EC7080 Project Progress Form

Section 1: Project details

Project Name DESIGNING A POWER ELECTRONIC CONVERTER FOR OPTIMAL SEA


WAVE ENERGY HARVESTING

Arampath K.G.S.B. 2019/E/008


Team Member and E-
Number
Medagedara M.I.R. 2019/E/078

Principal Supervisor Prof. T.Thiruvaran, (Eng. R.Valluvan)

Associate Supervisors Eng. R. Valluvan, Eng. S. Sangar

Section 2: Project Objectives and Timelines

• Please list your objectives for the projects in bullet points.

➢ Designing a power electronic converter for optimal sea wave energy harvesting
while considering oscillating water columns.
➢ Design a prototype (scale down) version circuit and simulate it using accurate
software.
➢ Scaling down the devices for modularity.
➢ Finding a 100% electronic solution without mechanical voltage stabilization.
➢ Eliminating / Reducing voltage fluctuations
• Detailed Project Timeline for this Semester.

Section 3: Bi-weekly Project Progress

• Please list your current bi-weekly tasks in bullet points and note the extent to which
you have achieved them. (Indicate the % of completion)

➢ Regulator Circuit errors were fixed (90%)


➢ Finalized the Inverter circuit (90%)
➢ Finalized the simulation of the full circuit (95%)
➢ Finlazed the full circuit schematic (90%)
➢ Designed the Schematic using proteus Designer (90%)
• Please list any other achievements /improvements not listed in the previous plans.
(Optional)

➢ Designed the PCB layout using Proteus Designer (70%)

• Please list any knowledge or skills you have obtained during the last two weeks.
(Optional)

PCB Schematic design using proteus Designer


PCB Layout Designing Basics using proteus Designer
SMD Technology soldering technoques

• Indicate any challenges you faced to achieve your targets. Please indicate the
plans to overcome those challenges. (Optional)
Section 4: Supervisor Meeting

• Indicate the Date you met your supervisors (Including associate supervisors).
(Minimum two meetings should be done.)
Date Key Points Discussed Name of the Supervisors
present
11.10.2023 Share simulation results and get Eng. R.valluvan
advice
12.10.2023 Discussed about input signal Eng. R. valluvan
genration and we suggested a
method to genarate – Damping
effect of a motor after free stop

• Provide a list of the most recent bi-weekly demo outcomes. Include details on the
demonstrated features and their completion percentage compared to the expected
final demo. If available, please attach a photo from the demo.
Section 5: Next Bi-Weekly Plan

• Please indicate the next Demo plan. What are you going to show in that demo?

• Planned tasks to be completed in the next two weeks.

Sub Task Assignee Deadline


Heat Discipation Technique 2019/E/078, 2019/E/008 2023.11.03
Proper Budget Planning 2019/E/078, 2019/E/008 2023.11.03
Power Budget Calculation 2019/E/078, 2019/E/008 2023.11.03
Noise Consideration 2019/E/078, 2019/E/008 2023.11.03

Supervisor’s feedback regarding


progress and demo should start the fabrication for testing.

Supervisor ‘s signature