Professional Documents
Culture Documents
while reducing operating costs. Many functions of new = 184 Trillion Btu/Vear
�
4% Separations
� 6% Ancillary Operations
5%Drilling 6000 �-------,
Petajoules (PJ) per Year
2% Blasting
� 6%Digging
5000
4000
Other Manufacturing
� 10% Ventilation
3000
2000
Petroleum Refi n i ng
Construction
....
�
Agriculture
Forestry
Chemical & Fertilizers
2%Dewatering Cement
1000 Alum. & Non-Ferrous
Iron and 5teel
Paper
17% Materials Handling o
1990 1993 1996 1999 2002 2005 2008
4% Materials Handling Diesel Equip.
FigA. Energy usage per segment.
Electrical Equip.
Ce ment 1%
continually operate during production shifts [4].
conveyors feed the fine crusher house, which contains
These
From From
4.l6KV BKR-Al 4.l6KV BKR-A2
4l60V MCC Al
1 4 - 3/C SOOKcmil
-'-' - '-'
} 4 - 3/C SOOKcmil
4l60V MCC A2
�
0-
- '- _._._._._._.- _._._._._._.- _._._.- ._._._._._._._._._._._._._._._._._._._.
.
1. .
! ! l200A 1
l200A
1· N.C.
--- � - K -t----·
. N.C. i
1. .
1• I 1 1.
1. I .
1• I 1 1.
1. I .
1 I
I
1 1.
1 .
0 0 0 0 0 0
-- -- -- -- -- -- 0
-- 0
--
'"
N
'"
N rl
'" ... rl
'" '"
N
'" '"
N
'"
N
u u u u u u u
--
'" -- -- -- --
'" -- -- u
--
'" '" '" '" '" '"
To To To To
4160V-480V 4l60V-480V 4l60V-480V 4l60V-480V
1000KVA lOOOKVA lOOOKVA 1000KVA
XFMR XFMR XFMR XFMR
Fig. 5. Typical taconite mine one line diagram.
facility has two feeds of 13.8 kV in a main-tie-main of collecting information from remote process locations for
configuration, each with its own transformer. The 13.8 kV use in central processing calculations. This paper proposes
distribution voltage is then stepped down to 4.16 kV at each the use of the IEC 61850 standard to serve as the backbone
building to feed individual loads. The 4.16 kV busses are for communications for addressing the IED-interface issue.
also configurable in a secondary-selective, main-tie-main The IEC 61850 standard can also be used for controlling
scheme that can be implemented in case of bus failure. This main-tie-main schemes through communications rather than
configuration is often preferred in large mining operations hardwire, in addition to its added SCADA benefits [6].
because it allows critical loads to be transferred to healthy
busses during times of an electrical system fault or
insufficient spinning reserve. Many relays are utilized for IV. IEC 61850-STANDARDOVERVIEW
operating and protecting these facilities including:
IEC 61850 is an international standard titled
instantaneous and time delay overcurrent (50/51 elements),
"Communication Networks and Systems in Substations,"
differential (87 element), under-voltage (27 element), and
developed by Technical Committee 57. The standard focuses
others.
on substation automation [7], and was drafted and adopted in
Electrical protection has evolved over the past three
an effort to unify substation equipment and communications
decades from electromechanical to microprocessor based
on a common platform, regardless of manufacturer. IEC
relays. Protection systems previously consisted of isolated,
61850 is divided into ten sub-sections that range from
hard-wired interlocked electro-mechanical and solid state
defming protocol terminology to conformance testing [7-22].
relays that had limited system visibility. These devices only
"The United States National Institute of Standards and
detected an electrical fault or overload, and lacked a way to
Technology (NIST) has advised the Federal Energy
report additional protection information. With the advent of
Regulatory Commission (FERC) that it has identified IEC
microprocessor based relays, more advanced protection
61850 as one of five 'foundational' standards for smart grid
schemes, that correctly identify faults in acceptable
interoperability and cyber security. This clearly shows that
timeframes, have been developed. Communication schemes
IEC 61850 is foreseeable in the future of all protection,
for providing electrical protection have also evolved with
automation, and control systems throughout the world [23]."
microprocessor based relays [5]. SCADA communications
There are multiple benefits to the IEC 61850 standard,
protocols and standards have been developed for the purpose
which include: support of comprehensive substation
V. SOLUTION OVERVIEW exceed the amount of spinning reserve that can be supplied
This section discusses an IEC 61850 solution applied to a from the electrical source. Because real power does not
simplified application that would be representative of a change at a fast rate, this measurand, as weil as others, can be
taconite facility. The distribution and SCADA system is grouped in a report and sent each minute if desired.
broken down to its base components, and their functionality Additionally, any form of relay can be used with this setup,
is described. as long as it is IEC 61850 compliant. For example, in a
The basic architecture consists of three major components: taconite mine, many differential protection relays are used to
IEDs, programmable automation controllers, and IEC 61850 protect the larger transformers that feed the processes within
to EtherNet/IP gateway modules. These components are all a facility. In addition, if a facility is large enough, there may
interconnected via the network infrastructure, in this case, be an opportunity for co-generation where generator
protection relays would be installed.
copper based Ethernet. Fig. 7 depicts a simplified
visualization of a typical system architecture configuration.
B. IEC 61850 to EtherNetliP Gateway
measurand. Subsequently, the control system can also be A graphical user interface was developed in the Windows
permitted to take remedial action based upon these alarms environment that provides the user drag-and-drop capabilities
[26]. to define parameters that are to be sent to the automation
controller. When the module is configured from the user
interface software, report configurations containing IED
D. Network lnfrastructure
parameters are stored on the gateway module SD card.
From a network perspective, this solution requires the use Additionally, when the user maps the IEC 61850 tags to
of a network switch to interconnect all devices. This switch EtherNet/IP tags, each 61850 tag is allocated a certain
should be a managed type to preserve data quality of service number of bytes depending upon the data type: Boolean,
throughout the network and provide layers of security. A float, double integer, etc. This configuration is also defined
managed switch should be utilized for segmentation of the on the SD card.
network as weil as an additional level of system security. By Tables l and 11 show an example of how measurands and
utilizing the virtual local area network (VLAN) feature of protection parameters would be mapped utilizing this
managed switches, groups of IEDs can be logically separated solution. Table I illustrates various parameters that would be
from other process equipment such as drives and motor of interest to a process engineer in a taconite facility. These
control centers. parameters include fundamental measurands, thermals,
physical status, and protection information. Table 11
VI. THE GATEWAY SOLUTION graphically defines how these data objects are packaged for
The hardware solution that was developed for this delivery to an automation controller with a 32 bit processor.
application is a standalone hardware gateway. This section
TABLE I DATA MAPPING EXAMPLE
describes how the gateway bridges the IEC 61850 and FieldName Da!. Type Size Bits Data Map Color
Transfer Switch A Pos. (A) 8001 1 11
process control network. The gateway module consists of a
Transfer Switch B Pos. (8) Bool 1 U
main processor with various peripherals including a network Fccdcr Rclay I Hcalth (C) Byte 8 U
I Ph. A (D) 32 •
lO/100 Mbit/s copper interface and Secure Disk (SD) Fccdcr Currcnt Dint
Feeder Relay 2 Health (E) Byte 8
interface to store system configurations. .J
Trip Counter (F) Int 16 iJ
The process of collecting data from various IEDs and Ball Mill Phase RTDs (GI Bjtel3J 24 •
Ball MiLI Motor RcLay Hcalth (H) Byte 8 U
converting it to an industry accepted process control protocol
is performed through the concept of multi-threading. Fig. 8
TABLE 11. GRAPHICAL MAPPING REPRESENTATION
depicts the various threads that are executing at any given Bit
location of where the parameter or electrical measurand lies displays fundamental metering data for the device. The
within the array of data to be captured. At the same time, the advantage of the faceplate is that it is a familiar, standard,
data that have changed also set a semaphore, or Boolean tlag, prebuilt, object that can be implemented repeatedly for
indicating new data is to be read by the EtherNet/IP driver. similar engineering designs.
The same process is performed when the parameter is to be
read by the EtherNet/IP driver and published to the controller.
The process can be seen in Fig. 9.
� Data
Data Tag Write Command
The command and control portion of this solution allows control device. As a result, monitoring and re-programming
operators and engineers to change setting groups and also the relay remotely keeps personnel far from any potentially
allows relay actuation from a remote location. It is extremely hazardous environment or situation [6, 25].
important to note that even though the standard defines how There may be a desire to place the relaying and metering in
an IED communicates on an IEC 61850 network, it does not a separate control area away from the switchgear. This is
include configuration information for the protection and contingent upon factors including: available space, current
control functions in a relay. Furthermore, the IEC 61850 transformer burden capabilities, as weil as hardwiring back to
standard does not provide a unified method for designing the control and switchgear. Although this method isolates the
communication-assisted automation, e.g., command and individual from the arc hazard, it introduces additional costs,
control functionality. The development and subsequent use additional space requirements, and additional wiring on
of faceplates is a solution that addresses both of these critical connections. As such, this method may not be viewed
concerns. This solution offers the operations personnel a as optimal.
standard methodology not only to gather the information By using relaying and metering products that include the
from the system, but also to control it. IEC 61850 standard over a common Ethernet communication
media, one can connect remotely to any metering or
protective device with complete isolation from all electrical
B. Sequence of Events
hazards. The entire process can be controlled and monitored
Sequence of Events for electric distribution systems is visually without being near the relays, metering devices, or
defined by IEEE standard C37.1. IEC 61850 allows for the the actual electrical equipment being controlled and
time stamping of target events at the relay level with 64 bit monitored, thus completely eliminating the arc-hazard to
double integer precision. This represents sub-millisecond personnel [25].
accuracy [26]. In addition, as many IEDs are commonly
connected to an absolute reference such as a GPS time clock,
the time stamp associated with each event is therefore E. Demand Side Management
accurate to GPS time quality [25]. Reports can be Energy management is becoming increasingly important
constructed to transfer this timestamp back to control systems for managing the increasing demand for electricity.
to be logged and displayed on workstations. With the Generally, energy management is composed of two
migration of GPS time to the controller level, these components - improving efficiency and managing demand.
timestamps can now be compared, plant-wide with electrical, Demand management is generally achieved by shedding
mechanical, and process systems. For example, timestamps loads during periods of high demand to prevent system
would be useful in reconstructing the sequence of events that overloads.
lead to process facility downtime. A common form of demand management is the use of an
interruptible rate agreement in which the utility can shed
loads in return for a special rate. Interruptible rates are very
C. System Health
beneficial to utilities because it allows them to manage
IEC 61850 defines a quality flag in each logical node that periods of high demand relatively easily. And, although the
can help validate the quality of the measurement received interruptible rate agreement can lead to savings through
from the IED at the SCADA system. This quality indicator is reduced rates, it is generally not a practical option for mining
usually a Boolean or integer value that will indicate a finite companies because it is impractical to take critical loads (or
state of a device, e.g., faulted. The quality flag can also be entire facilities) off-Iine on short notice. A more practical
used to assess the quality of the measurands. Additionally, approach for the mining industry is to implement some form
the time stamp associated with measurands and trip or alarm of load leveling during periods of high demand with the goal
events is also evaluated by a quality flag which indicates of reducing the demand component of its utility bill. This
timestamp accuracy relative to universal time coordinated approach gives mining companies the ability to reduce
(UTC) or other time reference [25]. The system health electricity costs and control how it is done.
quality flag in conjunction with long term trending can help Load leveling can be achieved in many different ways. For
improve predictive maintenance models at mines. example, loads can be shed automatically when the
consumption rate exceeds a predefmed rate called the ideal
D. Safety
rate. Loads with the lowest priority are shed first, followed
by loads with the second lowest priority, and so forth. Other
When metering or protective relays are mounted directly
demand control strategies can include demand prediction
on the front of switchgear or motor control cabinets, certain
such that loads are shed when the predicted energy
safety concerns arise. Operating personnel who are asked to
consumption in the current demand interval exceeds a
interact with the devices on the doors of this type of
specified value.
equipment may be exposed to arc flash hazards, especially
One of the difficulties of implementing load-side demand
during setting changes to the devices that can cause the
management has been the cost of installing monitoring and
actuation of a circuit breaker, contactor, or other secondary
control equipment. By linking the protection and metering [15] IEC, "Communication networks and systems for power utility
devices that include the IEC 61850 standard to the site-wide automation, " in Part7-3: Basic communication structure - Common
control system, mining companies can more easily implement data classes vol. 61850-7-3, ed. www.iec.ch: IEC, 2010, p. 186.
[16] IEC, "Communication networks and systems for power utility
load-side demand management at a relatively small cost.
7-4: Basic communication strucuture -
automation, " in Part
Compatible logical nodes classes and data object classes vol.
VIII. CONCLUSIONS 61850-7-4, ed. www.iec.ch: IEC, 2010, p. 184.
The IEC 61850 standard provides a uniform method of [17] IEC, "Communication networks and systems for power utility
Engineering in September 2013 on his work with the IEC 61850 Thomas Novak (M'83-SM'93-F'05) holds the Alliance Coal
standard. Academic Chair in the Department of Mining Engineering at the
David is an active member of the IEEE lAS and serves as University of Kentucky. His prior employment history includes:
working group chair for the Communication-Based Protection of Director of Mining Science and Technology, the National Institute
Industrial Applications Working Group. He also serves as a for Occupational Safety and Health (NIOSH); Department Head and
member of the Mining Industry Committee (MIC) as well as the C.T. Holland Professor of Mining and Minerals Engineering at the
Industrial and Commercial Power Systems Committee (I&CPS). Virginia Polytechnic Institute and State University (Virginia Tech);
David is also an active voting member of the IEEE Standards and Department Head and G. N. Drummond Chair at The University
Association (SA). of Alabama.
Dr. Novak received his B.S. degree in Electrical Engineering
Joseph Sottile (M'89-SM'01) Joseph Sottile is a Professor of from The Pennsylvania State University, University Park, in 1975,
Mining Engineering with a joint appointment in Electrical and his M.S. degree in Mining Engineering from the University of
Computer Engineering at the University of Kentucky, Lexington. Pittsburgh, in 1978, and his Ph.D. in Mining Engineering from The
His research interests include miner health and safety, mine Pennsylvania State University, in 1984.
electrical system safety and analysis, and incipient failure detection Dr. Novak served as the Chairman of the Mining Industry
of electrical components. Committee (MIC) (2011-12) in the IEEE Industry Applications
Dr. Sottile received the B.S., M.S., and Ph.D. degrees in mining Society (lAS). He has served as a member of the lAS Executive
engineering from The Pennsylvania State University, University Board and was Chairman of the Meetings Department (2000-2002)
Park in 1984, 1987, and 1991, respectively. and Chairman of the Process Industries Department (1994-1998). He
Dr. Sottile served as the Chair of the Mining Industry Committee also served as Chairman (1992-1994) and Vice-Chairman (1990-
(MIC) (1996-1997) and Secretary of the MIC (2007-present). He is 1992) of the MIC. He is a Registered Member of the Society of
currently the Chair of the IEEE Industry Applications Society Mining Metallurgy and Exploration (SME) and is a licensed
Education Department and is a senior member of the IEEE. professional engineer in Alabama and Pennsylvania.