WORK ORDER / JOB PENDING

ENGINEERING - PRODUKSI
PT. CAHAYA RIAU MANDIRI - DAS
2022
SITE : PT. CRM-DAS Overburden Coal Mining
DATE : 06-07 DES 2022 PLAN : 355,639 BCM 49,093 TON
TIME (From-Until) : 18.00 - 09.00 WIB MTD : 44,757 BCM 7,799.00 TON
PIT / BLOCK : CRM / UTARA PER DAY : 11,957 BCM 1,588 TON
CLASSIFICATION : Pit KURANG : 310,882 BCM 41,294 TON
HALAMAN : 1
COMMENT AFTER PROGRESS

Ex-22 vs 5 DT loading OB RL+90,


dumping ke OPD KPL, jarak 1300 meter
Ex-80 vs 5 DT loading OB RL+50,
dumping ke OPD KPL, jarak 1400
meter (P1)

Ex-20 vs 5 DT loading OB ekspose


Akses Jalan
seam B, dumping ke OPD KPL, jarak

Akses Jalan

Ex-13 vs 6 DT loading OB RL+90,


dumping ke OPD KPL, jarak 1600 meter

Pita boundary LOM

Ex-11 vs 6 DT loading OB RL+90, dumping


ke OPD KPL, jarak 1700 meter

SERAH TERIMA INSTRUKSI PELAKSANAAN PEKERJAAN SERAH TERIMA LAPORAN PELAKSANAAN PEKERJAAN
Dibuat Oleh, Diketahui Oleh, Diterima Oleh, Dilaporkan Oleh, Diterima Oleh, Diketahui Oleh,

Afri. S Riris.HH Afri. S Riris.HH


Mine Plan Engineering Suptend Product. SPV Product. SPV Mine Plan Engineering Suptend
WORK ORDER / JOB PENDING
ENGINEERING - PRODUKSI
PT. CAHAYA RIAU MANDIRI - DAS
2020
SITE : PT. CRM-DAS Overburden Coal Mining
DATE : 06-07 DES 2022 PLAN : 355,639 BCM 49,093 TON
TIME (From-Until) : 18.00 - 09.00 WIB MTD : 44,757 BCM 7,799.00 TON
PIT / BLOCK : CRM / UTARA PER DAY : 11,957 BCM 1,588 TON
CLASSIFICATION : Pit KURANG : 310,882 BCM 41,294 TON
HALAMAN : 2
COMMENT AFTER PROGRESS

Akses Jalan

Arah Aliran

1x PC 200/DZ continue pembentukan


bench counterweight sleding low wall

Ex-15 Coal getting seam B VS 6 TC,


loading satu layer, jarak 3400 meter
WORK ORDER / JOB PENDING
ENGINEERING - PRODUKSI
PT. CAHAYA RIAU MANDIRI - DAS
2022
SITE : PT. CRM-DAS Overburden Coal Mining
DATE : 06-07 DES 2022 PLAN : 355,639 BCM 49,093 TON
TIME (From-Until) : 18.00 - 09.00 WIB MTD : 44,757 BCM 7,799.00 TON
PIT / BLOCK : CRM / UTARA PER DAY : 11,957 BCM 1,588 TON
CLASSIFICATION : DSP KURANG : 310,882 BCM 41,294 TON
HALAMAN : 2
COMMENT AFTER PROGRESS

Peninggian area dumpingan

Jangan di dumping

Continue dumping desak lumpuran void


WORK ORDER / JOB PENDING
ENGINEERING - PRODUKSI
PT. CAHAYA RIAU MANDIRI - DAS
2022
SITE : PT. CRM-DAS Overburden Coal Mining
DATE : 06-07 DES 2022 PLAN : 355,639 BCM 49,093 TON
TIME (From-Until) : 18.00 - 09.00 WIB MTD : 44,757 BCM 7,799.00 TON
PIT / BLOCK : CRM / UTARA PER DAY : 11,957 BCM 1,588 TON
CLASSIFICATION : General KURANG : 310,882 BCM 41,294 TON
HALAMAN : 3
COMMENT AFTER PROGRESS

1x PC 200/DZ general pembentukan


box control
tanggul di jalan menuju sump dan di
upayakan air tidak masuk kedalam Pit dan
jalan
Arahkan aliran air menuju box
control, agar air over flow dan
mengalir ke kanal DAS

Arah aliran air

Paritan

1x PC 200/DZ general pembentukan


tanggul di badan jalan simpang lima
ketika hujan, untuk memblok dan
mengarahkan aliran air dari parkiran
menuju paritan yang sudah di bentuk