610 GSM AS PER TECHNICAL SPECIFICATION. PROJECT: SUBSTATION PACKAGE SS-86 FOR FATEHGARH-III S/S
UNDER TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM
REZ IN RAJASTHAN (20 GW) UNDER PHASE-III PART E1

TITLE: FABRICATION DETAIL OF 400 kV HIGH LEVEL LA SUPPORT


13. 3% EXTRA NUTS, BOLTS AND WASHERS SHALL BE SUPPLIED FOR ERECTION TO ALLOW FOR
STRUCTURE FOR FATEHGARH-III S/S
WASTAGE ETC.
14. STRUCTURE HEIGHT SHOWN IS INDICATIVE. THE SAME SHALL BE ADJUSTED FOR A BUS
HEIGHT OF 12000 MM FROM PLINTH LEVEL.
15. MOUNTING DETAILS ARE INDICATIVE AND SHALL BE AS PER THE EQUIPMENT MANUFACTURER
DRAWING NO: C/ ENGG/ NR-1/ FATEHGARH-III/ EQP/ 400kV/ HLA/ STR