Professional Documents
Culture Documents
3 SOP Display
13 Training Matrix
14 Twin Stop Testing
18 TEED Inspection
42 SCE PSV
SCBA Available
Training IWCF
Training Matrix
Environment Aspect
not available
Register
Risk register Updation
Illumination deficiency
TEED Inspection
HP line Anchoring
MSDS Biocide
BOP Recertification
Training MVT
Training IWCF
CCTV NO PASSWORD
BOP Inspection
Training IWCF
SCE List
TRAINING IWCF
Training MVT
TRAINING INTEGRATED
SCE LIST
AFDSS IC engines
CCTV not working
Insulation exhaust
Competency Training
Training Electrical
PME Pending
MSO Appointment
SOP No BOP
ERP deficiency
BOP Inspection
MOCK DRILL BOP
TEED Inspection
BOP Inspection
Training deficiency
BOP Pressure test
Mast Inspection
MSO Appointment
Incident Minor
Training IWCF
Training Matrix
BOP RAM
BOP Inspection
PSV Calibration
SOP Awarness
BOP drill
SOP BOP
BOP COC
8
9
10
11
12
13
14
15
16
17
18
19
2
2
6
6
10
11
12
13
14
15
16
17
18
19
20
21
22
5
6
10
11
12
13
14
15
16
17
18
19
20
21
22
D. Charted hired WOR: CH-7 (Audit date: 09.05.2022)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
10.
11.
12.
13.
14.
15.
16.
17.
18.
18.
19.
20.
21.
21.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
F. Departmental workover rig: DM-1 (Audit date: 11.05.2022)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
10.
11.
12.
13.
14.
15.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
25.
26.
27.
28.
G. Departmental Workover rig M-1 (Audit date: 12.05.2022)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
25.
26.
27.
28.
29.
9
9
10
18
12
13
14
15
16
17
19
20
21
21
2
2
10
11
12
13
14
15
16
17
18
19
20
(B) Drilling Rig: E-2000-6 Audit
#
1
2
6
7
10
11
12
13
14
15
16
17
18
19
20
20
6
7
10
11
13
14
15
S.No
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
24.
25.
26.
27.
28.
29.
30.
31.
32.
32.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
1.
2.
3.
4.
5.
6.
7.
8.
9.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
1
1
6
7
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
A. Departmental Drilling Rig: RD#20-1 with O&M manpower (Audit date: 11.07.2022)
Drilling Rig, RD#20-1
was commissioned at
Raniganj, CBM project
of GEECL. Detail of the
Rig is: Drilling capacity
1600 m with 4 ½” drill
pipe, Pull back capacity
120000 lbs., Engine
power 745 HP and Mast
height is 55 feet. Last
TPI was conducted on
17.05.2022 (Stability
test). It is presently
deployed at Raniganj
(South), Well No: 41 for
Workover job.
1
2
6
6
10
11
12
13
14
15
16
17
18
1.
1.
2.
3.
4.
5.
6.
7.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
5
6
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
6
6
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
S.No
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
20.
21.
22.
23.
24.
S.No
1.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
1.
2.
3.
4.
5.
6.
7.
8.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
20.
21.
22.
23.
24.
Chartered hired
Workover Rig GTC-100-
VII was presently
deployed at Well:NDN#71
having 3 cluster wells.
1.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
#
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
14.
15.
16.
17.
18.
19.
20.
21.
E. Chartered hired DR: GTC-200#1 (Audit date: 23.08.2022)
1.
2.
3.
4.
5.
6.
7.
8.
9.
9.
10.
11.
12.
13.
14.
14.
15.
16.
17.
18.
19.
20.
21.
21.
22.
1.
2.
3.
4.
5.
6.
7.
8.
9.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
SN
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
18.
19.
20.
21.
22.
23.
24.
25.
25.
26.
27.
28.
29.
30.
31.
32.
33.
(A) Workover Rig : CX-XJ-500 (Chartered Hired) (Well No. P-10)
S. No
1.
2.
3.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
SN
1.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
17.
18.
19.
20.
21.
22.
23.
24.
24.
25.
26.
27.
28.
29.
30.
31.
S. No
1.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
4
4
5
6
9
10
11
12
13
14
15
16
17
18
3
4
7
8
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
3
4
6
7
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
3
3
8
9
10
11
12
13
14
15
16
17
19
20
21
22
2
3
10
11
12
13
14
15
16
17
18
19
20
21
22
B. Departmental WOR(O&M): CW # 50-X (Audit date: 28.09.2022)
1
2
8
9
10
11
12
13
14
15
16
17
18
19
20
7
7
10
11
12
13
14
16
17
18
#
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
A. Workover rig
ROM-50-II
#
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
12.
13.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
C. Workover Rig: John-
50-V (Contractual)
1.
2.
3.
4.
5.
6.
7.
8.
9.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
#
1. 1
2. 2
3. 3
4. 4
5. 5
6. 6
7. 7
8. 8
9. 15
10. 9
11. 10
12. 11
13. 12
14. 13
15. 14
16. 15
17. 16
18. 17
19. 18
20. 19
21. 20
22. 21
23. 22
24. 23
25. 24
26. 25
E. Workover Rig:
ROM-50-1
(Departmental-
Manpower Contract)
#
1.
2.
3.
4.
5.
6.
7.
8.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
F. Workover Rig:
Aakash-XVI
(Contractual)
#
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
7
8
10
11
12
13
14
15
16
17
17
5
5
10
11
12
13
14
15
16
17
18
18
19
20
B. Chartered hired WOR: SKP 150-1 (Audit date: 08.09.2021)
2
3
8
8
10
11
12
13
14
15
16
17
19
20
21
22
C. Chartered hired WOR: SKP 135-III (Audit date: 07.09.2021)
1
2
4
4
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
1.
2.
3.
4.
5.
6.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
15.
16.
17.
18.
19.
20.
21.
22.
23.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
D. Workover rig Sitaram-100-01 (Audit Date: 15.12.2021)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
13.
14.
15.
16.
17.
18.
19.
1.
2.
3.
4.
5.
6.
7.
8.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
1
1
7
8
10
11
11
12
13
14
15
16
17
18
19
20
21
A. Chartered hired WOR: Akash-50 XIII (Audit date: 28.02.2022)
6
7
10
11
12
13
B. Chartered hired WOR: DR#2 (Audit date: 02.03.2022)
4
5
10
10
11
12
13
14
15
16
17
3
4
10
11
12
13
14
15
16
17
18
19
20
21
22
23
23
24
25
26
27
D. Chartered Hired Workover Rig: REPL#12 (Audit date: 01.03.2022)
3
3
7
8
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
#
1
3
4
10
11
12
13
14
15
16
17
18
19
20
21
21
22
23
24
25
26
27
observation
Drill deficiencies:
a) BOP trip drill was found not conducted in
all the scenarios as per the report generated
(conducted d/p against BOP only).
b) Record of only few BOP drills were found
available; only 4 in number.
Break out tong pull line was not secured with three
number of clamps. It was also an observation during
previous ESA conducted during 2018.
Training deficiencies:
a. MVT was due for 11 regular staff.
b. Electrical supervisory licence covering mining
installation was not available for electrical competent
person.
c. Training needs were not identified as defined in
OISD-STD-176.
Training Deficiencies:
a. MVT training is due for 2/27 regular staff and 6/15
contractual staff.
b. Training needs were not identified as defined in
OISD-STD-176.
Pressure test and function test deficiencies:
a. FOSV, IBOP, Kelly cock were not found tested in
BOP pressure test report.
b. Function test was not carried alternately from
remote panel & main control unit.
Observations
Observations
(a) Level III derrick inspection was pending since
21/12/2021. Last inspection was done in
21/12/2019.
(a) There was no check list for Rig mast up and rig
mast down procedure.
Various SOPs are still missing like for rig mast down
and rig mast up process, SOP for controlling blow
out when there is no BOP or X-Mas tree on well etc.
Work Instructions to be displayed in trilingual format
at all the designated locations.
(a) There was no check list for Rig mast up and rig
mast down procedure.
Various SOPs are still missing like for rig mast down
and rig mast up process, SOP for controlling blow
out when there is no BOP or X-Mas tree on well etc.
Observations
(a) There was no check list for Rig mast up and rig
mast down procedure.
Various SOPs are still missing like for rig mast down
and rig mast up process, SOP for controlling blow
out when there is no BOP or X-Mas tree on well etc.
Observations
(a) There was no check list for Rig mast up and rig
mast down procedure.
Various SOPs are still missing like for rig mast down
and rig mast up process, SOP for controlling blow
out when there is no BOP or X-Mas tree on well etc.
Observations
Counterweights of the power tongs were hanging
unsafely around cellar pit working area below the
substructure. (Unsafe condition)
The well was under simulation for flow.
a) The cellar pit was filled with water and any of the
wellheads for annulus monitoring was not visible.
The Bull line was not stacked properly and also not
lubricated and covered.
Audit Observations
All shifts are not being monitored by Organization’s
competent persons/ officials during each working
shifts, Only one Installation Manager (IM) and two
ONGC shift Coordinator are posted at present
(i) SOP for N/UP and N/DN of BOP and X-MAS tree
not available.
(ii) No gap analysis was done
Observations
Observations
(i) Presently two firewater pumps are provided
having capacity of 171 m3/hr. and 400 m3/hr.
respectively.
Observations
Observation
1 (Audit date:14/07/2022)
Observation
Observations
Observations
Observations
Trip drills were not being done weekly with both the
shifts. Dates of last two drills were 14/07/2022 and
22/08/2022.
Observations
5-yearly major inspection record of Accumulator unit
(NOV Sara, L080 M6 FA 25F; Year of
manufacture:2011 having 1 Remote panel) being
used was not available.
Drill deficiencies:
a) Drills as mentioned as per ERP & Bridging
document viz. Cyclone, Snake bite, Flood were
found not conducted.
b) Complete drill scenario and action taken was
not mentioned in the drill report. Shortcomings of the
drill to be mentioned for improvement (Drill report
dated 8.8.2022).
Observations
Drill deficiencies:
a) Drills mentioned as per ERP document viz.
Cyclone, Snake bite, Flood etc. were found not
conducted. Only fire & evacuation (stretcher) drill
were being carried out.
Observations
FAFFE system
Observations
Air compressor:
Audit Observation
Air compressor:
kover rig CW-100-VIII (Departmental Rig), ( Well No.KMP#20) Audit Date : 31.08.2022
Audit Observation
Audit Observation
Air compressor:
Observations
Drill deficiencies:
a) Stretcher drill, fall from height are some of the
scenarios identified in the ERP; however, no mock
drill has been carried out on these scenarios.
Observations
Drill deficiencies:
a) Shock treatment drill, stretcher drill, fall from
height are some of the scenarios identified in the
bridging document; however, no mock drill has been
carried out on these scenarios.
b) BOP trip drill was found not conducted in all the
scenarios as per report generated.
c) BOP Pit drill was not conducted.
Observations
Drill deficiencies:
a) Oil spillage and Gas leakage are some of
scenarios identified in bridging document; however,
no mock drill has been carried out on these
scenarios.
b) No drill was found conducted when there was
no BOP in the wellhead.
Function test discrepancies,
Observations
Observations
Drill deficiencies:
a) Oil spillage, Gas leakage and blow out during
logging are some of scenarios identified in bridging
document; however, no mock drill has been carried
out on these scenarios.
b) No drill was found conducted when there was no
BOP/ X-mast tree in the wellhead.
Observation
Test flow line from well to test tank was not hydro-
tested to the pressure likely to be encountered in the
surface during production testing of the well.
Observation
Observations
Initial Pressure test record at Rated Working
Pressure of Well Control Equipment at this location
was not available.
Observations
Pressure test record at Rated Working Pressure on
initial installation of Well Control Equipment was not
available.
Observations
Observations
Observations
Observations
Observations
Observations
Category III derrick inspection will be due on
17/12/2021. Last inspection was done in
17/12/2019.
Recertification record of Choke manifold used was
not available.
Observations
No approved Safety Critical Equipment (SCE) list
was available.
Observations
i) Well control training of IM (Sh. Devraj Hansdah)
is due since 19.10.2021.
ii) 2 SICs (Sh. M.V. Shah, H.M. Patel) were not
having valid & 2 SICs/ Asstt. DIC (Sh. V.B. Sharma,
B.K. Rana) were not having appropriate level of Well
control training certificates.
(i) BOP stack was not Function tested for ‘close’ &
‘open’ separately; it’s not clear from the format used
during testing.
Observations
Safety related trainings (viz. HAZOP, QRA, Safety
Management System etc.) for appropriate level were
also not identified.
Observations
Safety related trainings (viz. HAZOP, QRA, Safety
Management System etc.) for appropriate level were
also not identified.
Observations
Observations
All ONGC representatives / co-ordinator were not
having valid Well control training certificates.
Recommendations
Recommendations
Recommendations
Well servicing operation shall be done under the
direct supervision of a competent person
authorized for the purpose. (refer regulation 77,
OMR 2017).
Recommendations
i) Training matrix should be made for all the
rig crews and kept available at rig for both on
duty and off duty rig crew members.
ii) It should be ensured that all workers and
workers transferred to new jobs receive
adequate training in safety, firefighting and
maintain a detailed record (Refer: Regulation
23f, OMR-2017).
Further, all persons employed in a mine below
the supervisory level should have undergone
MVT training as per Mines Vocational Training
Rules, 1966.
iii) All the key operational personnel should
have valid Well control training certificate (of
appropriate level) from IWCF/ IADC accredited
well control training centre (Refer: Cl 8.1,
OISD-RP-174).
Recommendations
(i) Additional pump of similar capacity i.e. 400
m3/hr. should be provided. (refer clause 5.2 (4)
of OISD-STD-189)
(ii) Auto cut-in /cut-off facility should be
provided for jockey pumps. (refer clause 5.2
(15) of OISD-STD-189)
(iii) The fire assessment study should be
carried out for extend of fire proofing around
equipment and structure & firewater
requirement as per OISD-STD-164 and OISD-
STD-189.
No. 25
Recommendations
i) Updated training matrix should be kept
available at rig for both on duty and off duty rig
crew members.
ii) All the key operational personnel should
have valid Well control training certificate (of
appropriate level) from IWCF/ IADC accredited
well control training centre (Refer: Cl 8.1,
OISD-RP-174).
iii) Key operational personnel should have
some basic trainings as mentioned in OISD-
STD-176.
Recommendation
BOP function/ pressure test report/ format
should be in line as defined in OISD-RP-174 or
API-STD-53.
It is recommended to use high pressure testing
unit with pressure chart recorder for pressure
testing [Refer: Clause 6.7.2(V) of OISD-RP-
174].
Full particulars of all tests of BOP assembly
shall be recorded in the daily report (Refer:
Clause 6.3(ii) of OISD-RP-243).
Recommendation
BOP function/ pressure test report/ format
should be in line as defined in OISD-RP-174 or
API-STD-53.
It is recommended to use high pressure testing
unit with pressure chart recorder for pressure
testing [Refer: Clause 6.7.2(V) of OISD-RP-
174].
Full particulars of all tests of BOP assembly
shall be recorded in the daily report (Refer:
Clause 6.3(ii) of OISD-RP-243).
Recommendations
Major inspection of BOP control unit shall be
carried out after every 5 years by OEM/ OEM
authorized facility or an API 16D approved agency
as per Cl No. 6 of API 16D [Refer: Cl 6.2(IV),
OISD-RP-174].
Major inspection of choke, kill manifold shall be
carried out after every 5 years, preferably by OEM
or OEM authorized repair facility (Refer: Clause
6.2.IV, OISD-RP-174).
Recommendations
Recommendations
Recommendations
Major inspection of BOP Accumulator unit shall be
carried out after every 5 years, preferably by OEM
or OEM authorized repair facility or by an API 16D
approved facility for BOP control unit (Refer:
Clause 6.2.IV.C, OISD-RP-174).
Recommendations
Recommendations
a) Checking of tightening of guy ropes shall be
included in PWC Refer Clause 6.9.3 of OISD-GDN-
192)
Recommendation
a. Checking of tightening of guy ropes shall be
included in PWOC(Refer Clause 6.9.3 for Guy
derrick of OISD-GDN-192)
b. Performance test shall be carried out for fire
water pump (Refer Clause No.6.0(c) of OISD-STD-
119 & NFPA 25 of 2017)
c. Prior to undertaking SIMOPS, job safety
analysis should be carried out by the person
responsible for SIMOPS (company man / rig
manager, as the case may be) with all agencies
associated with SIMOPS, to ensure that all the
hazards related to the proposed operations are
identified, assessed, and determined to have the
risk as low as reasonably practicable. (Refer
Clause 5.1.3 of OISD-GDN-186)
36)
Recommendations
Recommendations
Recommendations
Frequency of inspection:
Level I – Daily & weekly.
Recommendations
Recommendations
Drill, while there is no BOP/ X-mast tree in the
wellhead to be conducted as per High-Level
Investigation committee report on incident at
Baghjan # 5.
Recommendation
Recommendation
(a) Work permit should be issued for working at
height as per OISD-STD-105.
Recommendations
Recommendations
Initial pressure test of blowout preventer stack,
manifold, valve etc. should be carried out at the
rated working pressure of the preventer stack or
well head whichever is lower and record of the test
to be retained. Initial pressure test is defined as
those that should be performed on location before
the equipment is put into operational service. Refer:
OISD-RP-174, Clause 6.7.2.(X).
Recommendations
Initial pressure test of blowout preventer stack,
manifold, valve etc. should be carried out at the
rated working pressure of the preventer stack or
well head whichever is lower. Initial pressure test is
defined as those that should be performed on
location before the equipment is put into
operational service. Refer: OISD-RP-174, Clause
6.7.2(X).
Recommendations
Recommendations
Recommendations
As per clause 4.3 of OISD-GDN-202 and clause
6.3 of API 4G, Category III inspection to be done
every 2 years.
It is recommended to follow Annexure VIII of OISD-
RP-174 for pressure test of BOP.
Recommendations
As per clause 6.3 of API 4G Category III inspection
to be done every 2 years.
Major inspection of choke manifold shall be carried
out after every 5 years, preferably by OEM or OEM
authorized repair facility or by an API 16C & 6A
approved facility for choke manifold & its
accessories (Refer: Clause 6.2.IV, OISD-RP-174).
Recommendations
All the key operational personnel should have valid
Well control training certificate (of appropriate level)
from IWCF/ IADC accredited well control training
centre (Refer: Cl 8.1, OISD-RP-174).