Days Task Originator
Monday
· First task Self
· Second task Ateli Biambo

· Third task Ateli Biambo


· Forth task
· Fifth task
Tuesday
· First task Ateli Biambo
· Second task Ateli Biambo
· Third task
· Forth task
· Fifth task
Wednesday
· First task Ateli Biambo
· Second task Ateli Biambo
· Third task Ateli Biambo
· Forth task
· Fifth task
Thursday
· First task Ateli Biambo
· Second task Ateli Biambo
· Third task
· Forth task
· Fifth task
Friday
· First task Ateli Biambo
· Second task Ateli Biambo
· Third task
· Forth task
· Fifth task
Miscellaneous
Item 1
Item 2
Item 3

Supervisor Remarks

Action Plan
C. D. PRINCETON NIGERIA LIMITED
WEEKLY REPORT

o 20/01/2023

Description of Task

Opening a 2023 HSE Statisitics Sheet for the year


Monitoring offloading of 20 drums of Hypochlorite, 10 drums of Shell
Turbo T68, 700 bags of Caustic Soda
Shrinkwrapping and strappping of 10 drums of Shell Turbo T68 for NLNG
Delivery

Strapping, shrinkwrapping of 300 bags of Caustic Soda Pearls for NLNG


Delivery
Receipt of Poker Vibrator Concrete and documenting

Preparation of Poker Vibrator for Nlng Delivery


Preparing Wilhelmson Laboratory items for delivery at BW Offshore
Updated Summary Sheet for Outstanding PO's

Preparation of Documents for Elcrest Tender


Deflating swollen hypochlorite Drums at NLNG Warehouse

Developing a google sheet for Monthly Warehouse Stock report for


Warehouse 1 & 2
Collection of all outstanding Waybills at NLNG
NIGERIA LIMITED
REPORT

Status/Achievement of Task Report/Remarks

Achieved as planned
Achieved as planned

Achieved as planned

Achieved as planned

Achieved as planned

Achieved as planned
Achieved as planned
Achieved as planned

Achieved as planned
Achieved as planned

Achieved as planned

Achieved as planned