Professional Documents
Culture Documents
CORE
PLANKS
Design Manual 2023 Edition
2
LOAD TABLE
BENEFITS
3-4 TOLERANCES
Camber Design
Camber Accomodations
7-8 SECTIONS
KR 8” Section
KR 12” Section
INSTALLATION
13 Steps 1-4
14 Steps 5-8
15 Steps 9-12
TYPICAL SECTIONS
Product
Overview
Product Overview 1
HOLLOW CORE
LOAD TABLE
Maximum Live Load (psf)
38 90 80 160 140
40 70 65 150 130
42 50 50 135 120
44 30 40 125 110
46 35 115 105
48 25 105 95
50 95 90
NOTES: • Self weight of member is included in load table NOTE: For applications requiring close control of member
• Composite section requires a min. 2½“ topping = 32 psf camber and deflections between adjacent members and
• Strand pattens may vary other constructed elements, see additional discussion
• F’c = 7000 psi (at 28 days) on pgs. 3-4
• F’ci = 4000 psi (at release)
• Topping f’c = 3000 psi (at 28 days)
• Assuming full cross-section available
BENEFITS
01 RAPID CONSTRUCTION
Reduced construction time results in significant
savings. An average of six to eight Hollow Core
planks can be set per hour.
02 ECONOMICAL CONSTRUCTION
Hollow Core is competitive with conventional
materials and methods. It alleviates the need to
combine multiple types of products to build a
floor or roof system.
03 MAINTENANCE FREE
Hollow Core is resistant to corrosion and deterioration.
It does not need to be painted, coated or covered to
protect it from interior or exterior elements.
TOLERANCES
For Hollow Core plank in
relation to camber
CAMBER DESIGN
Per PCI Manual for the Design of Hollow
Core Slabs and Walls (MNL-126-15E)
TOLERANCES
(cont’d)
CAMBER ACCOMMODATIONS
Camber must be accommodated in several design
considerations, including but not limited to:
05 ROOFING DETAILS
SUGGESTED
SPECIFICATIONS
SUGGESTED
SPECIFICATIONS
(cont’d)
WORK INCLUDED:
Furnishing and delivery of all precast planks. Engineering design and shop drawings.
Bearing pads, plank hangers, void dams and Openings larger than 6” in diameter as shown
dowels as specified on Knife River Prestress on structural drawings.
shop drawings as “SUPPLIED BY OP.”
Installation (quotes available upon request). Straps or threaded rods for hanging ceilings,
electrical and/or mechanical conduits, and other
Forming and shoring if required. suspended items.
YB (in) 4 5.63
WT (psf) 99
60
@155 pcf
YB (in) 6 7.73
WT (psf) 121
82
@155 pcf
HOLLOW CORE
DETAILS
PLAN
03 Hangers can be placed near the end of
the span, or two hangers can be placed
within the span.
SECTION 2
HOLLOW CORE PLANKS Design Manual KNIFE RIVER PRESTRESS
Product Overview 10
HOLLOW CORE
DETAILS
(cont’d)
HOLLOW CORE
DETAILS
(cont’d)
SUSPENDING GUIDE:
02 Install Planks
Install each plank in the same position as indicated on the shop drawing.
Lifting and handling should be done with strap slings capable of supporting
the plank weight plus appropriate safety margins. The lifting straps must be
placed at 2 feet or less from each plank end. Do not lift the plank near or at
the center or from any location other than 2 feet or less from each end.
Planks can be temporarily set on the ground but must be set on support
dunnage that is level and carefully placed within 2 feet or less from the end
of each plank. Do not support the plank near or at the center.
07 Proper Penetrations
Penetrations larger than the width of one voided cell should be cut by Knife
River during the manufacturing process. Holes smaller than the width of one
voided cell may be cut at the job site provided, the web or solid area of the
plank is not penetrated. Holes should be neatly cut or drilled. Using a
hammer to make an opening should be avoided. Knife River Prestress
should be consulted prior to cutting openings in the field that will penetrate
webs or sever prestressing strands. Please see the Penetration Guide in
this brochure (located on pg. 10).
09 Ceiling Suspension
Wires, threaded rods or other mechanical devices can be used to
support suspended ceilings, electrical conduits, plumbing or mechanical
equipment. Power-actuated fasteners should be avoided. Care should
be used to drill only in the void area of a plank. Prestressing strand must
not be penetrated. Please see the Suspending Guide in this brochure
(located on pg. 11).
11 Drain Water
Topping slab concrete should have a minimum compressive strength of
3,000 psi. Plank should be topped as soon as possible after the ends of the
plank are enclosed. Plank exposed to wet weather after the ends have been
enclosed may accumulate water in the voids. Water must be removed by
drilling small drain holes into the voids near the ends of the plank, prior to
finishing. Water that can seep into the cells that are enclosed may cause
freeze/thaw damage during freezing temperatures.
BACKER ROD
AND GROUT
NORTHWEST.
OREGON WASHINGTON