Diagrama PERT a investitiei: 'LOCUINTA PARTER', generata in data de: 21.03.

2023 12:41

0 0 0 0 4 3 11 0 11
Start - Start 0001.A.1 - INFRA+SUPRASTRUCTURA - Finish

0 0 0 7 7 10 11 0 11

0 11 10
0001.A.2 - ARHITECTURA

0 0 10

1 1 1
0001.B.1 - INSTALATII ELECTRICE

10 9 10

2 3 4
0001.C.1 - INSTALATII ALIM APA

8 6 10

0 8 7
0001.C.2 - INSTALATII DE SCURGERE

3 3 10

0 1 0
0001.C.3 - MONTAJ UTILAJ ALIM APA

10 10 10

0 0 0
c - 0-UTILAJ ALIM. APA

11 11 11

5 4 8
0001.D.1 - CONDUCTE SI RADIATOARE

7 2 10

2 1 2
0001.D.2 - MONTAJ UTILAJE SI
ECHIPAMENTE CT
10 8 10

0 0 0
d - 0-UTILAJ CT

11 11 11

3 1 3
0001.E.1 - INSTALATII GAZE

10 7 10