Professional Documents
Culture Documents
Example2.2: The water supply for a city is pumped from wells to a distribution reservoir. The
estimated hourly water requirements for the maximum day are indicated below. If the pumps
are to operate at a uniform rate, what distribution reservoir capacity is required?
Column 4 is obtained by subtracting the flow(supply) from the demand (column 2). At the time
when demand is less than the supply, reservoir requirement is zero. The required reservoir
capacity will be equal to the sum of the hourly requirements from storage. This comes out to
be 2324.7l m3. The graphical method of determining the reservoir capacity is also shown in
figure.
Example2.3: Incoming monthly flow during the critical period (1973-1975) for the Catalan
dam are given in the nearby table. Fthe ind active volume of the reservoir for 85% regulation using
SPA.
Water Resources Engineering II(CIV472)
Month St Dt Month St Dt
Jan-73 40 250 Jul-74 200 250
Feb-73 250 250 Aug-74 180 250
Mar-73 300 250 Sep-74 167 250
Apr-73 350 250 Oct-74 155 250
May-73 500 250 Nov-74 146 250
Jun-73 550 250 Dec-74 195 250
Jul-73 300 250 Jan-75 165 250
Aug-73 250 250 Feb-75 188 250
Sep-73 220 250 Mar-75 650 250
Oct-73 210 250 Apr-75 500 250
Nov-73 205 250 May-75 463 250
Dec-73 160 250 Jun-75 300 250
Jan-74 140 250 Jul-75 185 250
Feb-74 250 250 Aug-75 190 250
Mar-74 420 250 Sep-75 200 250
Apr-74 650 250 Oct-75 200 250
May-74 550 250 Nov-75 260 250
Jun-74 350 250 Dec-75 550 250
Vt = Dt – St + Vt-1; If positive
Vt = 0, Otherwise
Month St Dt Dt-St Vt
Jan-73 40 250 210 210
Feb-73 250 250 0 210
Mar-73 300 250 -50 160
Apr-73 350 250 -100 60
May-73 500 250 -250 0
Jun-73 550 250 -300 0
Jul-73 300 250 -50 0
Aug-73 250 250 0 0
Sep-73 220 250 30 30
Oct-73 210 250 40 70
Nov-73 205 250 45 115
Dec-73 160 250 90 205
Jan-74 140 250 110 315
Feb-74 250 250 0 315
Water Resources Engineering II(CIV472)
Time(month)
Example 2.4: The inflow yield and the release values of a storage reservoir are tabulated in
Table in terms of 106 m3. Determine the required active storage capacity using sequent-peak
analysis.
Water Resources Engineering II(CIV472)
t Dt St t Dt St
1 40 35 11 40 76
2 40 50 12 40 55
3 40 60 13 40 40
4 40 35 14 40 30
5 40 25 15 40 25
6 40 30 16 40 20
7 40 20 17 40 35
8 40 13 18 40 50
9 40 27 19 40 60
10 40 55
The analytical solution is presented in the following table. The graphical solution is also given
in the figure. As it can be seen from the table and the figure, the required storage is 90x106m3.
Therfore, the capacity of the reservoir is the diffference between the initial peak and the
coresponding lowest trough i.e.25x106m3+65x106m3= 90x106m3
Example2.5: the monthly inflows at the site of proposed reservoirs during a critical flow period
are given in the table. In addition, the monthly evaporation loss estimates and the monthly
amounts of net precipitation on the main pool level are given. A monthly uniform mandatory
release(DR) of 0.13*106m3/month is needed for downstream requirements. The monthly water
demand to be met from the active storage capacity are also listed in Table below. Fined the
required active storage capacity of the reservoir by an operational study. For the capacity that
you have found, calculate the monthly reservoir contents and spills from the reservoirs, if any.
Solution
Water Resources Engineering II(CIV472)
The available data are tabulated in columns (1) to (6) in table. Inflow (St), demand (Dt), rainfall
(Pt), evaporation (E) and downstream requirements (Mt) are given in 106 m3/month. The
required monthly storages, V , are computed in column (7) by
V = St – Dt + Pt – Mt – Et
The required total storage, Vt, is obtained by summing the values in column (7) as 33.38 x 106
m3. Column (8) gives the monthly contents of reservoir which is computed by:
Vt = Vt-1 + St – Dt + Pt – Mt – Et
where Vt is the volume of water stored in the reservoir at the end of month. The computation
of monthly reservoir contents starts from December because the reservoir must be emptied at
the end of November which is also the end of critical dry period. Thus, the reservoir content at
the end of November is zero. The monthly reservoir content cannot be more than 33.38x106
m3. So, during the months of April and May, the inflow which is in excess of the reservoir
capacity must be spilled. This problem is a very simplified example of an operation study.
More correctly the evaporation and precipitation amounts must be computed for actual levels
of reservoir using area-volume-elevation curves.
Example 2.6: A reservoir has a drainage area of 100 km2. Mean annual inflow to the reservoir
is expected to be 80 x 106 m3. Using the Brune trap efficiency curve given in Figure, plot the
variation of the reservoir capacity with respect to time. Assume that the initial reservoir
capacity is 40 x 106 m3. Determine the expected time for which 50% of the initial capacity is
reduced by sediment accumulation.
Water Resources Engineering II(CIV472)
Solution
With the information given, annual sediment yield is obtained using the following formula.
Y = 1906.26 Ad
0.953
Example 2.7: Determine the capacity of storage reservoir with given monthly flows using mass
curve analysis. Assume yield is equal to average flow. Also find the monthly contents of the
reservoir and monthly changes in the reservoir volume.
Solution
Water Resources Engineering II(CIV472)
Graphical solution