RENCANA KERJA HARIAN QUALITY CONTROL

PROYEK TOL TRANS SUMATERA RUAS PEKANBARU - PADANG


SEKSI PADANG - SICINCIN

Hari / Tanggal : Rabu/ 08 November 2023

No ITEM PEKERJAAN LOKASI PIC KETERANGAN


1 - Trial blending base-a Stone crusher BAS (wempi) depan lantas. Suharno
sta 13+118; Sta 15+700; Sta 15+867; Sta
- Pengecekan hasil pekerjaan struktur
2, 35+400 Budi
- Checklist Material Batu 1-2 & 2-3 PT. RMB Quary Nurbudi Alahan Panjang,
Uji kuat tekan sampel grouting umur 28 hari
- Laboratorium Pengujian PT. Hutama Karya
Estrong G50 & Estrong CG 300
Infrastruktur
3, - Uji kuat tekan Shotcrete Merki
- Destructive Test Pagar Rumija Sta 24+584
- Uji kuat tekan Shotcrete Sta 26+900L ,27+850 R
- Pengujian Kuat Tekan Beton
- Pengujian Kuat Lentur Beton Laboratorium Pengujian PT. Hutama Karya
4, Jumadino
- Pembuatan sampel base a Infrastruktur
- Pengujian Granular Backfill BGM
Sta 1+407, 5-1+700 L1, Vol: 324 m3, BP 10
- Rigid Pavement
5
Statiika Kayu Tanam Brili
Sta 25+020-25+290R2, Vol:
- Rigid Manual
300m3, BP HKsis 01
- Pengujian Kuat Tekan Beton
HKSIS
Laboratorium Pengujian PT. Hutama Karya
6 Nindya Beton Hendra
Infrastruktur
Statika Mitra Sarana
ABP
Sta 35+425 - 35+625 R/L ; Sta 35+625 -
- Sandcone test 35+675 R/L; Sta 35+700 - 35+850 R/L; Sta
7 34+375 - 34+500 R/L Dedy
- Base A Sta 2+700-2+775 L (Tarok city)
- Sandcone GBF Box Culvert Sta 1+300 (akses tarok city)
- Sandcone GBF ABT1 Sta 35+850
Sta 6+650-6+865 L; Sta 10+800 - 10+900 L;
- Base A
6+650 -6+865 L
8 - TSG Sta 13+350 - 13+450 R Andri
- caping layer Sta 11+025 - 11+100 L
- Sandcone dan Proofrolling (TSG) Sta 13+350-13+450 R
STA 20+000 - 20+100 L/R; STA 21+450 -
21+550 R; STA 16+325 - 16+400 L/R; STA
- Sand Cone Test (Trass) 16+800 - 16+925 L/R; STA 16+950 - 17+025
9
L/R; STA 17+025 - 17+100 L/R; STA 17+150 - Fitriadi
17+325 L/R; STA 17+850 - 17+950 L/R
- Capping Layer Sta 19+275-19+525 L3
Box Traffic STA 16+414
- GBF
Box Traffic STA 17+914