etc., the
developer shall submit all necessary documentation as per the regulations and
invite the Authority for final inspection.
The energization of the electrical system shall be subject to the following conditions:
a) Construction and installation work of all basic structural facilities have been
completed and tested.
c) All site facilities have been inspected and deemed satisfactory and a
"Building Completion Certificate" has been issued by the Authority.
f) The Authority shall not be liable in any manner whatsoever, for any
consequences arising out of the developer's use of the electrical energy.
g) The developer shall be fully responsible for the maintenance, safe operation
and security of his installations and the safety of personnel.
Though all efforts will be made by the Authority to maintain the quality and
continuity of power supply, it will assume no responsibility, in any manner
whatsoever, for any consequences arising out of an unexpected
degradation/failure of the power supply. If continuity of power is essential for the
safe operation of the facility, it shall be the responsibility of the developer to
provide suitable stand-by power supply arrangements in the event of rare mains
supply failures.
Page 36
14.9 Power Factor Correction and Under Voltage Protection
The internal electrical distribution system at the developer's premises shall comply
with DEWA's General Guidelines for Power Factor Correction and Under Voltage
Protection (see Appendix F).
Page 37
15. LIGHTING
Page 38
16. TELEPHONE INSTALLATIONS
16.1 The following requirements shall be complied with by the developer for the
provision of a satisfactory cabling access and distribution system.
a) 2 X 100 dia. PVC underground lead in ducts with draw rope at a minimum
depth of 750 mm from finished ground level shall be provided. The duct
including draw rope shall extend to a position not less than 0.5 metres outside
the plot boundary. Any intermediate jointing/inspection chambers shall be
provided as per the requirements and to the approval of ETISALAT.
16.3 If any underground telephone plant exists it shall be protected. The Etisalat Plant
Protection officer shall be contacted on tel. No. 2022414.
Page 39
17. WELFARE AND SANITATION
17.1 Every habitable building must include provision of sanitary facilities, unless
otherwise permitted by the Authority. These facilities must include the provision of
at least one W.C. with no direct access from a habitable room.
17.2 Sanitary facilities shall be provided at rates not less than the following:-
Offices, Workshops
17.3 Hot and cold water services shall be provided to wash hand basins.
17.4 Drinking water shall be provided from a potable supply, with one point per 50
persons or as agreed with the Authority.
17.5 Trapped floor gullies or drainage channels shall be provided in ablutions to enable
all areas to be washed down, cleaned and drained.
17.6 All finished internal surfaces of ablutions shall be non-absorbent and cleanable.
17.7 The construction of cubicles, where provided shall not impede the free movement
of air within ablution buildings.
17.8 Water closets, urinals and wash hand basins shall have a smooth and readily
cleanable non-absorbent surface. They shall be constructed and fitted to discharge
through an effective trap of suitable dimensions and thence without storage to a
pipe or drain. The flushing apparatus for a water closet or urinal shall be capable of
effective cleaning of the receptacle.
17.9 Soil pipes and waste pipes shall be of adequate size for their purposes but in no case
shall the internal diameter be less than the internal diameter of the outlet of any
appliance which discharges into it. Refer to the Health and Safety manual for
details.
17.10 Ventilation pipes shall be of adequate size for their purpose but in no case shall be
less than 50 mm internal diameter. They shall be carried upwards to such a height
and so positioned as not to transmit foul air in such a manner as to become
prejudicial to health.
Page 40
17.11 Permission must be obtained from the Authority for the siting of any manhole
within any building. Where permission is given such manholes must have a double
seal, screwed-down cover.
Page 41
18. RAINWATER DRAINAGE
18.1 The system for carrying rainwater from a roof shall be adequate. The system shall
carry the flow to an outfall, minimise the risk of blockage or leakage and be
accessible for cleaning the blockages.
18.2 Every exposed roof, canopy or building shall be finished with a gradient of at least
1:80 which shall direct the rainwater to suitable channels, gutters, outlet or
downpipes.
b) Of adequate size
18.4 Rainwater shall not be discharged into the septic tank or soakaway, the Authority’s
drainage system, where existing, or the adjacent plot.
18.5 All rainwater shall be either drained into a specially constructed soakaway or into
the approach road.
18.6 The rainfall data received from Meteorological Department of Dubai International
Airport indicate that a rainfall of 60 mm per hour for periods up to 20 minutes can
occur during heavy thunderstorms. The frequency of such storms is difficult to
assess but the table of 24-hour extreme rainfall and rainfall returns in Appendix I
may give some indication.
18.7 All surface water drainage shall be dispersed off to JAFZA’s road corridor and
measures to prevent dispersal of surface water towards adjacent plots shall be
provided.
Page 42
19. MESS AND KITCHEN:
19.1 A mess and kitchen if required shall be constructed of fire resisting materials and
comply with standards required by the Authority.
19.2 Floors and walls shall be impervious to moisture and capable of being cleaned by
washing down. Floors shall be hard-surfaced, non-absorbent & adequately drained.
They shall be constructed with waterproof, non-absorbent washable materials
without fissures or crevices.
19.3 Walls shall be tiled to a height of 2.1m above floor level with ceramic tiles. Internal
walls shall be smooth, waterproof, resistant to fracture, light coloured and readily
cleanable. (See also Food Establishment Guidelines for more details)
19.4 Drains shall incorporate grease and pea (rice) traps and interceptors.
19.5 Working surfaces for preparation of food are to be of stainless steel or other
approved impervious material to facilitate cleaning and maintenance of hygienic
conditions.
19.6 Mechanical extraction with exhaust hoods and fans shall be provided to all areas
involving cooking activities i.e. stoves, gas rings, tandoors etc.
19.7 Gas pipes to cookers, rings etc., shall be laid in an approved manner with approved
materials i.e. copper or steel tubing, permanent joints, minimum flexible hose.
19.8 Kitchens shall be fitted with recommended fire extinguishers as decided by the Fire
Officer.
19.9 Layout and construction details of any temporary canteen required during the
period of construction shall be approved by the Authority.
Page 43
20. REFUSE DISPOSAL
20.1 Refuse containers must be sited on the ground floor in a place directly accessible to
a road, and remote from habitable areas.
20.3 Where a large quantity of refuse is to be expected the owner may be required to
install an incinerator for the disposal of refuse on the site or to arrange for the
disposal of refuse in some other manner to the approval of the Authority. Early
consultation with the Authority is recommended where any large quantity of refuse
is anticipated.
Page 44
21. BUILDING OPERATIONS
21.1 The Authority shall have free and uninterrupted access to the site of the works at all
times of the day and night.
21.2 No work may be commenced unless a BUILDING PERMIT has been issued.
21.3 All building operations shall be confined within the boundary wall or fence of the
plot. All sites shall be enclosed with a temporary hoarding during the period of
construction displaying the names of the developer, consultant and the contractor.
A layout indicating the temporary fencing and sign board details shall be submitted
for approval.
21.4 The developer shall obtain the Authority's approval for the siting of all buildings,
sheds and temporary works for the construction of the new development and shall
satisfy the Authority in respect of adequate provisions for safety, prevention of
health hazards (e.g. sanitation and drainage disposal) and siting of such structures
and shall maintain them to these standards for the duration of the building works.
Their demolition or removal shall be within a stated time in the Permit, and the site
of such works shall be reinstated to the satisfaction of the Authority.
21.5 Where required by the Authority, artificial lighting shall be provided to illuminate
any obstruction, excavation or temporary fence within the site boundary. Protective
barriers shall be provided where necessary.
21.7 The developer or his Agent shall give not less than 24 hours notice of the date of all
or any of the following stages:
c) The completion of the structural steel frame and prior to false ceiling (if
applicable). The consultant shall confirm in writing that he has checked and
approved the alignment of the completed steel framework.
21.8 The consultant's representative shall be present on site at the requested date and
time and during concreting. Failure to comply with the above will result in
imposition of fines as per Free Zone Rules section 14.4 and subsequently suspension
of the consultant from operating in the Free Zone.
21.9 The consultant shall review and approve the method statement for erection of steel
structure and forward a copy to JAFZA.
Page 45
21.10 The developer or his Agent operating on site shall ensure that all works are
adequately supervised.
21.11 A copy of the Building Permit and approved drawings signed by the consultant and
the contractor shall be kept on site during building operations.
21.12 Any deviation from the approved drawings shall be approved by the Authority
prior to commencement of construction.
Page 46
22. ENVIRONMENT, HEALTH AND SAFETY REQUIREMENTS.
c. A proper holding tank with liquid tight liner (preferably 2mm HDPE liner) of
suitable capacity (minimum 3 days capacity) shall be provided for the
collection/storage of any industrial wastewater generated from the operations.
d. Proper facility for collection of spillage occurring in the liquid chemical storage/
production area shall be provided.
e. The construction of any boiler, heat, oven, etc., shall comply with JAFZA’s
guidelines.
i. A proper domestic waste skip facility shall be provided. The domestic waste
handling facility shall have proper/free access for vehicular movement and the
proposed paving/roadbase shall be proper to enable the same. Our standard
requirements are:
The underground storage of fuel shall adhere to the following EHS requirements:
Page 47
Bunded areas shall be provided for all overground fuel/chemical/ wastewater tanks,
designed to hold 110% capacity of the largest tank volume.
A walled enclosure with minimum 6 feet high walls with glazed ceramic tiles on three
sides for car washing areas to be provided.
The flooring and trench of the chemical storage warehouse shall be lined with
chemical/ acid resistant coating
a. Chemical Resistance
b. Mechanical Strength
c. Scratch Resistance
d. Non-absorption of materials
e. Heat Resistance
f. Ease of cleaning & Decontamination
g. Life Expectancy
h. Ease of repair & maintenance
i. Prevention of static charge
Since all types of acids, alkalis and flammable materials are used in the laboratory, the
schedule of finishes shall be selected with consideration to the above. Use of ceramic
tiles is recommended as the most suitable material since it meets/withstands all the
above requirements.
For further details Refer Environmental Control Rules & Requirements, IIIrd.
Edition, 2002 or Health & Safety manual, IIIrd. Edition, 2002 or Food Establishment
Guidelines.
Page 48
APPENDICES
APPENDIX 'A1'
APPOINTMENT OF CONSULTANT
To
Dear Sirs,
PROJECT:
Thanking you,
Yours faithfully,
AUTHORIZED SIGNATURE
.
APPENDIX A2
Name of Company :
Building Permit:
Date Issued/Rejected
F.Z.Civil Engineer.
APPENDIX A3
Name Of Company :
Building Permit:
Date Issued/Rejected:
F.Z.Civil Engineer.
APPENDIX A4
Note: EHS- form –2 shall be filled and COC –2 shall be obtained if the higher elevation work is
four meters and above.
We undertake to carry out the construction work in accordance with JAFZA/DM/EHS –Guidelines and
other relevant International Construction Safety Standards. We also aware that Personal Protective
Equipment (Coverall, helmet, safety shoes) are mandatory requirements for any construction work in Free
Zone and the Major Contractor will be held responsible for any accidents during our operation as per
st
JAFZA circular dated 21 November 1999.
EHS-FZ Inspector :
Inspection Date :
Approved By :
Project : Duration:
--------------------------------------------------------------------------------------------------------------------------------
We hereby confirm that the following EHS requirements have been complied satisfactorily.
DESCRIPTION Yes No N/A
1. Record for job Safety analysis
2. Availability of Tool Box meeting record
3. Availability of Work Permit system (Hot, Cold
etc.,)
4. Usage of Safety Harness/ life line etc.,
5. Availability of Safety net/ Scissors lift
6. Test record of Scaffolds approved by Competent
Person
7. Scaffolds fitted with proper ladder, working
platform, locking device etc.,
8. Gas cylinders fitted with flash back arrestors
9. Cylinders secured in a vertical position
10. Gauges in good working condition
11. Are open holes covered or barricaded?
12. JCB/Forklift fitted with Reverse alarm
13. Record for EHS-FZ entry Permit for heavy
vehicles/Lifting Equipments
14. Proper guard for saw cutting machine
15. Provision for barrication with flash light
16. Road marking & Diversion
17. Regular Disposal of Construction waste as per
DM regulation
18. Maintaining Good House keeping
We undertake to carry out the construction work in accordance with JAFZA/DM/EHS –Guidelines and
other relevant International Construction Safety Standards. We also aware that Personal Protective
Equipment (Coverall, helmet, safety shoes) are mandatory requirements for any construction work in Free
Zone and the Major Contractor will be held responsible for any accidents during your operation as per
st
JAFZA circular dated 21 November 2001
EHS-FZ Inspector :
Inspection Date :
Approved By :
BUILDINGS COMPLETED
ELECTRICITY (DEWA)
Drawings - Approved ο Pending ο Not applicable ο
ETISALAT
Plot Number:
Name of Consultant:
Project:
Planning approval for the above has been obtained from Civil Engineering Department as per
JAFZA control of Commercial Development Regulations, and Certificate of Conformity from
EHS-FZ department.
We undertake to hand excavate and physically locate all the services near area of work before
excavation. We also undertake to carry out the work in accordance with Authority's Planning
and Construction Regulations and to take care in preventing any damages to Port Property and to
clear all construction debris and dump in approved locations. Any damages to Port facility or
services shall be made good and all costs borne by us.
We are pleased to submit Name, Curriculum Vitae of the Engineer in charge of the project all the
time and Certificate of Conformity for your approval.
Enclosures: Copy of Trade Licence + C.V. + Certificate of Conformity from EHS-FZ dept.
Consultant's remarks: We confirm that the plot has been demarcated as per lease drawing and
checked by ourselves (Not required if already demarcated).
Signature: Date:
(Signature):
APPENDIX B2
(FOR JAFZA’S PRE-BUILT UNITS)
Name of Consultant:
Project:
Planning approval for the above has been obtained as per JAFZA control of Commercial
Development Regulations.
We undertake to hand excavate and physically locate all the services near area of work before
excavation. We also undertake to carry out the work in accordance with Authority's Planning and
Construction Regulations and to take care in preventing any damages to Port Property and to
clear all construction debris and dump in approved locations. Any damages to Port facility or
services shall be made good and all costs borne by us.
We are pleased to submit Name, Curriculum Vitae and contact telephone number of the Engineer
in charge of the project present at site all the time, for your approval. We also enclose a copy of
receipt of the payment of the refundable deposit.
(Signature):
APPENDIX ‘C’
NO._______________________________________
______________________________ * (Strike out whichever is not applicable)
____________________________________________________________________________________________
DETAILS OF EQUIPMENT
TO BE SUPPLIED WITH POWER
LIGHTING
GENERAL SUPPLIES
AIR CONDITIONING
FACILITY:
LIGHTING
GENERAL SUPPLIES
AIR CONDITIONING
MOTOR DRIVES:
1.
2.
3.
4.
5.
OTHER EQUIPMENT:
1.
2.
3.
KW
________________________________
Signed by Consumer Representative
THIS FORM IS DESIGNED TO ENABLE THE FREE ZONE AUTHORITY TO INSTALL THE
CORRECT CABLE AND EQUIPMENT TO SERVE YOUR FACILITY. IT IS THEREFORE
REQUIRED TO BE COMPLETED IN DETAIL BY A QUALIFIED ELECTRICAL
ENGINEER/CONSULTANT SO THAT A FULL UNDERSTANDING OF YOUR INSTALLATION IS
PRESENTED.
THE POWER SUPPLY CONNECTION WILL ONLY BE MADE UPON COMPLETION OF THE
FACILITY AND A BUILDING COMPLETION CERTIFICATE IS ISSUED. POWER IS NOT
PROVIDED DURING CONSTRUCTION.
ALL ELECTRIC MOTOR DRIVES ARE TO BE LISTED. THIS IS TO ENSURE THAT THE
CAPACITY OF THE SUPPLY IS SUFFICIENT WHEN STARTING DIRECT-ON-LINE DEVICES.
FOR EXAMPLE, STARTING OF MOTORS IS LIMITED TO DRIVES OF 22 KW CAPACITY ON A
150 KVA SUPPLY, WHEREAS FOR REDUCED CURRENT STARTING METHODS, THIS LIMIT IS
40 KW. THE TOTAL INSTALLED CAPACITY OF ELECTRIC MOTOR DRIVES IS LIMITED TO
64 KW ON A 150 KVA SUPPLY, INCLUDING AIR CONDITIONING. IF THERE IS A
REQUIREMENT FOR GREATER THAN 22 KW FOR DIRECT-ON-LINE STARTING, OR
GREATER THAN 40 KW FOR REDUCED CURRENT STARTING, THEN THE CAPACITY OF THE
SUPPLY WILL HAVE TO BE OF SUITABLE HIGHER RATING.
IF SPACE ON THIS FORM IS NOT SUFFICIENT TO LIST ALL EQUIPMENT, PLEASE SUBMIT
DETAILS ON A SEPARATE SHEET.
Introduction
i. The forms of Completion, Inspection and Testing required by Part 7 shall be made out
and signed by competent persons in respect of the design, construction, inspection and
testing of the work.
ii. Competent persons will, as appropriate to their function under i) above, have a sound
knowledge and experience relevant to the nature of the installation undertaken and to the
technical standards set down in the Wiring Regulations, be fully versed in the inspection
and testing procedures contained in the Regulations and employ adequate testing
equipment.
iii. Completed forms will indicate the responsibility for design, construction, inspection and
testing, whether in relation to new work or further work on an existing installation.
iv. When making out and signing a form on behalf of a company or other business entity,
individuals shall state for whom they are acting.
Client:
Address:
DESIGN
I/We being the person(s) responsible (as indicated by my/our signatures below) for the Design of the electrical
installation, particulars of which are described on Page 3 of this form CERTIFY that the said work for which I/we
have been responsible is to the best of my/our knowledge and belief in accordance with the Regulations for
Electrical Installations published by the Institution of Electrical Engineers, 16th Edition, amended to (3.)
(date . . . . . . . . . .) except for the departures, if any, stated in this Certificate.
The extent of liability of the signatory is limited to the work described above as the subject of this Certificate.
CONSTRUCTION
I/We being the person(s) responsible (as indicated by my/our signatures below) for the Construction of the electrical
installation, particulars of which are described on Page 3 of this form CERTIFY that the said work for which I/we
have been responsible is to the best of my/our knowledge and belief in accordance with the Regulations for
Electrical Installations published by the Institution of Electrical Engineers, 16th Edition, amended to (3.) (date . . . . . . .
. . .) except for the departures, if any, stated in this Certificate.
The extent of liability of the signatory is limited to the work described above as the subject of this Certificate.
The extent of liability of the signatory is limited to the work described above as the subject of this Certificate.
Page 1 of 3
1. This document is intended for the initial certification of a new installation or of an alteration or
addition to an existing installation and of an inspection.
2. The signatures appended are those of the persons authorised by the companies executing the
work of design, construction and inspection and testing respectively. A signatory authorised to
certify more than one category of work shall sign in each of the appropriate places.
3. Dates to be inserted.
4. Where particulars of the installation recorded herein constitute a sufficient schedule for the
purpose of Regulation 514-09-01 further drawings/schedules need not be provided. For other
installations the additional drawings/schedules listed below apply.
5. Insert here the time interval recommended between periodic inspections. Regard shall be paid to
relevant National or Local legislation and reference shall be made to Chapter 13.
6. The page numbers of each sheet shall be indicated together with the total number of sheets
involved.
Page 2 of 3
PARTICULARS OF THE INSTALLATION
2. Other (Describe) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Details of departures (if any) from the Wiring Regulations (120-04, 120-05) . . . . . . . . . . .
Page 3 of 3
APPLICATION FOR SUPPLY OF ELECTRICITY & WATER
I/We, the undersigned hereby apply for the supply of electricity & water for the purpose stated herein and I/we agree to pay for
providing the supply at the appropriate rate and scale of charges under DEWA’s tariff in force from time to time. I/We have read
and understand and agree to observe and be bound by DEWA’s Terms & Conditions printed overleaf and any amendments made
thereto by DEWA from time to time.
Signature of Consumer or Authorised Representative………………..:……………………………….Date: ………………………………
Stamp if applicable: …………..…………………………… Name and position held: ……………………………………………………...
II. DETAILS OF THE ELECTRICAL WIRING INSTALLATION (For use by the ‘E’ Division)
1. Details of the wiring installation.
Total
Total
By Nationals (Landlords):
1. Copy of DM approved site plan / affection plan (as proof of ownership) Attached( )
2. Copy of identification documents: ID Card & Passport Attached ( )
3. Authorisation letter for National’s representative Attached ( )
By Other / Contractors : (If consumer under 1.1 above is tenant / Non-National / Employee)
1. Employment certificate Attached ( )
2. Landlord’s guarantee (as per prescribed form) / Authorisation letter Attached ( )
3. Copy of passport (including copy of residence visa) Attached
( )
4. Copy of DM Building Permit (for Temporary / Construction Supply) Attached ( )
TERMS AND CONDITIONS FOR SUPPLY OF ELECTRICITY & WATER
In applying for the supply of electricity & water the Consumer specifically agrees to comply with the following rules and regulations
and any further rules and regulations that DEWA may introduce from time to time.
REQUIREMENT
GENERAL GUIDELINES
i. Central A/Cs, Chillers/Refrigeration Plants, Industrial Capacitor banks with suitable automatic step-control
Plants, etc.: incorporated within or external to the Control-Panel.
ii. Package & Split A/Cs, Machines, Pump-Motors and Individually connected capacitor, incorporated within
other Machines: Control-Panel or Capacitor Banks with suitable automatic
step-control for a group of machines.
iii. ‘Window’ type A/C units: Individually connected capacitor, incorporated within
Control-Panel or Capacitor Banks with suitable automatic
step-control for a group of machines.
REQUIREMENT
GENERAL GUIDELINES
i. Central A/Cs, Chillers, excluding AHU Fan-motors: U.V. relays with timer, incorporated within the Control
Panel.
ii. Package & Split A/Cs, excluding AHU Fan-motors: U.V. relays with timer, incorporated within the Unit/its
Control Panel.
iii. ‘Window’ type A/C units: U.V. relays with timer, incorporated with necessary
contractor/s within Distribution Board/s for a group of
units.
APPENDIX 'G'
2. Submit load schedules and drawings to DEWA Consumer Services Department and
obtain DEWA’s approval.
4. Register application with DEWA after getting item (2) & (3) above.
7. After inspection of the project arrange for inspection by JAFZA and DEWA (Electrical
Division) and clear all snags raised during inspections.
RAINFALL DATA
5 0.1281 1
10 0.1866 1
15 0.2537 1
20 0.3261 1
25 0.4003 2
30 0.4732 2
35 0.5427 2
40 0.6069 3
45 0.6649 3
50 0.7165 4
55 0.7615 4
60 0.8004 5
65 0.8337 6
70 0.8619 7
75 0.8857 9
80 0.9056 11
85 0.9221 13
90 0.9359 16
95 0.9473 19
100 0.9568 23
105 0.9645 28
110 0.9709 34
115 0.9762 42
120 0.9805 51
125 0.9840 63
130 0.9869 77
135 0.9893 94
140 0.9913 114
145 0.9929 140
150 0.9942 171
155 0.9952 209
160 0.9961 256
165 0.9968 313
170 0.9974 383
175 0.9979 469
180 0.9983 574
These figures are based on rainfall data from Sharjah from 1949 to 1968 and then figures from
Dubai from 1969 to May 1990. The above table shall be used as a guideline only. The user must
check the accuracy and correctness of the data.