SBPL-PM Usermanul Shutdown Maintenance
SBPL-PM Usermanul Shutdown Maintenance
Submitted
To
By
Plant Maintenance
Shutdown Maintenance
Jan 2023
Version 1.0
Shutdown Maintenance
User Manual – Plant Maintenance
DOCUMENT DETAILS:
Contents
1. Raising of Shutdown notification to notify the responsible Maintenance department/ main work centre.
The Shutdown notification will be raised by either operation group or by maintenance personnel.
Notification release (Put in process) by maintenance department.
It will enter a brief description of Work to be done, Reference object (Functional Location / Equipment) related with
that Shutdown work (If there is any), optionally the detail description in subject long text and task required to be
done.
B.PROCEDURE
A. Access the transaction choosing one of the following navigation options:
SAP Menu Logistics > Plant maintenance > Maintenance processing >
Notification > Create
Transaction code IW21
B. On the screen Create PM Notification: Initial Screen, make the following entries:
Field name Description R/O/C User action and Comment
values
2. On the screen Create PM Notification: , enter the following entries as specified in the table below and depicted
in the screen shots:
(Note: In the table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” = Conditional)
Enter all relevant field as well as mandatory like equipment, Main work center, reported by etc. marked in red color
or select from drop down box or by pressing F4
Enter Object part, Damage & cause code or select from Drop down as shown in below screens for breakdown
analysis.
Here enter all mandatory filed like breakdown check box, malfunction end date date and time while doing NOCO for
Notifications.
▪ Additional text can be added by user in the Text field to describe the task or if suitable task
A.USE
The Notification will be received by the concerned Maintenance department to which it was referred. An authorized
person from that dept. will release the notification after assessing the relevance of the job required. Before releasing
the notification, he will check/edit the Required Start / End dates, Planner group and Main work center and assign
task(s) if not entered before.
B.PROCEDURE
2. On the screen Change PM Notification: Initial Screen, make the following entries:
Click Green Flag button at top left of the screen to put Notification in process as shown in the above screen.
After putting Notification in Process Status of Notification will get changed from OSNO to NOPR as shown
below.
a. An Order can be created directly from the Notification screen. To create an Order directly from the notification
screen click create order, as shown in the above screen.
Then one pop will come as shown below, select the order type, work center etc. and then press enter or click
SAP Menu Logistics > Plant maintenance > Maintenance processing >
Order>Create (Special) > Order for notification
Transaction code IW31
On the screen Create Notification Order: Initial Screen, make the following entries:
(Note: On above table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” = Conditional)
b. On the Create Shutdown Maint. Order: Central Header Data will get copied from the Notification e.g. Order
Header, Planner Group, Maint work center, Reference object etc. If any changes are required it can be done.
USE :
Change the Shutdown maintenance Order of a Notification
Procedure:
SAP Menu
Logistics > Plant maintenance > Maintenance processing > Order
>Change
Here Check CC_ key to “calculate work” and ensure cntrl key to be PM01 and duration unit -H
Here select correct activity type –‘PMTECH’& C.key > calculate work to each operation ,enter correct duration &
duration unit then enter ,will calculate the total work done for each operation .
Here add components or select from drop down, add required quantity. Assign components to required operation
Once components added, Select the line item 10, then click on for material availabity check,
Save and click on to release the order, status changed from Create to release as shown in below screen.
Via Menus Logistics > Material Management > Inventory Management > Goods
Movement > Goods Movement (MIGO)
Tick on Item ok as shown above screen, click on save button on header menu
SAP menu
SAP Easy Access > Logistics > Plant maintenance > Maintenance
Processing > Completion confirmation > Entry > Collective time
confirmation. IW41 – Without Selection
Transaction code IW41
Enter Order number and click on arrow, following screen will be displayed:
Here enter all relevant field like personal number for each operation, actual duration etc. Then click on right arrow
for next operation if any
After click on Save , order will get confirmwd with message “Number of confirmations saved for order
7100000000: 1”. Work Order status now has CNF status as shown in below screen ,
Click on the technical completion flag button, the following pop up window appears
Here enter malfunction end date & time , the clock on save ,now order is technical completed.
NOTE: Herewith Order settlement will be done by finance department .final settlement screen will be displayed
Cost of orders becomes zero
To check Documents flow for order click on red mark as shown in below screen