SKENARIO PELAKSANAAN

REKONSTRUKSI JALAN SAGEA – PATANI 2/UMYC/PN

0+000 6+500 13+300 19+800 24+900


LPA LPA
AC -WC AC -BC AC -BC
AC - WC AC - BC

- LPA, Target Selesai 30 Nov 2019

- AC-BC Target Selesai ,Rabu 30 Okt 2019

- AC -WC , 31 Okt 2019 s/d 9 Nov 2019 - Perbaikan LPA , 31 Okt 2019 s/d 9 Nov 2019
5 DT Kecil 10 DT Kecil
3317.6 ton
± 331.8 ton/hari
- AC -BC , 10 Nov 2019 s/d 24 Nov 2019
5 DT Kecil , 5206.08 ton
± 371.8629 ton/hari
- AC -BC , 25 Nov 2019 s/d 10 Des 2019
- AC - WC , 11 Des 2019 s/d 21 Des 2019 3904.56 ton
3470.72 ton ± 260.3 ton/hari
± 347.1 ton/hari