International Journal of Advances in Mechanical and Civil Engineering, ISSN: 2394-2827 Volume-4, Issue-1, Feb.

-2017
http://iraj.in
THE BARRIERS TO THE IMPLEMENTATION OF INDUSTRIALIZED
BUILDING SYSTEM (IBS) IN HIGH RISE STRUCTURE IN
SELANGOR
1
MUSHTAQ AHMAD, 2OSAMA OMAR HASENESHKORFU, 3KASHIFNIGAR
1
Department of Civil Engineering; UniversitiTenagaNasional Malaysia Putrajaya Campus
2
School of Built Environment; Infrastructure University Kuala Lumpur Malaysia (IUKL)
3
Department of Civil Engineering; CECOS University Hayat Abad Peshawar, Pakistan
E-mail: 1ma_5099@yahoo.com, 2Kashifnigar@yahoo.com, 3osama.shk72@gmail.com

Abstract- Industrialized building system (IBS) is adopted as an alternative construction industry in Malaysia. This study is
conducted to investigate the barriers in the implementation of IBS in Selangor, Malaysia. Quantitative study was carried out
to collect primary data. Questionnaire survey was conducted among CIBD employees and construction experts involved in
IBS projects. Lack of awareness among the people, lack of government incentives and promotion, lack of manpower, low
quality and poor skills and knowledge are the top most barriers in the implementation IBS construction in Selangor. In the
conclusion, the acceptance level of IBS among experts and general public found lower further studies need to be carried out.
The study recommends awareness, skills and training program and government initiatives of promotion for the
implementation of industrialized building system (IBS) in Selangor, Malaysia

Key Words- Barriers, Implementation, Industrialized building system (IBS), High Rise structures; Selangor

I. INTRODUCTION including innovation, motivation of workforce,


scheduling, quality, safety and unskilled overseas
The Construction industry plays vital role in the workers are on the top prior issues in implementation
country economy. The Malaysian Productivity Report of IBS in Malaysia Malaysian dependency on
(MRP, 2013) revealed statistical data indicated that overseas unskilled workers, which has lack of
construction industry growth rate increased from knowledge and less productive rate in construction, is
4.5% in 2011 to 18.5% in 2012 with gross domestic the main problem in construction industry. The key
product GDP of 3.4%. Improvement has been aim of this research study is to investigate barriers to
recorded in mega construction projects in 2012 both the implementation in industrialized building system
private and government sectors in Malaysia. in Selangor state Malaysia. Research objectives are
According to world commission for environment and listed as;
development, (1987) life of common people changed
now and new ideas of sustainably development, 1. To determine the barriers in implementation of
economic growth, increasing population in the world IBS in high rise buildings in Selangor;
change the behavior of the people which directly or 2. To study level of acceptance for IBS
indirectly effect our environment. implementation in high rise buildings in
Hamid et al., (2008); CIDB, (2003-07) defined Selangor;
industrialized building system (IBS) techniques use in 3. To explore the ways to reduce barriers in
construction in which components developed on/off implementation of IBS in high rise building and
the site assembled into a structure to reduce extra cost promote to use IBS in Selangor State, Malaysia.
and time. According to CIDB, (2007) industrialized
building is made off precast components, innovative Primary significance of this study is investigation of
fabrication of components such as steel, concrete barriers in ways of IBS implementation in high rise
block and timbers structures. buildings. Investigation of the barriers is important to
On site fabrication and construction process of find which further help to develop strategies and
structure components of IBS are safe, innovative and solve the major issues in the implementation of IBS.
green (CIBD, 2007; CIBD, 2005). Presently,
industrialized building system (IBS) in developed II. LITERATURE REVIEW
countries comes out to cope various construction
problems such as to reduce land space, cost, time and Sharni& Ismail, (2003); Abdullah & Egbu, (2009)
low productivity labor etc (Nawi et al., 2014; defined IBS with more wider scope and extensive
Yahya&Shafie, 2012; Kamar et al., 2009). IBS view as IBS is transformation of traditional
roadmap survey study revealed that since 2003-2010 construction attitude, pre fabrication of constructional
only 15% IBS system was followed in the components off sites and once fabricated transport to
construction projects completed locally in Malaysia the site and assembled, modern method of
(Kamar et al., 2009; CIBD, 2007). Recently, construction and off site production are the key
construction industry is facing many challenges definition of IBS terms use in construction.

The Barriers to the Implementation of Industrialized Building System (IBS) in High Rise Structure in Selangor

94
International Journal of Advances in Mechanical and Civil Engineering, ISSN: 2394-2827 Volume-4, Issue-1, Feb.-2017
http://iraj.in
Rahman& Omar, (2006) defined industrialized that using IBS system broadly in many projects done
building system (IBS) as the process of construction in Malaysia such as hybrid construction technique to
of building erections based on previously fabricated build national landmarks such as Bukit Jalil Sport
construction components off site. Complex, Kuala Lumpur Convention Centre,
Chung and Kidar, (2007) describe IBS as the huge Lightweight Railway Train (LRT), Petronas Twin
production of building components transport to the Towers, KL-Sentral, KLIA airport, construction of
actual site erected the building based on design and new administration capital of Malaysia in Putrajya
shape. and first Malaysia cyber city (Cybberjya) are the
example of IBS construction in Malaysia. The current
2.1 IBS Overview in Malaysian Context IBS systems used in Malaysia housing projects are
According to Thanoon et al., (2003) industrialized large panel systems, metal form systems and modular
building system is not new in Malaysia, the history system. In the past, many foreign based companies
start just after independence of Malaysia in (1960) involved in developing IBS construction system in
when country housing ministry and local government Malaysia but Malaysia was always keep to develop
traveled to some European countries to study their IBS technologies named Zenbes, CSR, IJM and HC
housing program. IBS was initiated in (1964) in precast. Kamar et al., (2009) documented that total
Malaysia, just after successful visit to Europe and registered number of contractors in 2007dealing with
government lunched their first project on 2.7 acres IBS in Malaysia is 895 companies. Registered IBS
land along jalanPekeliling Kuala to construct 300 manufacturer in Malaysia until 2007 is 138 producing
units in seven blocks and 17 stories tall with forty 347 IBS products which are available in the market.
shops lots and aim was to enhance quality, reduce Malaysia is in the row of developing nation by using
completion time compare to conventional method of IBS technology with cooperation of many local and
construction and build low cost buildings, project was foreign companies and completed many projects.
completed in 27 months period (CIBD, 2003). Government of Malaysia emphasized to use IBS
technology in government and private project any
government projects must not be less than 70% use of
IBS and IBS must be the part of construction
documents (Kamar et al., 2009).

2.2The Barriers to IBS Implementation in


Malaysia
Strong encouragement of IBS implementation from
the government and private sectors construction
industries has big contribution to implement IBS in
Malaysia (Kamar et al., 2009). Unavoidable benefits
of IBS and highly progress in construction witnessed
hurdles and barriers to the implementation on large
scale of Malaysia Selangor state is also one of them.
Based on past studies followings barriers have been
Figure 2.1; Development of IBS in Malaysia (Abedi identified to IBS implementation in Malaysia.
et al., 2011) 2.2.1 Awareness and Knowledge
IBS Roadmap review (2007) reported that to adopt
Figure 2.1 shows that much effort has been done by IBS technology system based on client good
Malaysian government to establish IBS system in awareness and knowledge, and surely they will
country since 1960s onward for future and much encourage if they have idea and knowledge.
improvement has been reported. In addition to, Knowledge deficiency among skilled worker
second IBS project in Malaysia was launched in including designer, engineers and others led the
1965, consist of six blocks seventeen stories flats and project delay and request for extra time to finish task
three buildings eighteen stories flats at Penang state. also one o the hurdle in IBS implementation. IBS
Numerous private construction industries with Roadmap review, (2007) awareness of IBS will
cooperation of foreign investment involved in IBS accelerate the overall performance of the project and
and in the result several method of IBS construction it is knowledge of IBS is necessarily important for all
developed in Malaysia. Selangor State government stakeholders. Chung &Kadir , (2007) observed that
(PKNS) in the period of 1981-1993 made contract most of the authorities has no idea and knowledge of
with Germany based construction company IBS design which further take them long time to
PratonHaus to build low and high cost house for the understand the design and process which delay
development of new township in Selangor. The overall project duration.
company built around 52,000 house units using IBS 2.2.2 Planning and Implementation
technology in Selangor (CIBD, 2003). Thriving At presents, the pre-casters and contracting firm in
period of Malaysian construction 1994-1994 shows Malaysia are involved after tender stage of the

The Barriers to the Implementation of Industrialized Building System (IBS) in High Rise Structure in Selangor

95
International Journal of Advances in Mechanical and Civil Engineering, ISSN: 2394-2827 Volume-4, Issue-1, Feb.-2017
http://iraj.in
construction value chain. However, the paper important and this is one barrier in the
observed that, IBS design needs to be addressed and implementation of IBS in Malaysia.
plan form the design stage to be successful adopted
trough the integration of pre-caster, designer and III. METHODOLOGY
contracting firm (IBS Roadmap Review, 2007). As a
result, a lot of IBS project in Malaysia is not cost Questionnaire was designed based on previously
effective as it is proposed to be an alternative design conducted surveys which consist of several sections
to traditional method. IBS application has to be to validate research objectives. Reliable close ended
incorporated during the design stage. questionnaire was generated comprise 20-30
Rahman and Omar, (2006) alignment and leveling are questions to represent the aim of the study. Structure
critical to the IBS implementation but lack of of the questionnaire is given in Table 2.1.
planning and management not handle them well so
for proper erection of structural member’s alignment Table 2.1; IBS questionnaire structure
and leveling is important.
2.2.3 Negative Perception
Lack of knowledge and unavailability’s of skilled
workers in the past, the image of IBS is presenting
negatively today (Rahman& Omar, 2006). Several
reasons presented to indicate negative impact of IBS
is due to low quality production, alignments, leveling,
mass construction method, leakage unpleasant
architectural appearances and other drawbacks. Due
to the poor architectural design, the old pre-fabricated
buildings have given the public, bad impression about
pre-cast concrete. Clients are often in doubt of using
IBS because of fear of customer rejection. Even
construction professionals are in doubt in IBS
3.1 Respondents of the Study
technology and relate IBS with a potential post-
Many construction manufacturing companies are
construction problem. In addition, it is always not
involved in IBS in Selangor state. According to
popular among the designers as they found pre-
construction industry development board, (CIBD,
fabrication has limiting their creativity in design
2011) registered companies are 36 in Malaysia and
process (Hamid et al. 2008).
most of them are in the state of Selangor and Kuala
2.2.4 Components Standardization
Lumpur. CIBD employees and CIBD registered 10
One of the key reasons of IBS technology success in
construction companies involved in IBS were the
construction is utilization of standard components in
respondents of the study.
construction. Study revealed that low quality
components using in IBS is obstacle and issue to
3.2 Sample Size
implement IBS in future. Every skilled person related
In this study, total 60 questionnaires were distributed
to IBS has standard, architects, designer, engineers,
among the following construction experts CIBD staff
contractors and the material technology use in IBS.
;Company owner; General Manager /Project Manager
2.2.5 Transportation /Project Engineer ; Project Designer; Project
According to Hass &Fagerlund, (2002) to manage
Contractor etc.
IBS construction feasible transportation is important.
Transportation of fabricated components and using
3.3 Data Analysis
crane, lift machines to erect the components
Frequency and Descriptive Analysis (Mean and Std
according to the design and nature of the work. When
deviation) was determined using SPSS.
structural members transported to the site need
additional machinery to erect and complete the
project. Advance and quality transportation is

IV. RESULTS AND DISCUSSION

A total of 60 questionnaire samples were distributed among CIBD staff and construction expert involved in IBS
construction in Selangor Malaysia. The survey response was 95.0%. Likertscale five was used where 1.0
strongly disagrees and 5.0 strongly agree.

4.1 Level of Acceptance of Industrialized Building System


Among others factorstop five IBS level of acceptance is shown in Figure 2.0. The respondents of the study
claimed that more research studies should conduct to enhance the level of acceptance in IBS. More research

The Barriers to the Implementation of Industrialized Building System (IBS) in High Rise Structure in Selangor

96
International Journal of Advances in Mechanical and Civil Engineering, ISSN: 2394-2827 Volume-4, Issue-1, Feb.-2017
http://iraj.in
studies will improve and spread awareness among public regarding IBS construction system. In the parallel
CIBD should encourage private and public sectors is ranked top. Less involvement of the government sectors in
IBS shows lower level of acceptance. Normally construction companies followed client request so the client
lack of awareness and attitude towards IBS shows the main barriers in Selangor. This part of the study is
concluded likewise IBS acceptance level in Selangor is not very high according to the obtained results
respondents neutral views regarding higher cost of IBS mean value of 3.28 shows that high cost of IBS is not the
reason of acceptance IBS in construction. In contrast of the findings respondents highly recommend that CIBD
should have to encourage private and government sectors to accept and adopt IBS construction in Selangor.

3.5
3.38 3.38
3.4
3.28
3.3 3.24
3.2
3.1 3.03
3
2.9
2.8
Conduct more CIBD sould Higher cost public sector Companies
research encourage affect IBS involved more less
studies private and acceptance in IBS involvment in
public sector IBS

Figure 2.0: Level of Acceptance of IBS

4.2 Barriers to Industrialized Building System


This study has found five top ranked factors as shown in Figure 3.0. Most of the respondents claimed that lack
of awareness among public is one of the main barrier in the implementation of IBS. Lack of government
incentives and promotion among private and government sectors is ranked second. Lack of manpower followed
by the low quality and poor skills and knowledge are the top most occurring barriers to the adoption of IBS in
Selangor. Chung &Kadir (2007) found similar barriers factors and stated that lack of manpower and lack of
general public awareness are the amongst top ranked barriers factors. Lack of knowledge and skills lead the
employees to low quality and which is also shown few of the most top ranked barriers in the implementation of
IBS in Selangor. In every system development and promotions government played huge role but in this scenario
study found that lack of government promotion in private and public sectors lead the factor to the top barriers in
the adoption of IBS in Selangor. In contrast, legal and cultural issues were ranked lowest ranked barrier
followed by the lack of technology issues. Study found that cost, time and wastage of material are the least
affecting barriers to the implementation of IBS in Selangor.

4.8 4.7
4.6 4.42
4.4 4.28 4.26
4.2 4.1
4
3.8
Lack of Lack of Lack of Low quality Poor skill and
awareness government manpower knowledge
among people incentives and
promotion

Figure 3.0: Barriers to Industrialized Building System

4.3 Method to reduce Barriers in the Implementations of IBS


In the last section of the questionnaire, respondents were asked to rank the most influential methods to reduce
barriers in the implementations of industrialized building system (IBS) in Selangor is shown in Figure 4.0. The
The Barriers to the Implementation of Industrialized Building System (IBS) in High Rise Structure in Selangor

97
International Journal of Advances in Mechanical and Civil Engineering, ISSN: 2394-2827 Volume-4, Issue-1, Feb.-2017
http://iraj.in
study has sum up top most ranked method suggested by the respondents to reduce the barriers of industrialized
building system (IBS) are create awareness program among public has found the most influential method of
reducing barriers in the implementation of IBS in Malaysia. The second influential method was ranked by the
respondents is formal education in business and engineering process will significantly reduce the barrier present
in the implementation of IBS in Malaysia. Offer more incentives for users of industrialized building system
(IBS); Training program of local labors to encourage and reduce manpower cost to hire professional from
abroad followed by scientific supply chain management will significantly reduce barriers in the implementation
of industrialized building system (IBS).

5
4.8
4.6 4.78
4.68
4.61
4.4
4.2 4.4

4 4.1
3.8
3.6
Create awareness Formal education Offer more Training program Scientific supply
programs in business incentives for user for local labors chain
process management

Figure 4.0: Methods of barriers reductions

CONCLUSIONS AND RECOMMENDATIONS market. BuHu 9th International Postgraduate Research


Conference. (pp15-25). Salford, United Kingdom
[2] Abosaad. H, Underwood. J and Boveny. S (2009);
Industrialized Building Systems (IBS) is a Towards an information system representation of OSM in
construction process that utilizes techniques, facilitating the virtual prototyping of housing design.
products, components, or building systems which BuHu9th International Postgraduate Research Conference
involves mainly the prefabricated components and (IPGRC): Salford, United Kingdom, 509-520,
[3] BeedleLS , Mir M. Ali , Armstrong PJ . (2007); the
onsite installation. Successful and effective Skyscraper and the City: Design, Technology, and
implementation of IBS in Malaysia construction Innovation. Books 1 and 2 . Lewiston, NY: The Edwin
industry can offer various benefits compare to MellenPress ;
[4] Chung L. and P.Kadir.M, (2007); “Implementation
conventional in-situ systems. Study concludes that
strategies for industrialized building system” Phd thesis
awareness of industrialized building system in university of Malaysia
Selangor; private and in government level incentives [5] Construction Industry Development Board, Malaysia
should be provided to attract people by (CIDB).(2007) “IBS Digest at Malbex”, IBS Digest,
implementation of IBS as well as promote with Special Issues on 24th Malaysian International Buildin
Exposition, pp. 19-22,
benefits and flexible cost. [6] Construction Industry Development Board, Malaysia
Study recommend local as well as foreigner (2010); “New perspective in industrialization in
construction employees properly be trained and construction a state of the art report CIB Publication 329,
organize training program to enrich employees with [7] Haas, C. T., &Fagerlund, W. R. (2002) preliminary
research on prefabrication, pre-assembly, modularization
high skills and knowledge. In the last study and off-sitefabrication in construction. The Construction
recommend based on findings scientific supply chain Industry Institute, The University of Texas at Austin
management should be employed in the process to [8] Hamid, Z., Kamar, K.A.M., Zain, M., Ghani, K., Rahim,
A.H.A., (2008) “Industrialized Building System (IBS) in
enhance and promote industrialized building system
Malaysia: The Current State and R&D Initiatives”
in Selangor, Malaysia. Due to short time study has Malaysia Construction Research Journal (MCRJ), Vol. 2
limitation of study area in Selangor state only. This (1), pp 1-13
study further recommends to extent the study area to [9] Hong chin Ong, (2006); “Analysis of IBS for school
other parts of the Klang valley as well as cost complex” Master thesis university of Malaysia
[10] IBS Roadmap Review (Final Report) (2007), 2007, IBS
comparison with traditional building system in Centre, Construction Industry Development Board,
Malaysia. Malaysia, Kuala Lumpur (unpublished)
[11] JabarIzatullaili, Faridah Ismail, ArniatulAiza Mustafa,
(2013); Issues in Managing Construction Phase of IBS
REFERENCE Projects, Procedia - Social and Behavioral Sciences 101
[12] KamarulAnuarMohdKamar, ZuhairiAbd Hamid,
[1] Abdullah, M.R. &Egbu, C. (2009). IBS in Malaysia:
Mohamed Nor, AzhariAzman, MohdSanusi S Ahamad,
Issues for research in a changing financial and property
(2011); “Industrialized Building System (IBS): Revisiting

The Barriers to the Implementation of Industrialized Building System (IBS) in High Rise Structure in Selangor

98
International Journal of Advances in Mechanical and Civil Engineering, ISSN: 2394-2827 Volume-4, Issue-1, Feb.-2017
http://iraj.in
Issues of Definition and Classification” Int. J. Emerg. Sci., [21] Rahman A.B.A and Omar.W (2006); “Issues and
1(2), 120-132, challenges in implementation of IBS in Malaysia” Journal
[13] Kamar, K. A. M., Alshawi, M.and Hamid, Z, (2009); of Structure engineering
“Barriers to industrialized building system (IBS): the Case [22] Senturer, A. (2001) Which Industrialized Systems Are
of Malaysia” International Postgraduate Research Appropriate for Turkey. Available at:
Conference (IPGRC 2009), The University of Salford, www.emu.edu.tr/academic/publicat/archpub/arch-32a.htm
[14] Kiong Ng Ban and ZainalAbidinAkasah,(2011); [23] Shaari. SN and Ismail, (2003); E. Promoting the usage of
“Maintenance Management system for industrialized Industrialized Building System (IBS) and Modular
building system” International Building & Infrastructure Coordination (MC) in Malaysia. Construction Industry in
technology conference Engineers (Board of Engineer Malaysia)
[15] Kong Xi Haw, (2009); “Barriers in the implementation of [24] Thanoon, W. A. M., Peng, L. W., Abdul Kadir, M. R.,
Industrialized building system in Malaysian construction Jaafar, M.S. and Salit, M.S. (2003).The Experiences of
industry” Master thesis: University Technology Malaysia Malaysia and Other Countries in Industrialised Building
[16] Majzub (1977); “Modular housing systems used around System in Malaysia, Proceeding on IBS Seminar, UPM,
the world” International Journal of Housing Science Malaysia
[17] Malaysian Productivity Report, (MPR) (2013); Malaysian [25] Waleed, T., Mohd, P. D., Abdul, S. A., Abdul Kadir, M.
productivity Coorporation, Kualal Lumper R., &Abang Ali, A. A. (1997); Industrialized building
[18] NFPA. (2006). Life Safety Code 101. National Fire systems.Proceeding of Seminar on Affordable Quality
Protection Association. Housing, Housing Research Centre, Univ. Putra, Malaysia
[19] NawiMohdNasrunMohd,, Angela lee, Mohamed Nor, (UPM).
Azhari azman3, KamarulAnuarMohamadKamar, (2014); [26] Warszawski A (1999).Industrialized and automated
“Fragmentation issue in Malaysian industrialized Building building system. E & FN Spon: TechnionIsrael
system (IBS) project” Journal of Engineering Science and [27] Institute of Technology.
Technology [28] World Commission on Environment and Development,
[20] Pan W., Gibb, A., Dainty, A. R. J. (2008) Perspectives of (1987). Our Common Future Oxford: Oxford University
UK housebuilders on the use of off-site modern method of Press.
construction, Construction Management and Economic, [29] YahyaMuhamadAzani&MuhamadNurSafwanShafie,
25, 2, 183-19 (2012).Level of acceptance towards industrialized
Building system (IBs) in Malaysia” International Journal
of Sustainable Construction Engineering & Technology



The Barriers to the Implementation of Industrialized Building System (IBS) in High Rise Structure in Selangor

99